Unifier - P6 EPPM

<Insert Picture Here> Integration

Nnogge Lovis,PMP® Eng. Ali AlSaffar


Agenda
• Gateway
• P6 connection to Gateway
• Unifier connection to Gateway
• Integration area for Musanada
• Activity List in P6  Activity Sheet in Unifier
• Business Process in Unifier  Update actual schedule date
in P6.
• Linking BP in Unifier  Update Actual Schedule Date in P6
• Cost Code in Cost Sheet in Unifier  CBS in P6 Activity
Gateway
Gateway works by supporting bi-directional data between P6 and Unifier

Integration Prerequisites:
 Only existing projects in P6 and Unifier can be integrated.
 Projects which need to be linked must have the same;
- Project ID
- Project Name

P6 EPPM Gateway Test Unifier Staging


Development Environment Environment
Environment
P6 connection to Gateway
Unifier connection to Gateway
Integration Area for Musanada

• Area 1: Dates (Design Phase)

• Activity list in P6  Activity Sheet in Unifier


• Business Process in Unifier  Update Actual Schedule Date in P6

• Area 2: Cost Code, Progress, Payment (Design & Construction Phases)


• Cost Code in Cost Sheet in Unifier  CBS in P6 Activity
• Payment for Contract Line Items  Activity Progress
Activity list in P6  Activity Sheet in
Unifier
Business Process in Unifier  Update
Actual Schedule Date in P6
Business process / Schedule interaction

Now
Business
Process

<Actual Finish>
Linking BP in Unifier  Update Actual
Schedule Date in P6
Cost Code in Cost Sheet in Unifier 
CBS in P6 Activity
Q&A