Professional Documents
Culture Documents
Finishing. MATERIALS
Finishing. MATERIALS
Finishing. MATERIALS
Presented BY:
13.3 Lime
Lime for mortar for marking lime concrete shall be class B or C
conforming to IS 712, as specified in Section 4-Concrete.
13.4 Aggregates
Coarse and fine aggregates for cement concrete and granolithic
concrete shall conform to IS 383-1970, as specified in Section 4
Concrete.
MATERIALS
13.4.1 Aggregates for granolithic concrete shall consist of crushed
granite, basalt, trap or quartzite. The aggregate crushing value shall
not exceed 30 per cent. The grading of aggregates shall be as given
below :-
MATERIALS
13.4.2
Sand for mortar for laying slab/tiles shall conform to IS
2116-1980 as specified in Section 5- Brick work.
13.10 Abrasives
Metallic hardeners in the topping of floors and paving for
increasing abrasion resistance shall be Ironite, Hardonate,
Ferronite or other equal and approved metallic floor hardeners.
13.11 Bricks
Bricks for flooring shall have a compressive strength of at least 75
Kg/Sq cm and shall be of sub class A or B as indicated. Bricks shall
conform to IS 1077-1992 as specified in Section 5- Brickwork.
MATERIALS
13.12 Sand Stone Slabs
The stone slab shall be hard, even, sound, durable, tough, regular
in shape, of uniform colour and free from soft veins, cracks and
flaws, decay and weathering. Stone slabs shall be obtained from
approved quarries as indicated. The slabs shall have transverse
strength not less than 70 Kg/Sq cm and resistance to wear shall
not be more than 2mm. In case of red sand stone white patches or
streaks and in case of white sand stone, red patches or streaks
shall not be allowed. However, scattered spots upto 10mm
diameter will be permitted. The slabs shall be cut along planes
parallel to natural bed of stone. The slabs shall not be less than 0.1
Sq metre in area. The slabs used in any one room shall be of
uniform size. Thickness shall be as specified, with a permissible
tolerance of + 3mm.
MATERIALS
13.12.1 Marble Stone Slab and Tile
Marble stone slab and tile shall be as per requirement listed in the section 6-
Stone Masonry. The slab shall not be less than 0.21 Sq metre in area. The
slab/tile used in any one room shall be uniform. The thickness shall be as
specified with permissible tolerance of + 3%.
Heavy duty vitrified tiles shall be of sizes, colour, texture and designs as
indicated but size if not indicated it shall be of 300mm x 300 mm . The
thickness shall be as specified by the manufacturer.
MATERIALS
13.16 Plain Cement Concrete and Terrazo Flooring Tiles
13.16.1 Plain cement concrete tiles, coloured cement concrete
tiles and terrazzo tiles; and specials shall conform to IS 1237-1980
specification for cement concrete flooring tiles. Plain and
coloured cement concrete tiles shall be general purpose type and
shall be manufactured by pressure process. Thickness of wearing
layer in case of plain and coloured cement concrete tiles shall not
be less than 5mm. The thickness of wearing layer of terrazzo tiles
shall be 6mm for chips of sizes varying from smallest to 6mm or
smallest to 12mm and shall be 7mm for chips of sizes from
smallest to 20mm.
MATERIALS
13.16.2 Unless otherwise directed, the wearing face of the
terrazzo tiles shall be mechanically ground and filled. The
wearing face shall be plane, free from projections,
depressions and cracks (hair cracks not included) and shall
be reasonably parallel to the back face of the tiles. All angles
shall be right angles and all arises shall be sharp and true.
The colour and texture of the tiles shall be uniform
throughout its thickness. Tiles shall be 200mm x 200mm x
20mm thick or 250mm x 250mm x 22mm thick, plain,
coloured or terrazzo finish with marble chips of size and
shade, as indicated. Tiles in treads shall be 40mm thick and
bull nosed. The tolerance on thickness of tiles shall be plus
5mm but shall not exceed 3mm in case of any one delivery.
