Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 83

SEMI QUANTITATIVE

RISK ASSESMENT
RISK MANAGEMENT TEAM TEACHING 2018
Concept Definitions
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Concept Definitions
Hazard – An intrinsic chemical, physical, societal, economic or political condition that
has the potential for causing damage to a risk receptor (people, property or
the environment).

A hazardous event (undesirable event) requires an initiating event or failure and then either failure
of or lack of safeguards to prevent the realisation of the hazardous event.

Examples of intrinsic hazards:


• Toxicity and flammability – H2S in sour natural gas
• High pressure and temperature – steam drum
• Potential energy – walking a tight rope
3
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Concept Definitions

Risk – A measure of human injury, environmental damage or economic loss in


terms of both the frequency and the magnitude of the loss or injury.

Risk = Consequence x Frequency

4
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Concept Definitions

Risk

Intrinsic Undesirable
Hazards Event
Consequences
Likelihood Likelihood of
of Event Consequences

Example
Storage Loss of life/ property,
Spill and Environmental
tank with
Fire damage,
flammable Damage to reputation
material of facility
5
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Concept Definitions

Risk

Intrinsic Undesirable
Hazards Event
Consequences
Likelihood Likelihood of
Causes of Event Consequences

6
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Concept Definitions Layers of Protection are used to


enhance the safe operation. Layers of
Protection Analysis (LOPA) is used to
Risk Layers of Layers of determine if there are sufficient layers of
Protection Protection protection for a predicted accident
scenario. Can the risk of this scenario
be tolerated?
Intrinsic Undesirable
Hazards Event
Consequences
Likelihood Likelihood of
Causes of Event Consequences
Causes are also known
as Initiating Events.

Preparedness,
Prevention Mitigation,
Land Use Planning,
Response, Recovery
7
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Quantifying Risk
Risk – A measure of human injury, environmental damage or economic loss in
terms of both the frequency and the magnitude of the loss or injury.
N
Riskh =å Consequencei,h * Frequencyi,h
i=1
Rh Consequencei, of Frequencyi, of
Risk from an undesirable event, h consequence i from
undesirable event h
event, h
where i is each consequence

8
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Quantifying Risk
If more than one type of receptor can be impacted by an event, then the
total risk from an undesirable event can be calculated as:
K N
Riskh =å å Consequencei,h,k * Frequencyi,h,k
Rh k=1 i=1
Risk from an Consequencei, of Frequencyi, of
undesirable undesirable event, h consequence i, from
event, h event h

where k is each receptor (ie. people, equipment, the


environment, production)
9
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Define the System


Overview of Risk Assessment
Risk
Hazard
1. Identify hazardous materials and process Analysis
conditions Identification
2. Identify hazardous events
3. Analyse the consequences and frequency of
events using:
i. Qualitative Risk Assessment Consequence Frequency
(Process Hazard Analysis using
Risk Matrix techniques) Analysis Analysis
- SLRA (screening level risk assessment)
- What-if
- HAZOP (Hazard & Operability study) Risk
- FMEA (failure modes and effects analysis)
Evaluation

Risk Assessment
10
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Define the System


Overview of Risk Assessment
Risk
Hazard
ii. Semi-Quantitative Risk Assessment Analysis
- Fault trees/ Event trees/ Bow-tie
Identification

iii. Quantitative Risk Assessment


- Mathematical models for hazard effents Consequence Frequency
include explosion overpressure levels, Analysis Analysis
thermal radiation levels
- The consequences are determined from
the hazardous effects
Risk
Evaluation

Risk Assessment
11
Perform Quantitative Risk Analysis
• The process of numerically analyzing the effect of identified risks
on overall Organization objectives
• Quantitative analysis is performed onrisks that have been
prioritized by the qualitative risk analysis process as potentially
and substantially impacting the competing demands.
Techniques Used in Quantitative Risk Analysis
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Risk Assessment requires QUANTITATIVE frequency analysis.

Quantifying risk enables estimation of:


• How often an undesirable initiating event may occur.

• The probability of a hazard outcome after the initiating event.

• The probability of a consequence severity level after the hazard outcome


(i.e. fatalities, injuries, severity of economic loss).

