Professional Documents
Culture Documents
Construction Contract & Law (Ceng 6107)
Construction Contract & Law (Ceng 6107)
Construction Contract & Law (Ceng 6107)
Contractor’s Obligation:
Its Regulation & Management under the MDB-
FIDIC (2006) & the PPA (2011)Conditions of
Construction Contracts & the Applicable Laws
Instructor: ATO ZEWDU TEFERA WORKE
Presented by :
Legal Definition
- corporate entity
(Formed under proper licensing and registration)
- Contractor is LEGAL PERSON
Contractual Definition
- Contractually recognized after signing of contract
succeeding the fulfillment of legal definition off course
CHAPTER 4 - STATUS OF THE CONTRACTOR (CONTD)
b) Work Program
Used to monitor progress of works
Work program shall be realistic & the utmost way to fulfill requirements of the contract
Includes the following
• Duration of each activity and critical activities
• Resource allocation at each stage of work
• Proposed deployment of plant, equipment, labor, materials
• Proposed temporary works
• Time for inspections of works and required tests
• Projection of earned value at each months
• Nominated Subcontractor’s (if any)
• Drawings and Methods of construction
In Case of non compliance with the above Revised work Schedule
progress evaluation is conducted by comparing the original work plan to the up-to-date
status of the project.
CHAPTER 6: EXECUTION OBLIGATION (CONTD)
6.4 Subcontractor
- A Contractor, has legal autonomy
- undertakes part of the work from the main Contractor
Could be nominated – knowing to the employer & included in the contract
Appointed by the contractor – unknown to the employer
Submit all “as-built” documents and, design documents of permanent works (if any by the
contractor), operation and/or maintenance manuals (if any)
Complete environmental safety and protection works
Time for Completion = contract time + extension of time (if any)
CHAPTER 7: COMPLETION OBLIGATION (CONTD)
Test on Completion
Fail Pass
CHAPTER 7: COMPLETION OBLIGATION (CONTD)
• Ethiopian civil code, Article 3020 (2): states the evidence of the contract
to be where the contractor has undertaken the work to the knowledge of
the client or received an advance payment from the client.
New provisions under MDB FIDIC Condition of Contract
Notice of a claim (Clause 20.1), “If the Contractor fails to give notice of a claim within
such period of 28 days, the Time for Completion shall not be extended, the Contractor shall
not be entitled to additional payment, and the Employer shall be discharged from all liability
in connection with the claim.”
CHAPTER 9: COMPARATIVE ANALYSIS (CONTD)
Value Engineering (Clause 13.2 (c) ), “if this change results in a reduction in
the contract value of this part, the Engineer shall proceed in accordance
with Sub-Clause 3.5 [Determinations] to agree or determine a fee, which
shall be included in the Contract Price. This fee shall be half (50%) of the
difference between………….”
Post Completion Obligation, the Contractor will not be liable under the
contract after issuance of performance certificate. However, as per Article
3039 of Ethiopian civil code he will be liable for 10 years for any loss or
deterioration of the work as is due to a defect in its execution.
CHAPTER 10: CASE STUDY
Concluding remarks
• The Contract more or less include the required provision under the General
and Special condition of contract
• The Contractor performed his obligation as per the contract requirement
• The project progress - not satisfactory, for which he is required to submit
request for EOT for the delay recorded so far if he has justified delay
• Recommended the contractor to prepare realistic work program and
accelerate the work to catch up the slippage.
CHAPTER 11: CONCLUSIONS AND RECOMMENDATIONS
11.1 Conclusion
The Contractor has key role for the successful completion of the
project, therefore he is required to fulfill his obligations and strictly
follow all his contractual and legal responsibility.
11.2 Recommendation
Knowledge of construction contract and law is just like the backbone
of the construction project
It is recommended the course to be given in higher credit hour to
enable the young Engineer to understand the impact of
contractual obligations in the construction project.
THANK YOU