MATERIALS
13.17 Chequered Cement Concrete and Terrazo Flooring
Tiles
13.17.1 Chequered cement concrete tiles, coloured chequered
cement concrete tiles and chequered terrazzo tiles shall conform
to IS 13801-1993 specification for Chequered cement concrete
tiles. Chequered tiles shall be with the centre to centre distance
of chequers not less than 25mm and not more than 50mm, the
groove in chequers being uniform and straight with the depth of
grooves not less than 3mm. Tiles shall be manufactured by
pressure process. Thickness of wearing layer measured from top
of the chequers shall not be less than 6mm.
MATERIALS
13.17.2 Unless otherwise directed, the tiles shall be supplied with
initial grinding and grouting of the upper layer. The upper layer of
the tiles shall be free from projections, depressions and cracks,
holes, cavities and other blemishes. The edges of the tiles may be
rounded. All angles shall be right angles and all arises shall be
sharp and true. The colour and texture of the wearing layer shall
be uniform throughout its thickness. The size of Chequered Tiles
shall be200mm x 200mm x 22mm thick or 250mm x 250mm x
22mm thick or 300 x 300mm x 25mm thick as indicated. The
tolerance on length or breadth of tiles shall be +1mm and
tolerance on thickness of tiles shall be +5mm. In addition the
difference in thickness between the thickest and thinnest tile in
the sample shall not exceed 3mm.
MATERIALS
13.18 Precast Interlocking Paver blocks
Precast concrete Paver blocks shall conform to IS 15658:2006, Specification
for Precast concrete blocks for paving. Paver blocks shall be sound and free
from cracks or other visual defects. The tolerance on length or breadth of
paver blocks shall be +2mm and tolerance on thickness of tiles shall be
+3mm. Water absorption shall not be more than 6 percent by mass.
Shapes shall be triangular, Zigzag, Haxagon or other shape as indicated.
Colour of paver blocks shall be as indicated or as decided by GE. Thickness
and grade of concrete of paver blocks is decided based on intensity of
traffic, which is as under (Refer Table 1 of IS 15658 ):-
MATERIALS
13.19 Linoleum Flooring
13.19.1 Linoleum shall comply with the requirements of IS 653-
1992, Specification for linoleum sheets and tiles. There shall be
adequate adhesion between the composition and the Hessian
backing. The surface shall be smooth, uniform, free from
indentations and protrusions, streaks and marks. The thickness and
size shall be as indicated. The mean thickness shall not vary by more
than 0.1 mm from the specified thickness. Linoleum shall be plain,
moiré or jaspe, or marbled type, as indicated. Colour and shade shall
be as approved by the GE.
13.25.5 All points of level from the finished floor surface and
outlets shall be clearly marked and outlet openings made before
hand.
WORKMANSHIP
13.25.6 In the case of suspended floor slabs any slope in the floor
finish shall be given in the structural concrete itself. The surface
of the floor slabs shall be kept rough to provide an adequate
bond for the topping.
13.25.9 Tiles fixed in the floor adjacent to the wall shall enter
plaster, skirting or dado to a minimum depth of 10mm.
WORKMANSHIP
13.25.10 Mortars
Cement, Lime and composite mortars shall be made as detailed
in Section 5-Brickwork. The quantity of water added shall be the
minimum to give sufficient plasticity and workability for laying. A
high water cement ratio will produce a screeded bed with a high
drying shrinkage and shall be avoided.
13.26.1 Before laying the lime concrete, the surface of sub-base shall
be thoroughly cleaned of dirt, dust etc. and surface well wetted. On
the clean damp surface of sub base, lime concrete shall be spread
between forms, if necessary, thoroughly tamped and levelled. The
top surface shall be left rough to provide an adequate bond for the
topping.
13.26.2 Lime concrete shall be allowed to set for seven days before
floor finish of topping layer is laid.
WORKMANSHIP
13.27 Cement Concrete Sub-floors, Base or Sub Base
Cement concrete of the specified mix in sub-floor base or
sub-base etc., shall be mixed as specified in Section 4-
Concrete, and shall be laid, compacted and finished as
specified under Cement Concrete Flooring. The top surface
shall be broomed to have adequate bond with the topping.
Flooring shall be commenced within 48 hours of laying the
concrete sub floor etc, failing which the surface of the sub-
floor, etc,. shall be roughened with steel wire brushes,
wetted by sprinkling water and smeared with a coat of
cement slurry at 3 kg per sq.m.