14
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Historical data can be used to calculate the frequency of


initiating events, hazard outcomes and the severity of the
consequence.

Analysis Techniques
1. Frequency modelling techniques
2. Common-cause failure analysis
3. Human reliability analysis
4. External events analysis
• Used

15
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Data can be used to calculate the frequency of initiating


events, hazard outcomes and the severity of the
consequence.

Analysis Techniques
1. Frequency modelling techniques Used to estimate frequencies or
2. Common-cause failure analysis probabilities from basic data.
3. Human reliability analysis Typically used when detailed
historical data is not available.
4. External events analysis
• Used

i. EVENT TREES
ii. FAULT TREES

16
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Data can be used to calculate the frequency of initiating


events, hazard outcomes and the severity of the
consequence.

Analysis Techniques
1. Frequency modelling techniques Used to identify and analyse
2. Common-cause failure analysis failures common to multiple
3. Human reliability analysis components found in systems
4. External events analysis that can lead to a hazardous
event.
• Used

17
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Data can be used to calculate the frequency of initiating


events, hazard outcomes and the severity of the
consequence.

Analysis Techniques
1. Frequency modelling techniques
2. Common-cause failure analysis Used to provide quantitative
3. Human reliability analysis estimates of human error
4. External events analysis probabilities.
• Used

18
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Data can be used to calculate the frequency of initiating events,


hazard outcomes and the severity of the consequence.

Analysis Techniques
1. Frequency modelling techniques
2. Common-cause failure analysis
3. Human reliability analysis
4. External events analysis Used to identify and assess
external events (i.e. plane crash,
• Used

terrorist activities, earthquakes)


to understand expected
frequency of occurrence and/or
consequence severity per
occurence. 19
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

Data can be used to calculate the frequency of initiating


events, hazard outcomes and the severity of the
consequence.

Analysis Techniques
1. Frequency modelling techniques Used to estimate frequencies or
2. Common-cause failure analysis probabilities from basic data.
3. Human reliability analysis Typically used when detailed
historical data is not available.
4. External events analysis
• Used

i. EVENT TREES
ii. FAULT TREES
We will focus on event and fault trees as frequency modelling techniques.
20
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees
• Fault trees are logic diagrams using and/or combinations.
• They are a deductive method to identify how hazards culminate from
system failures.
• The analysis starts with a well-defined accident and works backwards
towards the causes of the accident.

21
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Typical Steps


STEP 1 – Start with a major accident of hazardous event (release of toxic/
flammable material, vessel failure). This is called a TOP EVENT.
STEP 2 – Identify the necessary and sufficient causes for the top event to occur.
How can the top event happen?
What are the causes of this event?
STEP 3 – Continue working backwards and follow the series of events that
would lead to the top event. Go backwards until a basic event with a
known frequency is reached (pump failure, human error).

22
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Simple Example


Car Flat Tire
(TOP EVENT)

Driving over Tire failure


debris on the
road

Defective Worn
Tire Tire
This is not an exhaustive list of failures.
Failures could also include software, human and environmental factors.
23
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Simple Example


Car Flat Tire
(TOP EVENT)

Driving over Tire failure INTERMEDIATE


debris on the EVENT
road

Defective Worn
Tire Tire

24
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Simple Example


Car Flat Tire
(TOP EVENT)

Driving over Tire failure


debris on the
road

BASIC Defective Worn


EVENTS Tire Tire

Let’s now format this tree as a fault tree logic diagram.


25
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Simple Example, Logic Diagram


TOP EVENT Car Flat Tire

OR

Tire failure

Driving over OR
debris on
the road
Defective Worn
Tire Tire
26
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Tree Logic Transfer Components


BASIC EVENT
AND GATE This is fault event with a
Output event requires simultaneous known frequency and needs
occurrence of all input events no further definition.
INTERMEDIATE
EVENT
OR GATE An event that results from the
Output event requires the interaction of other events.
occurrence of any individual input UNDEVELOPED EVENT
event. An event that cannot be developed
further (lack of information), or for
INHIBIT EVENT which no further development is
needed.
Inhibit Output event will not occur if EXTERNAL EVENT
Condition the input and the inhibit An event that is a boundary
condition occur condition to the fault tree.
27
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – BEFORE YOU START DRAWING THE TREE, Preliminary Steps

STEP 1 – Precisely define the top event.


