CONCRETE
F1 - 25pcs
F2 – 1pcs
CF1- 1 pc
CF2- 1pc
Footing
F1 - 25 pcs
F2 – 1pcs
CF1- 1 pc
CF2- 1pc
Step 3: Compute for the volume
For F1: V = 1.5 x 1.5 x 0.4 = 0.9 cu.m.
For F1: V = 1.5 x 1.5 x 0.4 = 0.9 cu.m.
Total Vol = 0.9 x 25 = 22.5cu.m.
For F2: V = 2x2x 0.4 = 1.6 cu.m.
Total Vol = 1.6 x 1 = 1.6cu.m.
For CF1: V = 3x1.25x 0.4 = 1.5 cu.m.
Total Vol = 1.5 x 1 = 1.5cu.m.
For CF2: V = 3.1x1.5x 0.4 = 1.86 cu.m.
Total Vol = 1.5 x 1 = 1.86cu.m.
TOTAL FOOTING VOLUME: 22.5 + 1.6 + 1.5 + 1.86 = 27.46cu.m. x 1.1
Total vol = 30.206cu.m.
Step 4: Compute for the qty of materials
D=?
Step 2: Quantify the total length of each column (compare foundation to elevation plan)
Step 2: Quantify the total length of each column (compare foundation to elevation plan)
Step 2: Quantify the total length of each column
C1 = 3pcs @ 4.5m
C1 =17pcs @ 7.2m
C2 =4pcs @ 7.2m
C3 =6pcs @ 7.2m
Step 3: Compute for the total volume
350mm
Step 4: Compute for the qty of materials
B-1= 39.5m
B-2= 53.5m
B-3= 14.5m
B-4=7.5m
RB-1 = 60m
Step 2: Calculate the total
length of each beam
FTB =97.5m
B-1= 39.5m
B-2= 53.5m
B-3= 14.5m
B-4=7.5m
RB-1 = 60m + 26.5 = 86.5
RB-2= 91m
Step 3: Calculate the total volume
Vol=(142.5+46+27) x 0.10m
Vol=21.55 cu.m.
A3
Step 4: Compute for the qty of materials
A1
A2 = 16sq.m.
A3 = 2.24sq.m.
TOTAL VOL = (86.25+16+2.24)X0.10)
TOTAL VOL =10.449 cu.m.
Step 4: Compute for the qty of materials
SAMPLE COMPUTATION
SLAB ON GRADE = 21.55 M3 ELEVATED SLAB:
ELEVATED SLAB = 10.50M3 10.5M3 X 16 MH/M3 = 5.25DAYS
32MH/DAY
MANPOWER: 2 MASON 2 LABOR =
32MH/DAY
WITH MIXER:
MIXING MACHINE = 1.8 MH/M3
PLACING slab on fill = 5.0MH/M3
PLACING elevated slab = 7.0MH/M3