Professional Documents
Culture Documents
Alternator Presentation
Alternator Presentation
1 11/26/20
Stamford Range
BC 16 - 10 – 15 KVA
BC 18 - 15 – 40 KVA
UC22 - 30 - 82.5 KVA
UC27 - 100 - 200 KVA
HC4- 225 - 380 KVA
HC5 - 400 - 625 KVA
HC6- 750 - 1250 KVA
P7 - 1260 – 2200 KVA
Stamford Range New Frame
UC224C 42.5 -
Alternator Overview
AVR
Main Stator
Exciter Field (Stator)
Exciter Rotor
(Armature)
Rotating Diodes
5 11/26/20
Alternator Types
6 11/26/20
Self-Excited operation principle
7 11/26/20
Separately-Excited operation principle
9 11/26/20
Advantages of PMG
10 11/26/20
Alternator Overview
11 11/26/20
Main Complete Generator
Terminals
Assembly
A.V.R.
on A.V.M,s Main Rotor
Main Stator Drive end
Non drive
end Bracket Frame Bracket
P.M.G
Rotor
P.M.G
Stator
Rotating Rectifier Assembly
Positive
Diodes
Varistor
Negative
13 11/26/20
Diode Checking with Multi-Meter
14 11/26/20
Surge Suppressor
The device is not polarized and will show a virtually infinite reading
in both directions with an ordinary resistance meter.
Replace if faulty.
15 11/26/20
Maintenance of alternator
4. Operational Checks
Maintenance requirements - Bearings
Vibration
Increased vibration in the Generator, suddenly, or slowly over a period of time.
Vibration equipment is expensive, a check by hand near the bearing will give an
indication. ( Note: this could also be an engine related problem).
Noise
Bearing making abnormal noises, audible, with or without Stethoscope. (
A Stethoscope is required for elimination of other possible causes of noise )
Experience gained from touch and sound, will establish ‘normal’ conditions.
Periodic Health monitoring is recommended throughout the life of the Generator to
establish normal conditions.
Maintenance requirements - Bearings
2 BEARING KITS
HC6, 45 - 0880, HC7 45 - 0872.
1 BEARING KITS
HC6, 45 - 0879, HC7 45 - 0877
Maintenance requirements - Insulation checks
1. The Generator has been STATIONARY for a long period with Anti-
Condensation heaters SWITCHED OFF.
23 11/26/20
Maintenance requirements - Testing the Main Stator Insulation
Connections shown in Series Star
EARTH
AVR Sensing W6
& Power supply N
UV6 Neutral
6
00
0 10
M
0 10 1 0
.1
.01
from Main 1
Stator W
6 5
W
2 W W1
V Test
7
V
5
2 V V1
3 Phase M 1KV
8 5
U
2 U U
1
EARTH MEGGE
FRAME R
1. When (after drying), the windings are still reading less than 1 M to
earth.
3. MAIN
RECTIFIER
COMPONENTS
Maintenance requirements – Health checks
High humidity, or exposure to the elements, rainwater, and/or offshore sea mists.
Dust, dirt, and/or corrosive chemicals in the atmosphere.
Excessive vibration from the Engine, or worn coupling rubbers/ vibration mounts.
1. The NO LOAD D.C voltage across the AVR terminals X+ (F1) and X-.
Keep this reading in the Gen-set maintenance record book for future reference.
Example :-
DATE FRAME SIZE SERIAL NUMBER R.P.M VOLTS LOAD D.C EXT
######## HCI734E C098976/2 1560 415 0 11.5
K2 K1 P2 P3 P4 XX X 3 2 2 1
VOLTS XX X 6 7 8
A1
4 TRIM A2
S1
DROOP S2
1
2
UFRO SX460 SX440 VOLTS
3
3 4
5
6
50 7
8
C UFRO STABILITY
STABILITY
260
50 C 60 C B A
29 11/26/20
PMG AVR Examples
K2 K1 P2 P3 P4 XX X 3 2 2 1 VOLTS
A1 P4 XX X 6
K2 K1 P2 P3 7 8 1 2
TRIM A2
S1
I/LIMIT
MX341 DROOP S2
MX321
UFRO
3 2 1
1
2 DIP RMS
VOLTS 3
4 DWELL
DIP 5
EXC TRIP STABILITY
6 EXC
7 OVER/V DROOP
8
TRIP S2 S2 S2 A2 TRIM
UFRO STABILITY
E0 E1 B0 B1 C B A S1 S1 S1 A1
3 2 1 C B A
30 11/26/20
AVR General Fault Findings
Check Speed.
No voltage build
Check residual voltage.
up when starting
Follow separate excitation test. Procedure to check
set.
generator & AVR.
Unstable voltage
Check speed stability.
either on no load
Check stability setting of AVR.
or with load.
High voltage Check speed.
either on no load Check that generator load is not capacitive (leading
or with load. power factor).
Check speed.
Low voltage on
Check link 1 – 2 or external hand trimmer leads for
no load.
continuity.
Check speed.
Low voltage on Check UFRO setting.
load. Follow separate excitation test procedure to check
generator & AVR.
31 11/26/20
Parallel Operation
equipment.
6. Essential protection should include Reverse power, Over-current ,
live Bus-bar, either in Island mode ( with multiple Generator sets as the
GEN 1
AVR DROOP CT
CB1 BUS-BAR
LOAD
GEN 2 MCB
AVR DROOP CT
CB2
Consider a simple installation with two Identical Gen-sets, (breakers open circuit).
Normally, one (or more), generators will already be connected to the load, and
supplying power. (GEN 2 is now closed onto the Bus-bar).