WORKMANSHIP
13.28 Stone Slab Flooring
13.28.1 Dressing of Stone Slabs and Tiles :-
(a) Rough Dressed Slabs:- Every slab shall be cut to required size and
shape. The top surface of the slabs and tiles may be self faced or rough
chisel dressed so that the dressed surface shall not be more than 6mm
from the straight edge placed on it. The edges of depressions or
projections shall be chisel dressed in a slant so that the surface does not
have sharp unevenness. The side shall be chisel dressed to half the depth
so that the dressed edge shall, at no place, be more than 3mm from a
straight edge butted against it. Beyond this depth the sides may be
dressed slightly splayed so as to form an inverted ‘V’ shaped joint with
adjoining slab. The surface shall be reasonably true and plain and all the
angles and edges shall be true, square and free from chippings. Where
slabs are used for nosing, the exposed edges shall be rough tooled to full
depth and cut to a uniform thickness.
WORKMANSHIP
(b) Fine dressed slabs :- All joints upto half the depth and exposed faces
shall be fine tooled so that a straight edge placed on it is fully in contact
with it.
(c) Polished Slabs:- Every slab shall be machine cut or hand cut to the
required size. Hand cut slabs shall be first fine tooled as specified for fine
dressed slab and then table rubbed before paving, to obtain a perfectly
true surface free from chisel marks. Machine cut slabs shall have fine
tooled dressing on all sides to full depth. Machine cut slabs may be
supplied with polished (one cut) surface on top.
WORKMANSHIP
13.28.2 Laying of Stone Slabs
13.28.2.1 Slabs shall be washed clean before laying. The bedding mortar of
the specified mix, shall be spread under each slab, Slab shall be then laid
on top, pressed so that all hollows underneath get filled and surplus mortar
works up through the joints. The slab shall be tapped with a wooden mallet
and brought level and close to the adjoining slab with thickness of joint not
exceeding 10mm in the case of rough dressed slabs and 3mm in the case of
fine dressed slabs. After laying each slab, surplus mortar on the surface of
slabs shall be cleaned off and joints finished flush. Subsequent slabs shall
be laid in the same manner. In case slabs are specified to be pointed, the
joints shall be left raked out uniformly to a depth not less than 10mm,
when the mortar is still green. The surface of the flooring, as laid, shall be
true to levels and slopes, as directed by the Engineer-in-Charge. Slab which
are fixed in the floor adjoining the wall shall enter not less than 12mm
under the plaster, skirting or dado. The junction between wall plaster and
floor shall be finished neatly and without waviness.
13.28.2.2 In case of polished slab flooring, after paving, the slabs shall be
polished first by grinding with Carborundum stone of 120 grit and
second cut with 220-250 grit stones as described for terrazzo flooring.
Joints shall be very fine; thickness of joints shall not exceed 1.5mm.
13.30.4 Thickness of joints shall be between 8 to 10mm. The joints shall be flush
pointed incement and sand mortar 1:3 or as indicated after being raked out 10mm
deep while the mortar is still green.
13.30.5 Curing
The flooring shall be kept wet for at least 7 days after completion. In case of lime or
cement lime mortar curing shall commence two days after the laying and shall
continue for seven days.
13.31 Dry Brick Flooring/Paving
The bricks without soaking in water shall be laid dry, flat or on edge, as indicated
on a layer of sand, 25mm thick, laid to required slope on the subgrade. The bricks
may be laid in plain, diagonal, herringbone or other suitable pattern as indicated.
After laying the bricks, the joints shall be filled with fine sand. Where indicated,
joints shall be flush pointed to a depth of 15mm in cement and sand mortar 1:3.
13.32.3 Joints
Construction joints between bays of the floor finish need only be
plain, untreated, vertical butt joints and shall be placed over any
joint in the base.
13.32.4 Floor Finish Laid Monolithically with the Base Concrete
1. Laying the Sub-Floor or Base :-
The area to be paved shall be divided into suitable panels. Before placing the base
concrete, the sub-base shall be properly wetted. The concrete of the specified mix
shall then be deposited between the screed strips, thoroughly tamped and the
surface screeded uniformly. The surface shall be finished rough to provide
adequate bond for the topping.
If dividing strips are provided, the base concrete and the topping may be
laid in all the panels simultaneously.
