TASK TYPE OF HAZARD HIERARCHY OF CONTROL

(ELIMINATION, SUBSTITUTION,
ENGINEERING, WARNINGS,
ADMINISTRATION AND PPE)
1. EMBANKMENT • BIOLOGICAL HAZARD • ELIMINATION
• PHYSICAL HAZARD (NOISE HAZARD - OBSTRUCTION
AND TEMPERATURE HAZARD) - CLEARING OF RIGHT OF WAY
• CHEMICAL HAZARD • ENGINEERING
-BARRIER FOR MATERIALS
-WARNINGS
• ADMINISTRATION
-CAUTION TAPE
-TRAFFIC CONTROL/ SIGNAGE
-FLAGMAN OR SPOTTER
• PPE
- UNIFORM
- BOOTS / SAFETY SHOES
- REFLECTORIZED VEST
- DUST MASK
- HELMET
- GLOVES
2. BASE PREPARATION • PHYSICAL HAZARD ( VIBRATION ) • ELIMINATION
• CHEMICAL HAZARD OBSTRUCTION
• BIOLOGICAL HAZARD CLEARING OF RIGHT OF WAY
• ENGINEERING
-BARRIER FOR MATERIALS
-WARNINGS
• ADMINISTRATION
-CAUTION TAPE
-TRAFFIC CONTROL/ SIGNAGE
-FLAGMAN OR SPOTTER
• PPE
UNIFORM
BOOTS / SAFETY SHOES
REFLECTORIZED VEST
DUST MASK
HELMET
GLOVES
3. FORM WORKS • ERGONOMIC HAZARD • ELIMINATION
• PHYSICAL HAZARD OBSTRUCTION
• CHEMICAL HAZARD CLEARING OF RIGHT OF WAY
• BIOLOGICAL HAZARD • ENGINEERING
-BARRIER FOR MATERIALS
-WARNINGS
• ADMINISTRATION
-CAUTION TAPE
-TRAFFIC CONTROL/ SIGNAGE
-FLAGMAN OR SPOTTER
• PPE
UNIFORM
BOOTS / SAFETY SHOES
REFLECTORIZED VEST
DUST MASK
HELMET
GLOVES
4. CONCRETE POURING • ERGONOMIC HAZARD • ELIMINATION
• CHEMICAL HAZARD OBSTRUCTION
• BIOLOGICAL HAZARD CLEARING OF RIGHT OF WAY
• PHYSICAL HAZARD (NOISE • ENGINEERING
HAZARD AND TEMPERATURE -WARNINGS
HAZARD) • ADMINISTRATION
-CAUTION TAPE
-TRAFFIC CONTROL/ SIGNAGE
-FLAGMAN OR SPOTTER
• PPE
UNIFORM
5. CONCRETE SURFACE • PHYSICAL HAZARD BOOTS / SAFETY SHOES
PREPARATION • ERGONOMIC HAZARD REFLECTORIZED VEST
• CHEMICAL HAZARD DUST MASK
• BIOLOGICAL HAZARD HELMET
GLOVES