It is also normal that the Generator on line (GEN2) will be running at nominal
frequency (50HZ), while the incoming generator (GEN1), can be running at a higher
(NO LOAD), frequency of about 52 HZ.
Parallel Operation - Synchronising AC Generators
GEN 1 Synchronising
AVR DROOP CT
Equipment
CB1 BUS-BAR
LOAD
GEN 2 MCB
AVR DROOP CT
CB2
When the relative Engine speeds are different, the Generator waveforms will be
rapidly going in and out of phase with each other.
To correctly Synchronise A.C. Generators, the frequencies must be ALMOST identical.
Frequency (HZ), is the Electrical equivalent of Speed (RPM), which means that the
engine SPEEDS must be ALMOST identical.
Synchronising equipment is required to monitor the Bus Frequency and the
Incoming Generator frequency, to ensure that the Generators are in Synchronism.
Parallel Operation - Synchronising AC Generators
SYNCHRONISED
Incoming Generator Set On-line Generator Set
EXAMPLE : In this analogy two trucks represent two Generator sets, to be paralleled .
If both trucks are travelling at EXACTLY THE SAME SPEED, they will ALWAYS
remain the SAME DISTANCE APART, ( IRRESPECTIVE OF SPEED).
However, if the REAR truck is A FEW RPM FASTER than the FRONT truck, it will
VERY SLOWLY catch up with the truck in front.
SYNCHRONISING is exactly the same process, the RATE OF CHANGE in speed must be
SLOW ENOUGH to allow the BREAKER to close when the Generators are IN PHASE .
Parallel Operation - Synchronising AC Generators
GEN 1
IN PHASE
50 HZ
(1500 RPM)
GEN 2 50.1 HZ
(1503 RPM)
GEN 1 is INCOMING, and the engine speed has been adjusted down slightly to
almost 1500 RPM (for example 50.1 HZ).
As there is a SMALL RELATIVE DIFFERENCE between speeds, the Synchronising
equipment should be indicating that the Generators are moving IN and OUT of phase
SLOWLY enough to ALLOW TIME to close the breaker.
Parallel Operation - Synchronising AC Generators
GEN 2 50.1 HZ
What will happen if the circuit breaker is closed in the final condition above ?
Parallel Operation - Synchronising AC Generators
GEN 1
CRASHED
180º
INTO PHASE
GEN 2
The Generator waveforms are 180º OUT OF PHASE with each other.
As the breaker closes, GEN 1 will instantly try to reverse the rotation of GEN 2.
This is IMPOSSIBLE, because of the inertia in the Engine/Generator moving parts.
The Generators will be INSTANTLY ‘CRASHED’ into synchronism. .
The transient forces created are both Electrically and Mechanically DESTRUCTIVE
Electrical damage can occur to Diodes, Varistors, and Main Stator windings.
Mechanical damage may also occur to Couplings, Bearings, and Shaft.
Parallel Operation - Synchronising AC Generators
GEN 1
IN PHASE
50 HZ
1500 RPM
GEN 2 50.1 HZ
1503 RPM
GEN 1 engine speed has been adjusted to almost 1500 RPM (50.1 HZ).
Synchronising
GEN 1 AVR DROOP CT
Equipment
OK !
CB1 BUS-BAR
LOAD
GEN 2 AVR MCB
DROOP CT
CB2
When the Synchronising equipment indicates that the incoming Generator (GEN 1) is IN
PHASE with the Bus-bar frequency, the circuit breaker can be safely closed.
The INCOMING Generator should ALWAYS be slightly FASTER than the loaded
generator. This ensure that the incoming Generator ALWAYS takes a small proportion of
load when the breaker is closed. This will prevent REVERSE POWER protection tripping.
The Generators are now IN PARALLEL
Parallel Operation - Circulating Current
WHY IS DROOP IS REQUIRED FOR GENERATORS IN PARALLEL ?
CB1
BUS
0 LOAD
403V
GEN 2 AVR 2 MCB
403V
406V
CB2
GEN 1 AVR
BUS-BAR
400V CB1
403 V
403V LOAD
GEN 2 AVR MCB
406V
BUS-BAR
LOAD
GEN 2 AVR 2 DROOP CT MCB
ACTIVE CURRENT or
kW kW
LEA
D
kWATT
METER
ACTIVE CURRENT (power factor 1) is the kWATT component of the load, and is
CONTROLLED and SHARED by the PRIME MOVERS (ENGINES).
The PRIME MOVERS (ENGINES), must have similar NO LOAD to FULL LOAD
GOVERNOR CHARACTERISTICS, in order to share the ACTIVE CURRENT, (PF1).
KW Load Sharing is unequal
48 11/26/20
Reverse Power failure symptoms.
49 11/26/20
3 PHASE UNBALANCED LOADS
Example 2 66 kVA 3 phase 380 Volts 100 Amps Generator with unbalanced
load current
U
100
O
U
Line - Line Voltage Line - Neutral Voltage T
= 380 V = 220 V P
U
T
N 35 T
O
L
O
w 85
v A
D
60
Unbalanced single phase loads kVA = (220 X 100 ) + (220 X 85) + (220 X 60) / 1000
kVA = 22000 + 18700 + 13200 / 1000 =
53.9 kVA
Note1. U phase has FULL LOAD AMPERES, therefore preventing further addition of 3 phase load.
Note 2. The Neutral current is equal to the VECTORIAL sum of the three line currents i.e, = 35 Amps
NEUTRAL CURRENTS
Unbalance Loading failure symptoms.
51 11/26/20