STEP 2 – Define pre-cursor events.
What conditions will be present when the top event occurs?
STEP 3 – Define unlikely events.
What events are unlikely to occur and are not being considered?
Wiring failures, lightning, tornadoes, hurricanes.
STEP 4 – Define physical bounds of the process.
What components are considered in the fault tree?

28
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – BEFORE YOU START DRAWING THE TREE, Preliminary Steps

STEP 5 – Define the equipment configuration.


What valves are open or closed?
What are liquid levels in tanks?
Is there a normal operation state?
STEP 6 – Define the level of resolution.
Will the analysis consider only a valve or is it necessary to
consider all valve components?

29
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – DRAWING THE TREE


STEP 1 – Draw the top event at the top of the page.
STEP 2 – Determine the major events (intermediate, basic, undeveloped or
external events) that contribute to the top event.
STEP 3 – Define these events using logic functions.
a. AND gate – all events must occur in order for the top event to occur
b. OR gate – any events can occur for the top event to occur
c. Unsure? If the events are not related with the OR or AND gate, the
event likely needs to be defined more precisely.
STEP 4 – Repeat step 3 for all intermediate, undeveloped and external
events. Continue until all branches end with a basic cause.
30
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Chemical Reactor Shutdown Example


A chemical reactor is fitted with a
high pressure alarm to alert the
operator in the event of dangerous
reactor pressures. An reactor also
has an automatic high-pressure
shutoff system.
The high pressure shutoff system
also closes the reactor feed line
through a solenoid valve.
The alarm and feed shutdown
systems are installed in parallel.
31
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Fault Trees – Chemical Reactor Shutdown Example


Define the Problem
TOP EVENT = Damage to the reactor by overpressure
EXISTING CONDITION = Abnormal high process pressure
IRRELEVANT EVENTS = Failure of mixer, electrical failures,
wiring failures, tornadoes, hurricanes, electrical storms
PHYSICAL BOUNDS = Process flow diagram (on left)
EQUIPMENT CONFIG = Reactor feed flowing when solenoid
valve open
RESOLUTION = Equipment shown in process flow diagram

32
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

TOP EVENT Reactor Overpressure


and Damage

1. Start by writing out the top event on


Note that you can only have the top of the page in the middle.
Reactor Overpressure, if
“Reactor Pressure Increasing” is
an intermediate or undefined
condition; the system passes
through pressure increasing to
overpressure

33
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

TOP EVENT Reactor Overpressure

AND A

High Pressure Emergency


Alarm Indicator Shutdown failure
Failure

2. The AND gate notes that two events must occur in


parallel. These two events are intermediate events.

34
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

TOP EVENT Reactor Overpressure


3. The OR gates
define one of two AND A
events can occur.
Alarm Indicator Failure Emergency Shutdown Failure

OR B OR C

Pressure Pressure Pressure Solenoid


Switch 1 Indicator Switch 2 Valve
Failure Light Failure Failure Failure
35
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

TOP EVENT Reactor Overpressure


4. We’ll give a
number to each of AND A
the basic causes &
basic events. Alarm Indicator Failure Emergency Shutdown Failure

OR B OR C

Pressure Pressure Pressure Solenoid


Switch 1 Indicator Switch 2 Valve
Failure Light Failure Failure Failure
1 2 3 4
36
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Chemical Reactor Shutdown Example – Determining Minimal Cuts


After drawing a fault tree, we can determine minimum cut sets which are sets of
various unique event/condition combinations, without unnecessary additional
events/conditions which can give rise to the top event.
Each minimal cut set will be associated with a probability of occurring – human
interaction is more likely to fail that hardware.
It is of interest to understand sets that are more likely to fail using failure
probability. Additional safety systems can then be installed at these points in the
system.
Example: The combination of A and B and C can lead to the Top Event. However,
A and B alone can lead to the Top Event, and C is unnecesary
37
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Chemical Reactor Shutdown Example – Determining Minimal Cuts


1. Write drop the first logic gate below the top
event.

2. AND gates increase the number of events in


the cut set. Gate A has two inputs: B and C. The
AND gate is replaced by its two inputs.