13.32.5 Floor Finish Laid Separately on Hardened Concrete Base
13.32.5.1 Laying the Base Concrete
The base concrete may be deposited in the whole area at a
stretch. Before placing the concrete, the sub-base shall be
properly wetted and rammed. The concrete shall then be
deposited between the forms, where provided, thoroughly
tamped and the surface finished level with the top edges of the
forms. The surface of base concrete shall be left rough to
provide adequate bond for the topping. Two or three hours
after the concrete has been laid in position, the surface shall be
brushed with a hard brush to remove any scum or laitance and
swept clean so that the coarse aggregate is exposed.
13.32.5.2 Laying the Topping
13.32.5.2.1 The surface of base concrete shall be thoroughly cleaned of all
dirt, loose particles, caked mortar dropping and laitance, if any, by scrubbing
with coir or steel wire brush. Where the concrete has hardened so much that
roughening of surface by wire brush is not possible, the entire surface shall
be roughened by chipping or hacking. Before laying the topping, the surface
shall be soaked with water, at least for twelve hours and surplus water shall
be removed by mopping immediately before the topping is laid in position.
13.32.5.2.2 The forms shall be fixed over the base concrete dividing it into
suitable panels. Before placing the concrete mix for topping, neat cement
slurry at the rate of 3 Kg/sq m shall be thoroughly brushed into the prepared
surface of the base concrete just ahead of the finish. The topping shall then
be laid, thoroughly tamped or vibrated, the surface floated with a wooden
float to a fair and even surface. The surface shall be tested and finished as
specified for laying of topping laid monolithically with base concrete.
13.32.6 Laying the Topping in Two Layers
Where the topping is to be laid in two layers, the surface of the
concrete in the under-layer of topping shall not be finished smooth
with a trowel but left rough after tamping it and levelling it with
screed board.
Where the surface is to be finished with a steel trowel using extra cement, it shall be
clearly indicated.
13.32.9 Spike Rolling, etc
Spike rolling to concrete surface where indicated shall be executed with a
suitable roller to produce indentations, whilst the concrete is green.
Expanded metal impressions, where indicated, shall be made on the floor
surface while green by pressing expanded metal of the mesh as directed to
a depth of 3mm and removing the same carefully.
13.32.10 Curing
Immediately after the flooring surface is finished, it shall be protected from
rapid drying and strong sunlight. As soon as the surface has hardened
sufficiently to prevent damage to it, it shall be kept continuously moist for
at least fifteen days by means of wet gunny bags or 50mm thick layers of
damp sand spread over the surface or pooling water on the surface.
During this period the flooring shall not be exposed to any traffic. Regular
traffic on the floor shall be allowed only after 28 days.
13.33 Polished Coloured Concrete Floor
13.33.1 The surface of cement concrete floor, when indicated to be
coloured, shall be finished with a thin topping not less than 3mm
thick; consisting of one part of cement to two parts of sand,
coloured with the addition of approved mineral pigment of required
colour; thoroughly mixed with cement, when dry. The quantity of
pigment shall be such as to produce the required shade. The
coloured top layer shall be laid monolithically with the concrete.
13.37.2 The slabs shall be bedded and jointed in cement and sand
mortar (1:6) and pointed in cement and sand mortar (1:4). The
thickness of bedding mortar shall be not less than 15mm and
thickness of joints shall not exceed 6mm.
13.38 Terrazo Cast-in-Situ in Floors, Skirtings and Dados
13.38.1 Size of Tarrazo Panel
The Floor, both while laying the under layer and the topping shall be divided into
panels not exceeding 2 Sq m. The joints shall be so located that the longer
dimension of any panel does not exceed 2m. The panels, where indicated shall
be separated by means of dividing strips. However, where butt joints are
provided, the bays shall be laid alternately allowing for an interval of at least 24
hours between the laying of adjacent bays.
3. The proportion of cement and marble powder shall be 3 parts of cement and 1 part of
marble powder by weight. For every part of cement and marble powder mix, the proportion
of aggregates, by volume, shall be 1.75 parts for aggregates of 1 to 7 mm and 1.5 parts of 7
to 15mm. The cement shall be mixed thoroughly in dry state with marble powder. The
binder so obtained and the marble chips shall then be mixed dry together.
