Professional Documents
Culture Documents
Lec - 15 & 16 - Project Management
Lec - 15 & 16 - Project Management
Lec- 15 & 16
Learning Objectives
• Discuss the behavioral aspects of projects in
terms of project personnel and the project
manager.
• Discuss the nature and importance of a work
breakdown structure in project management.
• Give a general description of PERT/CPM
techniques.
• Construct simple network diagrams.
Learning Objectives
• List the kinds of information that a PERT or
CPM analysis can provide.
• Activity Scheduling
• Analyze networks with deterministic times.
• Analyze networks with probabilistic times.
• Describe activity “crashing.
What is Project
• “A project is a set of activities with a defined start
point and a defined end state, which pursues a
defined goal and uses a defined set of resources”
Build C
C Done
Build D On time!
Ship
Work Quality
Human Resources Time
Communications Costs
Project Life Cycle
Project Management
• What are the tools?
– Gantt charts
– Work breakdown structure
– Network diagram
– Risk management
Gantt Chart
A popular tool for planning and scheduling simple projects,
and for initial planning for more complex projects
Graph or bar chart
Bars represent the time for each task
Bars also indicate status of tasks
Provides visual display of project schedule
Closely associated with PERT
Slack
amount of time an activity can be delayed without delaying the
project
Planning and Scheduling
Gantt Chart MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive materials
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Using Gantt Charts
• Positives
– Communicates the plan
– Easy to construct
– Readily understood
– Good for static environments
– Widely used
– Graphical interface for most project planning software
Using Gantt Charts
• Limitations
– Difficult to update manually
– Does not equate time and cost
– Does not help in optimizing resource allocation
– Tendency to be perceived as a ‘statement of reality’ or
certainty, whereas it is really a statement of ‘how it might
be done’, recognizing the uncertainty that managers in
projects have to deal with, the nature of estimating, the
quality of input information
Work Breakdown Structure
Project
Project XX
Level 1
Level 2
Level 3
Level 4
Work Breakdown Structure
PERT and CPM
Interview
Hire and
train
3
Project Network – Activity on Node
Order
furniture
Locate Furniture
2 setup
facilities
AON
1 6
Move in
Remodel
S 5 7
Hire and
Interview
train
3 4
AON Network for House Building Project
Lay Build
foundation house
Activity Number
2 4
Activity Time
2 3
Start 1 7
3 1
Finish work
Design house 3 5 6
and obtain
1 1 1
financing
Order &receive Select Select
materials paint carpet
Critical Path
Activity Network (Scheduling) Diagrams are used to determine Critical Path.
2 4
2 3
Start 1 7
3 1
3 5 6
1 1 1
A: 1-2-4-7
3 + 2 + 3 + 1 = 9 months Critical path
B: 1-2-5-6-7 Longest path through a
3 + 2 + 1 + 1 + 1 = 8 months network
C: 1-3-4-7
3 + 1 + 3 + 1 = 8 months
Minimum project
D: 1-3-5-6-7 completion time
3 + 1 + 1 + 1 + 1 = 7 months
Node Configuration
Activity Earliest Earliest
number start (ES) finish (EF)
1 0 3
3 0 3
• Forward pass
starts at beginning of CPM/PERT network to determine
earliest activity times
• Backward pass
Determines latest activity times by starting at the end of
CPM/PERT network and working forward
Time Estimates
• Deterministic
– Time estimates that are fairly certain
• Probabilistic
– Estimates of times that allow for variation
Example 1
6 weeks
Deterministic 4
time estimates rder e
O itur
Furn p
3 weeks
furn
setu
8 weeks 2
itur
Rem
ate s ode
e
c
Lo ilitie l
11 weeks Move in
fac
1 5 6
1 week
In n
te
vie r trai
4 weeks w and
e
Hi r 9 weeks
3
Example 1 Solution: Deterministic
Critical Path
P
at
h L
eng
th S
la
ck
(
w e
eks
)
1
-2
-3
-4
-5
-6 1
8 2
1
-2
-5
-6 2
0 0
1
-3
-5
-6 1
4 6
Step 2- Diagram the Network for
Cables By Us
Step 3 (a)- Add Deterministic Time Estimates
and Connected Paths
ES, EF Network
Forward Pass
LS, LF Network
Backward Pass
Calculating Slack
Project Evaluation and Review Technique
(PERT)
• Large complex engineering projects are usually planned using project
management systems that are based upon Project Evaluation and
Review Technique (PERT).
• The Critical Path Method uses single value deterministic estimates for
each activity duration - PERT assumes three duration estimates for
each activity (optimistic, most likely, pessimistic).
2 =(P– O) 2
36
where p=pessimistic activity time estimate
o=optimistic activity time estimate
Project Activity Variance
Variances of Each Path through the
Network
Calculating the Probability of Completing the
Project in Less Than a Specified Time
Example: Calculating the probability of
finishing the project in 48 weeks
Reducing Project Completion Time
10
6 b
a
2
f
5
9
c
4 e
d
Project Crashing Solution
1. Find the critical path:
a. Crash activity c one day for $300. Length of critical path in now 19 days.
b. Activity c cannot be crashed any more (only had 1 day available for
crashing).
c. Crash activity e one day for $600. Length of critical path is now 18 days
– same as path a-b-f.
d. Both paths are now critical. We must shorten both paths for further
improvement
Project Crashing Solution
4. Remaining activities for crashing and costs:
5. Analysis:
a) Should we crash f? f is on both paths, and crashing cost is
$800 per day.
b) Alternatively, we may crash b ($500/day) and e ($600/day) to
reduce 1 day. But the combined cost is $1100.
Project Crashing Solution
6. Crash f. Project duration is now 17 days.
7. Analysis: can we crash any more activities?
Cost is crash b is $500 and cost to crash e is
$600, added together ($1100) exceeds the
project daily cost of $1000.
8. Conclusion: no more crashing is feasible.
9. Summary:
Advantages of PERT
3
Limitations of PERT
on critical path
142 weeks
3
Project Management Software