AB C

38
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Chemical Reactor Shutdown Example – Determining Minimal Cuts


3. OR gates increase the number of sets. Gate B
has inputs from events 1 and 2. Gate B is replaced by
one input and another row is added with the second
input.

AB1 C
2 C
4. Gate C has inputs from basic events 3 and 4.
Replace gate C with its first input and additional rows
are added with the second input.

39
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Chemical Reactor Shutdown Example – Determining Minimal Cuts


4. Gate C has inputs from basic events 3 and 4.
Replace gate C with its first input and additional rows
are added with the second input. The second input
from gate C are matched with gate B.

AB1 C 3
2 C 3
1 4
2 4
40
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Chemical Reactor Shutdown Example – Determining Minimal Cuts


5. The top event can occur following one
of these cut sets:

Events 1 and 3
Events 2 and 3
Events 1 and 4
Events 2 and 4

41
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Process equipment failures occur following interactions of individual components
in a system. The type of component interaction dictates the probability of failure.
A component in a system, on average, will fail after a certain time. This is called
the average failure rate (µ, units: faults/time).
Using the failure rate of a component, we can determine its reliability and
probability of failure.
Failure Rate Probability Reliability

µ P(t) t
R(t) 1-P(t)
P(t) = ò f (t)dt
t=0

Time, t Time, t Time, t 42


Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Failure Rate Reliability Probability

t
µ R(t) 1-P(t) P(t) P(t) = òf (t)dt
t=0

Time, t Time, t Time, t

R(t) =exp(- m t) P(t) = 1- R(t)


P(t) =1 - exp(- m t)

43
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis

PFDavg – Probability of failure on Demand, averaged over time

1 t=T PFD at any given time, averaged


PFDavg =
T
ò t=0
PFD(t)dt over a period of time

Reliability, R(t), is the Probability of Success,


averaged over a specified period of time

44
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Component Failure Rate, µ R(t) P(t)
Failure data for typical (faults/year)
process components can be Control Valve 0.60 0.55 0.45
obtained from published Flow Measurement
Fluids 1.14 0.32 0.68
literature. Solids 3.75 0.02 0.98
Flow Switch 1.12 0.33 0.67
Hand Valve 0.13 0.88 0.12
Indicator Lamp 0.044 0.96 0.04
Level Measurement
Liquids 1.70 0.18 0.82
Solids 6.86 0.001 0.999
pH Meter 5.88 0.003 0.997
Pressure Measurement 1.41 0.24 0.76
Pressure Relief Valve 0.022 0.98 0.02
Pressure Switch 0.14 0.87 0.13
Solenoid Valve 0.42 0.66 0.34
Temperature Measurement
Thermocouple 0.52 0.59 0.41 45
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Component Failure Rate, µ R(t) P(t)
The failure probability and (faults/year)
reliability of a component Control Valve 0.60 0.55 0.45
can be calculated from its Flow Measurement
Fluids 1.14 0.32 0.68
known failure rate. Solids 3.75 0.02 0.98
Flow Switch 1.12 0.33 0.67
Hand Valve 0.13 0.88 0.12
Indicator Lamp 0.044 0.96 0.04
Level Measurement
Liquids 1.70 0.18 0.82
Solids 6.86 0.001 0.999
pH Meter 5.88 0.003 0.997
Pressure Measurement 1.41 0.24 0.76
Pressure Relief Valve 0.022 0.98 0.02
Pressure Switch 0.14 0.87 0.13
Solenoid Valve 0.42 0.66 0.34
Temperature Measurement
Thermocouple 0.52 0.59 0.41 46
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


We’ve discussed the failure probability of individual components.Failures in chemical
plants, result from the interaction of multiple components.We need to calculate the
overall failure probability and reliability of these component interactions (R = 1 – P)

Components in Parallel - AND gates


Failure Probability P  Reliability n

P =Õ P
n
P R =1 - Õ (1 - Ri ) R
i
P 2 i=1 R2
n is the totali=1number of components n is the total number of components
Pi is the failure probability of each component Ri is the reliability of each component