4. The mixing, if done manually, shall preferably be done in a trough or tub. While mixing
the aggregate, care shall be taken not to get the materials into a heap. The material shall be
kept, as far as possible in an even layer during mixing.
5. After the materials have been thoroughly mixed in the dry state, water shall be added in
small quantities, preferably in fine spray, while the materials are being worked until proper
consistency is obtained. The mixture shall be plastic but not so wet that it will flow.
6. The mix shall be used in the work within half an hour of the addition of water during
preparation.
13.38.3 Spreading the Underlayers
1. Dividing strips, where indicated, shall be glass, aluminium or plastic as
indicated and shall be fixed on the base to the exact surface level of floor
so as to divide the surface of the base into the required arrangement of
panels. Aluminium dividing strip shall have protective coating of bitumen.
The thickness of strip shall be as indicated but not less than 1.5mm.
Where dividing strips are not used, screed strips shall be fixed on the
base, properly leveled to the correct height to suit the thickness of floor.
2. Before spreading the underlayer, the base shall be cleaned of all dirt,
laitance or loose material and then well wetted with water without
forming any water pools on the surface. It shall then be smeared with
cement slurry at the rate of 3 kg of cement per sq. m just before the
spreading of underlayer.
3. After application of cement slurry, the underlayer of cement concrete
of mix as indicated shall be spread and leveled with a screeding board to
leave slightly rough surface.
13.38.4 Laying Terrazo Topping
1. Terrazo topping, of the thickness, as indicated, shall be laid, while the
underlayer is still plastic, but it has hardened sufficiently to prevent
cement from rising to the surface; this is normally achieved between 18
to 24 hours after the underlayer has been laid. A cement slurry @ 2.5 Kg
per sq m, preferably of the same colour as the topping shall be brushed
on the surface immediately before the laying is commenced.
2. The terrazzo mix shall be placed on the screed bed (underlayer) and
compacted thoroughly by tamping or rolling and trowelled smooth.
Excessive trowelling in earlystages shall be avoided. Care shall be taken
that cement does not get worked up to the surface which will produce a
finish liable to crack and will also necessitate more grinding of surface to
expose the marble chips.
3. The surface shall then be rammed in order to consolidate the terrazzo;
it is not sufficient just to float lightly as this would cause depressions
which have to be filled with mortar. A piece of smooth marble stone of
size 15cm x 15cm x 2.5cm may be advantageously used for ramming.
Following the rammer, a trowel may be used. Internal and external
angles may be rounded upto 25mm radius, where directed.
13.38.6 Grinding
The grinding shall be done by machine or by hand where machine grinding is not
feasible such as in skirting, dados, treads etc. First grinding shall be done with
carborundum stone of 60 grit size, the second with 80 grit size, the third with 120 to
150 grit size and the fourth with 320 to 400 grit size. Between each grinding the
surface shall be washed clean and grouted with neat cement grout of cream like
consistency using the same coloured cement as in the original mix and allowed to dry
for 24 hours (except 12 hours in lieu of 24 hours after the third grinding) and then wet
cured for four days. After the final grinding the surface shall again be washed clean
and rubbed hard with felt and slightly moistened oxalic acid powder, at the rate of 5
gm of oxalic acid powder for one sq m of floor surface.
13.38.7 Just before completion, the floor shall be washed clean with
dilute oxalic acid solution and dried. Floor polishing machine fitted with
felt or Hessain bobs shall then be run over it until the floor shines.
2. After the tiles have been laid in a room or the day's laying work is
completed, the surplus cement slurry and the joints shall be cleaned and
washed fairly deep with the help of a broom stick. It shall be seen that the
cement slurry is cleaned before it sets hard.
3. The day after tiles have been laid, the joints shall be filled with cement
grout of the same shade as the colour of the matrix of the tiles.
4. Tiles which are fixed in the floor adjoining the wall shall go about 10mm
under the plaster or skirting or dado. For this purpose, the wall plaster may
be left unfinished by about 50mm above the level of the proposed finished
flooring, skirting or dado and the unfinished strip may be plastered later on
after the tiles are fixed.
