HSSE Requirements

Cleaning Tank SP 3
HSSE EPC 2 JWFP
Work Hazards
• Gas vapor dispersion from TOS.
• Hot work activity.
• Confined space entry.
• Spillage.
• Miss operate tank valves.
• Sludge waste.
• Liquid carryover from TOS.
Risk
• Fire & Explosion.
• Gas vapor intake tanks via air blower during tank cleaning.
• Oil spill.
• Health risk.
Mitigation
• Check radius vapor dispersion. • SIKA.
• Ensure in & out valve disconnect from production line. • JSA.
• Limitation for hot work area due to vapor hazard. • Personil certified to CSE.
• Stand by fire extinguisher and fire fighter. • ERP.
• Provide containment. • Rescue team stand by.
• LOTO. • Ambulance & Paramedic
• Monitor pump operation & TOS liquid level. standby.
• Sludge disposal. • Monitoring flammable,
• Open/close valve must operated by operation team. hazardous gas by AGT.
HSE Tools
• Gas detector. • Cleaning tank outfit.
• APAR. • Trash Bag.
• Airline respirator system. • Blower.
• Cartridge Mask. • Submersible pump.
• LOTO.
• Ambulance.
• Oil spill kit.
• SCBA.
• Pakaian pemadam kebakaran
Checklist Equipment

NO TOOLS QUANTITY DOCUMENTATION STATUS


1 Gas detector 2 Unit Kalibrasi gas detector
aktif, alat siap di
gunakan.

2 APAR 2 Tabung APAR 6 Kg. Siap


digunakan.

3 Airline respirator system 1 Unit Terlampir Belum tersedia.


4 Cartridge Mask 6 Pcs Catridge mask, spare
catridge tersedia.
Checklist Equipment

NO TOOLS QUANTITY DOCUMENTATION STATUS


5 LOTO 2 pcs Belum tersedia. Size
agar di sesuaikan
dengan size valve.

6 Ambulance 1 Unit Tersedia, siap


digunakan.

7 Oil spill kit 1 Belum tersedia.


Checklist Equipment

NO TOOLS QUANTITY DOCUMENTATION STATUS


8 SCBA 1 Unit Tersedia, siap
digunakan.

9 Pakaian pemadam 1 Pcs Sepatu tahan api


kebakaran belum tersedia.

10 Cleaning tank outfit 10 Pcs Tersedia, siap


digunakan.
Checklist Equipment

NO TOOLS QUANTITY DOCUMENTATION STATUS


11 Trash Bag 1000 Tersedia, siap
digunakan.

12 Blower 2 Blower tersedia 2


unit.

13 Submersible pump 1 Unit Belum tersedia.

Catatan: Info
pelaksana sisa liquid
menggunakan metode
manual tidak
menggunakan pompa.
AIR LOOP SYSTEM
Air Manifold

Air Regulator

Air Compressor L/P Hose

L/P Hose

H/P Hose

Work Unit C/W box


Cascade Rack