Components in Series – OR gates


Failure Probability Reliability
n
P  n

P =1 - Õ (1 - P ) i P R =Õ Ri R
i=1
P2 i=1 R2 47
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Calculations for failure probability can be simplified for systems comprised of
only two components
n
P =1 - Õ (1 - Pi )
i=1

Can be expanded to:


P(A or B) = P(A) + P(B) – P(A and B) = P(A) + P(B) – P(A)*P(B)

or A A and B at the
  &   same time
A B
B

48
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Quantifying the Probability of the Top Event


Two methods are available:
1. The failure probability of all basic, external and undeveloped events are written on
the fault tree diagram.
2. The minimum cut sets can be used. As only the basic events are being
evaluated in this case, the computed probabilities for all events will be larger than
the actual probability.

49
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Reactor Example – Quantifying the Probability of the Top Event


Fault Tree Diagram Method
We must first compile the reliability
and failure probabilities of each basic
event from tables.

Remember P = 1 - R
Component Reliability, Failure Probability,
R P
Pressure Switch 1 0.87 0.13
Alarm Indicator 0.96 0.04
Pressure Switch 2 0.87 0.13
Solenoid Valve 0.66 0.34
System condition
“Reactor Pressure Increasing”
50
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Reactor Example – Quantifying the Probability of the Top Event


Fault Tree Diagram Method AND 2gate A
R =1 - P
P =Õ Pi
i=1
P =1 - 0.0702
P =(0.135) * (0.426) P =0.93
OR gate B P =0.0702
2
R =Õ Ri OR gate C
i=1
R =(0.87)
R =(0.87) * (0.96) (0.66)=0.574
R =0.835 P = 1-0.574 =
0.426
P =1 - R =0.165
The total failure
probability is
P = 0.13 P = 0.04 P = 0.13 P = 0.34 0.0702.
R = 0.87 R = 0.96 R = 0.87 R = 0.66
51
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Reactor Example – Quantifying the Probability of the Top Event


Direct Method

P(B) = P(1 or 2) =P(1) + P(2) - P(1) * P(2) =0.13 + 0.04 - 0.13 * 0.04 =0.1648
P(C) = P(3 or 4) =P(3) + P(4) - P(3) * P(4) =0.13 + 0.34 - 0.13 * 0.34 =0.4258
P(A) = P(B and C) =P(B) * P(C) =0.1648 * 0.4258 =0.0702

52
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Reactor Example – Quantifying the Probability of the Top Event


Minimum Cut Set Method

Events 1 and 3 P(1 and 3) = (0.13)(0.13) = 0.0169


Events 2 and 3 P(2 and 3) = (0.04)(0.13) = 0.0052
Events 1 and 4 P(1 and 4) = (0.13)(0.34) = 0.0442
Events 2 and 4 P(2 and 4) = (0.04)(0.34) = 0.0136
TOTAL Failure Probability = 0.0799
Note that the failure probability calculated using
minimum cut sets is greater than using the
actual fault tree. 53
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Words of Caution with Fault Trees


• Fault trees can be very large if the process is complicated. A real-
world system can include thousands of gates and intermediate
events.

• Care must be taken when estimating failure modes – best to get


advice from experienced engineers when developing complicated
fault trees. It is important to remember that fault trees can differ
between engineers.

• Failures in fault trees are complete failures – a failure will or will


not failure, there cannot be a partial failure.

54
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Moving from Control Measures to Consequences


• We can move from thinking about the basic events that will lead to a
top event to the consequence that can follow the top event. This can
be done using Event Trees.

• Fault Tree Analysis starts with a top event and then works backward
to identify various basic causes using “and/or” logic

• Event Tree Analysis starts with an initiating event or cause and works
forward to identify possible various defined outcomes

55
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees
Failures and
Successes of Various
Initiating Various Defined
Event Intervening Final
(Cause) Safety
Outcomes
- these Systems/Actio
ns - These will
have an have
- These have
associated associated
an average
frequency Probability on frequencies
Demand

When an accident occurs, safety systems can fail or succeed.


Event trees provide information on how a failure can occur.

56
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Typical Steps


1. Identify an initiating event
2. Identify the safety functions designed to deal with the initiating event
3. Construct the event tree
4. Describe the resulting sequence of accident events.

