Professional Documents
Culture Documents
Transportation Problem NWC
Transportation Problem NWC
Transportation Problem NWC
MANUFACTURING MANAGEMENT
TRANSPORTATION MODEL
Step 1.
Balancing the given problem. Balancing means check whether sum of availability constraints
must be equals to sum of requirement constraints.
That Σ bi = Σd j . Once they are equal, go to step two. If not by opening a Dummy row or
Dummy column balance the problem.
The cost coefficients of dummy cells are zero. If Σbi is greater than Σd j , then open a dummy
column, whose requirement constraint is equals to Σbi – Σd j and the cost coefficient of the cells
are zeros.
In case if Σd j is greater than Σbi , then open a dummy row, whose availability constraint will be
equals to Σd j – Σbi and the cost coefficient of the cells are zeros.
Once the balancing is over, then go to second step. Remember while solving general linear
programming problem to convert an inequality into an equation, we add (for maximization
problem) a slack variable.
In transportation problem, the dummy row or dummy column, exactly similar to a slack variable.
Basic feasible solution can be obtained by
three methods
(a) Stepping
Stone Method.
(a) North - west
corner method.
(c) Vogel's
Approximation
Method, generally
known as VAM. (b) Modified Distribution
Method, generally known
as MODI method.
NORTH WEST CORNER METHOD
(i) Balance the problem. That is see whether Σbi = Σd j . If not open a dummy column or dummy
row as the case may be and balance the problem.
(ii) Start from the left hand side top corner or cell and make allocations depending on the
availability and requirement constraint. If the availability constraint is less than the requirement
constraint, then for that cell make allocation in units which is equal to the availability constraint. In
general, verify which is the smallest among the availability and requirement and allocate the
smallest one to the cell under question. Then proceed allocating either sidewise or downward to
satisfy the rim requirement. Continue this until all the allocations are over.
(iii) Once all the allocations are over, i.e., both rim requirement (column and row i.e., availability and
requirement constraints) are satisfied, write allocations and calculate the cost of transportation.
Problem
• Four factories A, B,C and D manufactures Fabrics and
are located in different regions.
• Factory A produces 10 meters of fabric, B produces 8
meters of fabric, C produces 5 meters of fabric and D
produces 6 meters of fabric. The fabric has demand in
Three markets X, Y and Z.
• The demand of market X is 7 meters, that of market Y is
12 meters and the demand of market Z is 5 meters.
• The transportation cost of one meter of fabric from each
factory to market is given in the matrix below.
• Find the Optimal Solution for least cost transportation cost
Matrix
Balance demand and availability
A 4 3 2 0 10
B 5 6 1 0 8
C 6 4 3 0 5
D 3 5 4 0 6
Requirement in Meters 7 12 5 5 29
Iteration 1
Cost in Rs. per meter Markets.
A 7 4 3 2 0 10
3
B 5 6 1 0 8
C 6 4 3 0 5
D 3 5 4 0 6
Requirement in Meters 7 12 5 5 29
0
Iteration 2
Cost in Rs. per meter Markets.
Availability in
Factories. NWC Y Z Dummy
Meters
A 3 3 2 0 3
0
B 6 1 0 8
C 4 3 0 5
D 5 4 0 6
Requirement in Meters 12 5 5 22
9
Iteration 3
Cost in Rs. per meter Markets.
Availability in
Factories. NWC Y Z Dummy
Meters
B 8 6 1 0 8
0
C 4 3 0 5
D 5 4 0 6
Requirement in Meters 9 5 5 19
1
Iteration 4
Cost in Rs. per meter Markets.
Availability
Factories. NWC Y Z Dummy
in Meters
C 1 4 3 0 5
4
D 5 4 0 6
Requirement in Meters 1 5 5 11
0
Iteration 5
Cost in Rs. per meter Markets.
Availability in
Factories. NWC Z Dummy
Meters
C 4 3 0 4
0
D 4 0 6
Requirement in Meters 5 5 10
1
Iteration 6
Cost in Rs. per meter Markets.
Availability in
Factories. NWC Z Dummy
Meters
D 1 4 0 6
5
Requirement in Meters 1 5 6
0
Iteration 7
D 5 0 5
0
Requirement in Meters 5 5
0
Allocated
Factories. X Y Z Dummy
A 4*7 3*3 2 0
B 5 6*8 4*1 0
C 6 4 3*4 0
D 3 5 4*1 0*5
Feasible solution NWC
From To Units in meters Cost in Rs Total
A X 7 4 28
A Y 3 3 9
B Y 8 6 48
B Z 1 4 4
C Z 4 3 12
D Z 1 4 4
D Dummy 5 0 0
Total 105