5. After fixing, the flooring shall be kept moist and allowed to mature
undisturbed for seven days so that the bedding and joints set properly. After
this, it may be used for light traffic. Heavy traffic shall not be allowed on the
floor for at least 14 days after fixing the tiles.
6. Wherever big areas of floors are to be tiled, the level of the central
portion of the floor shall be kept about 10mm higher than the level marked
at the wall.
13.39.3 Grinding and Polishing
1. Grinding and polishing of the tiles shall be commenced only after the
floor as well as the joints have properly set but in no case earlier than 14
days of laying.
2. Grinding shall preferably be done using a machine except for skirting and
dados. Chequered or grooved tiles shall be polished by hand.
3. For grinding terrazzo tile flooring, the first grinding shall be with Carborundum
stone of 48 to 60 grit. When floor is rubbed even and the chips show uniformity it
shall be cleaned with water making bare all pin holes. Grouting in the same shade is
then briskly applied so that all pin holes are properly filled in. The grout shall be kept
moist for a week for proper setting. Thereafter, the second grinding operation with
Carborundum of 120 grit is commenced. The floor is grouted again to fill in fine pin
holes. After curing for a week, the floor is left with this protective film till other works
are completed. Final grinding is done with Carborundum of 220 to 350 grit using
plenty of water. When surface is rendered smooth it is washed with water. After
wards oxalic acid powder is vigorously applied with machine fitted with Hessian bobs
to bring out shine. Floor is then washed clean and dry linen applied to suck- in-
moisture. Where indicated, wax polish shall finally be applied mechanically with
clean Hessian bobs. Superfluous wax is moped-up with saw dust to prevent
slipperiness. Saw dust may be allowed to remain on the surface till occupation. This
will protect the surface and help to increase luster. When saw dust is spread, water
should not be spilled as this is likely to leave stains on the polished surface.
4. In the case of plain cement and coloured cement tiles, the process of polishing shall be
the same as described for terrazzo tiles except that initial grinding with Carborundum
stone 48 to 60 grit is not necessary.
Tiles shall be ground and polished as for flooring by hand. Precast treads and risers
for staircase shall be laid and polished as for flooring.
13.39.5 The finished floor, skirting and dado shall have an
even smooth and shining surface. Joints shall be in correct
alignment. After laying the floor shall be allowed to remain
clean and free from cement, oil, paint, distemper, plaster
dropping and all materials likely to stain or spoil the tiles.
In the cases of skirting and dado, the wall surface shall be covered with about 10mm
thick plaster of cement and sand mortar 1:3 and allowed to harden. The plaster shall be
roughened with wire brushes or by scratching diagonal lines. The back of tiles shall be
buttered with cement paste and set on bedding mortar. The tiles shall be gently tapped
in position one after the other. Top of skirting or dado shall be truly horizontal and the
joints vertical or as per required pattern. Joints shall be flush pointed with white cement
with pigment to match the colour of tiles.
13.41 Vitrified Porcelain Tiles flooring
13.41.1 Bedding
The screed bed for laying Vitrified Porcelain Tiles shall be of cement and sand mortar 1:4. Bedding over
which the tiles shall be laid shall not be less than 10mm at any place.
13.41.2 Laying
Base concrete or RCC slab shall be cleaned and wetted. The bedding shall then be laid evenly over the
surface, tamped and corrected to desired levels and allowed to harden enough to offer a rigid cushion
to tiles. Before laying the tiles , tiles shall be washed and then applied fine cement slurry on the back
of the tile to ensure full and proper bedding. Tiles shall then be placed on bedding, each tile being
gently tapped with rubber hammer in its position till it is properly bedded and in level and line with
adjoining tiles. Use of spacers is recommended for uniformity in joints and better finish. Remove the
residual cement or jointing material immediately by a wet sponge. After 24 hours when the tiles are
properly set and cured, fill the joint gaps with joint filler as per recommendation of manufacturer.
The joint gap shall be filled by spreading joint filler paste in the spaces between the tiles with the
help of rubber trowel. Clean the tiles surface immediately with the help of wet sponge .
Vitrified Porcelain Tiles can be laid in flooring over Base concrete or RCC slab directly by using
suitable chemical adhesive as per manufacturers instructions if so indicated.
13.42 Linoleum Flooring
The linoleum shall be laid either loose or fixed to the sub-floor by
means of a suitable adhesive as indicated.