The procedure can be used to determine probability of


certain event sequences. This can be use to decide if
improvement to the system should be made.

57
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example

What happens if
there is a loss of
coolant?

High Temperature
Alarm
58
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


Safety operations following the
loss of coolant (the initiating
event)
High temp alarm alerts operator
0.01 failures/demand
Operator acknowledges alarm
0.25 failures/demand
Operator restarts cooling system
0.25 failures/demand
Operator shuts down reactor
High Temperature 0.1 failures/demand
Alarm
59
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


Safety operations following the
loss of coolant (the initiating
event)
High temp alarm alerts operator
We can note 0.01 failures/demand
the probability
of failure on Operator acknowledges alarm
demand of 0.25 failures/demand
each safety
function Operator restarts cooling system
0.25 failures/demand
Operator shuts down reactor
High Temperature 0.1 failures/demand
Alarm
60
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


Safety operations following the
loss of coolant (the initiating
event)
High temp alarm alerts operator [B]
And assign an 0.01 failures/demand
ID to each
operation Operator acknowledges alarm [C]
0.25 failures/demand
Operator restarts cooling system [D]
0.25 failures/demand
Operator shuts down reactor [E]
High Temperature 0.1 failures/demand
Alarm
61
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example

1. Start by writing out the initiating


event on the left side of the page, in
the middle.

Loss of coolant
(initiating event)

62
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example

1. Start by writing out the


initiating event on the left side
of the page.
2. Note the frequency of this
event (occurrences per year)

Loss of coolant
(initiating event)
1 occurrence/year

63
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


ID B (High Temp Alarm Alerts Operator) 3. We’ll call the initiating event A and
0.01 failures/demand also note the occurrence per year.
4. Draw a line from the initiating event
to the first safety function (ID B) – a
Success straight line up indicates the results for
of Safety a success in the safety function and a
A Function B failure is represented by a line drawn
down.
1
Failure 5. We can assume the high temp alarm
Loss of coolant will fail to alert the operator 1% of the
(initiating event) of Safety time when in demand OR 0.01
Function B failure/demand.(This is a probability of
1 occurrence/year
failure on demand)
64
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


Safety Function 7. Consider Safety Function B (operator
ID B (High Temp Alarm Alerts Operator) alerted by temperature safety alarm).
0.01 failures/demand There are 0.01 failures/demand of this
function.
Success 0.99
of Safety
Function B
A Success of Safety Function B
= (1- 0.01)* 1 occurrence/year
1 = 0.99 occurrence/year
Failure
Loss of coolant of Safety
(initiating event) Function B Failure of Safety Function B
1 occurrence/year = 0.01 * 1 occurrence/year
0.01 = 0.01 occurrence/year
65
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

ID C (Operator Acknowledges Alarm)


0.25 failures/demand

ID B Success Success of Safety Function C


= (1-0.25 failures/demand)*0.01
0.0075
occurrence/year
Success = 0.0075 occurrence/year
0.99 Failure
Failure of Safety Function C
0.0025 = 0.25 failures/demand *0.01
A
occurrence/year
1 = 0.0025 occurrence/year

Loss of coolant Failure


(initiating event) 0.01 8. If the safety function does not apply
1 occurrence/year for the scenario, the horizontal line
continues through the function.
66
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie
ID B ID C ID D (Cooling System Restarted)
0.25 failures/demand
Success of Safety Function D
0.7425 = (1- 0.25 failures/demand)* 0.99
= 0.0075 occurrence/year
0.0075 0.2475
Success Failure of Safety Function D
0.99 = 0.25 failures/demand* 0.99
= 0.0075 occurrence/year
Loss of A 0.0025
coolant
(initiating
event)
1
Failure Similar calculation for
1
occurrence/ remaining scenarios.
0.01
year

67
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie
ID B ID C ID D ID E (System Shutdown)
0.1 failures/demand
Continue
0.7425 Operation
0.0075 0.2227 Shutdown
Success 0.2475
0.99 0.02475
Runway
Runway
0.0025
A
1
Failure Runway
0.01

