<Division> Project Charter: <Project Name>

Team Members (Div/Dept.): 1. Tarik-commercial


Project Sponsor (PS): Md. Abdur Rahman 1. Mehedi-Logistics support 2. Ashik-MIS
Project Manager (PM): Md. Shariful Islam 2. Bipul – Eng. 3. Dewan-Audit
Tech/Functional Lead (T/FL): Md. Fuad 3. Salim-Lrgal 4. Kawsar-design
4. Mustaq-Finance

Budget Info [Mn BDT]


• CapEx:180000 Start Date:01-01-2021
• OpEx:100000 End Date:31-12-2021
• Total:280000

Key Objective
It gives a primer depiction of jobs and obligations, traces the task's key objectives, distinguishes the primary partners, and characterizes the
authority of the undertaking chief. A venture sanction should go about as an agreement between the venture support, key partners and the task
group.

Key Deliverables Serial Deliverable Planned completion date

1  Investment approval 31-12-2020 


2  Location 30-01-2021 
3  Logistics 30-01-2021 

Charter Sign-Off date: <Date>


Project Definition Doc Sign-Off date: <Date>
Project Charter 1
Head office in Dhaka-Risks, Dependencies, Out of Scope

Risks

Serial Risk Description Mitigation plan

1 Design change Monitor Properly

We will provide actual information and maintain proper constitution to get


2 RAJUK Approval
approval easily

3 Finance Maintain consistency

Dependencies
• Commercial
• Logistics

Out of Scope Declaration


• WTP installation
• Alternative electricity
Project Charter 2
<Project Name>

Proposed by Recommend by

Project Manager Project Sponsor

______________________ _______________________
Name:Md.Shariful Islam Name:Md. Abdur Rahman
Designation:PM Designation: COO
Date:05-12-2020 Date:05-12-2021

Approved by

Managing Director & CEO

_______________________
Name:Sushmita
Date:CEO

Project Charter 3