It shall be cut closely to size and fitted loose on the floor. One-half
of the sheet is turned back into the centre and adhesive is spread
on both floor and linoleum and allowed to become tacky. After an
interval of time appropriate for the adhesive used, the linoleum
shall be rolled on to the floor, with a 70 Kg linoleum roller
working from the centre to the walls. If necessary, the linoleum
may be loaded with sand bags at various points until the adhesive
has gripped. The operation shall be repeated for the other half.
13.42.3 Finishing
Any adhesive contaminating the face of the flooring shall be
removed as soon as possible and in any case within the setting
time. When the flooring has been securely fixed, it shall be
cleaned with soap and warm water. The surface shall be wax
polished where so indicated.
13.43 Rubber Sheet and Tile Flooring
13.43.1 Before commencing the laying operations, it shall be ensured
that base concrete or mortar is even, clean and dry. The layout of the
rubber flooring on the sub-floor to be covered shall be marked with
guidelines. The rubber flooring shall be first laid for trial without using
the adhesive according to the required layout. The adhesive shall be
applied by using a notched trowel to the sub-floor and to the back
side of the rubber sheet or tile flooring. When set sufficiently for
laying, the adhesive shall be tacky to the touch, but shall not mark the
fingers. In general, the adhesive will require about half an hour for
setting, it should not be left after setting for too long a period as the
adhesive properties will be lost owing to dust film and other causes.
Care shall be taken while laying the flooring that condensation does
not take place on the surface of the adhesive. It is preferable to avoid
laying under high humidity conditions.
13.43.2 When the adhesive is just tack free, the rubber flooring
sheet shall be carefully taken and placed in position from one end
onward slowly so that the air will be completely squeezed out
between the sheet and the background surface. After laying the
sheet in position, it shall be pressed with suitable roller to develop
proper contact with the sub-floor. The next sheet with its backside
applied with the adhesive shall be laid to edge with the sheet
already laid and fixed in exactly the same manner as the first
sheet. Care shall be taken that sheets are laid close to each other
with minimum gap between joints. The alignment shall be
checked after laying of each row of sheet is completed. If the
alignment is not perfect, the sheets may be trimmed by using a
straight edge.
13.43.3 The tiles shall be fixed in exactly the same manner as the
sheets. It is preferable to start laying of the tiles from the centre of
the area. The tiles shall always be lowered in position and pressed
firmly on to the adhesive for full contact with the background
surface. The tiles shall not be slid as it may result in adhesive being
squeezed up between the joints. Any undulations noticed on the
rubber flooring surface shall be rectified by removing and relaying
the tiles after thorough cleaning of the under side of the affected
tiles. The adhesive applied earlier in such places shall be thoroughly
removed by using proper solvents and the surface shall be cleaned
to remove the traces of solvents used. Work shall be constantly
checked against guidelines to ensure that all the four edges of
adjacent tiles meet accurately.
13.43.4 Any adhesive contaminating the face of the rubber flooring
before it hardens shall be removed as the work proceeds, without
smearing the adjacent surfaces. In case a solvent is used care shall
be taken so that the solvent does not cause any damage to the
rubber.
The slabs shall have the top (exposed) face polished before being brought to site. Before
starting the work, Contractor shall get the sample of slabs approved by the Engineer-in-
Charge.
13.47.3.3 Slabs which are fixed in the floor adjoining the wall shall enter not less than
twelve (12) mm under the plaster skirting or dado. The junction between wall plaster
and the floor shall be finished neatly and without waviness.
13.47.4 Curing, Polishing and Finishing
13.47.4.1 The floor shall be kept wet for a minimum period of seven (7)
days. The surface shall thereafter be ground evenly with machine fitted
with fine grade blocks (No. 120). The final grinding with machine fitted
with the finest grade grit blocks (No. 320) shall be carried out the day
after the first grinding described above or before handing over the floor,
as ordered by the Engineer-in-Charge.
13.47.4.4 After the final polish, oxalic acid shall be dusted over the
surface at the rates of thirty three (33) gms. per square metre sprinkled
with water and rubbed hard with pad of wooden rags. The following day
the floor shall be wiped with a moist rag and dried with a soft cloth and
finished clean.