68
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie
ID B ID C ID D ID E (System Shutdown)
0.1 failures/demandSequence of Safety Function Failures
Continue A
0.7425 Operation
0.0075 0.2227 Shutdown AD
Success 0.2475
0.99 0.02475
Runway ADE
Runway AC
0.0025
A
1
Failure Runway AB
0.01

69
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie
Sequence of Safety Occurrences/year
Function Failures
Continue Operation A 0.7425
9. The initiating event is used to indicate
Shutdown AD 0.2227 by the first letter in the sequence (ie. A).
10. The sequence ABE indicates an the
Runway ADE 0.02475 initiating event A followed by failures in
safety functions B and E.
11. Using the data provided on the
Initiating Event frequency and the
Probability on Demand of Failure or
Runway AC 0.0025
Success for the safety functions, the
overall runway and shutdown
occurrences per year can be calculated.

Runway AB 0.01
70
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie
Sequence of Safety Occurrences/year
Function Failures
Continue Operation A 0.7425 Total Shutdown
Occurrences per year
Shutdown AD 0.2227
= 0.2227 occurrences/year
= Once every 4.5 years
Runway ADE 0.02475

Total Runway
Runway AC 0.0025 Occurrences per year
= 0.02475 + 0.0025 + 0.01
= 0.03725 occurrences/year
= Once every 26.8 years

Runway AB 0.01
71
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


What is expected if there is an
accident due to a loss of coolant?

• A system shutdown will occur


one every 4.5 years.
• A runway will occur one every
28.6 years.

High Temperature
Alarm
72
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees – Chemical Reactor Example


What happens if there is an accident
due to a loss of coolant?

• A system shutdown will occur one every


4.5 years.
• A runway will occur one every 28.6
years.
A runway reaction once every 30 years is
considered to high! Installation of a high
temperature automatic reactor shutdown
High Temperature function can decrease this occurrence rate.
Alarm
73
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Summary of Event Trees


• The objective is to identify important possible safety failures from an
initiating event that could have a bearing on risk assessment.

• Primary purpose is to modify the system design to improve safety.

• Real systems are complex which can result in large event trees.

• The risk analyst MUST know the order and magnitude of the potential
event consequences in order to complete the event tree analysis.

• The lack of certainty that a consequence will result from a selected


failure is the major disadvantage of event trees.
74
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees and Fault Trees

s
Con
trol a sure
Eve
M M e ce 6
ery
nt 1
ea s urr en
ure
s ec ov Occ
ce 5
Event
2 R Occurren

Initiating Event 3 Fault Critical Event Occurrence 4


Tree Event Tree Occurrence 3 Consequences
Events Event 4
Occur
rence
Event 5 Occ 2
ur r
e nc
nt 6 e1
Eve

Working Backwards Working Forwards


Deduction Process Induction Process 75
Hazardous Modelling Quantitative
Risk Final
Review Material Frequency
Consequence Source Hazard Effect Estimation Thoughts
Release Analysis
Fault Trees Event Trees Bow-Tie

Event Trees and Fault Trees = BOW-TIE

s
Con
trol a sure
Eve
M M e ce 6
ery
nt 1
ea s urr en
ure
s ec ov Occ
ce 5
Event
2 R Occurren

Initiating Event 3 Fault Critical Event Occurrence 4


Tree Event Tree Occurrence 3 Consequences
Events Event 4
Occur
rence
Event 5 Occ 2
ur r
e nc
nt 6 e1
Eve

Working Backwards Working Forwards


Deduction Process Induction Process 76
Sensitivity Expected Monetary Value (EMV)

Sensitivity Expected Monetary Value (EMV)


analysis is about coming up with possible scenarios to
deal with a risk and assessing how much each of those
paths will cost the project
Example : Expected Monetary Value (EMV)
Modelling And Simulation
• Modeling and simulation translate detailed
uncertainties of the project into their potential
impact on project objectives
• Monte Carlo simulation is used to arrive at a likelihood of
achieving specific cost or schedule targets
• This technique iteratively computes the model several times
from randomly selected input values.
Example : Modelling And Simulation (Monte Carlo Total
Project Cost )
Important Note : Quantitative Risk Analysis

Quantitative Risk Analysis may be skipped :


• For Risk With Low Priority
• For Risk Requiring Urgent Response
• When There is no Sufficient Data

You might also like