Professional Documents
Culture Documents
06 - PMP Topic 6 - Time Management
06 - PMP Topic 6 - Time Management
06 - PMP Topic 6 - Time Management
4
Process Group and Knowledge Area Mapping
Project Management Process Groups
…
5. Project Scope 5.1 Plan Scope 5.5 Validate Scope
Management Management 5.6 Control Scope
5.2 Collect
Requirements
5.3 Define Scope
5.4 Create WBS
6. Project Time 6.1 Plan Schedule 6.7 Control
Management Management Schedule
6.2 Define
Activities
6.3 Sequence
Activities
6.4 Estimate
Activity Resources
6.5 Estimate
Activity Durations
6.6 Develop
Schedule
7. Project Cost 7.1 Plan Cost 7.4 Control Costs
Management Management
7.2 Estimate Costs
7.3 Determine
Budget
…
• Many questions on the exam will test your knowledge of specific terms and
nuances
• Learning the formula and techniques for diagramming is a must (as well as how
to apply them)
• Tip: During the exam tutorial, write formulas on scrap paper
• You need to know the main outputs that are produced during each of the six
processes
Why it is important
• It provides guidance and direction on how the project schedule will be
managed throughout the project.
How it works
• The schedule management plan is a component of the project
management plan.
• Formal or informal
• Defines how schedule contingencies will be reported and assessed.
Project Charter
• Issued by the project initiator or sponsor, formally authorizes the existence of a
project, and provides the project manager with the authority to apply
organizational resources to project activities.
• Defines the summary milestone schedule and project approval requirements
that will influence the management of the project schedule.
Analytical Techniques
• Includes scheduling methodology, scheduling tools and techniques, estimating
approaches, and project management software
Meetings
• Meetings with stakeholders to discuss and develop the schedule management
plan
Why it is important
• To gain a detailed understanding of how and when the work is accomplished.
The activity list is an essential input into building the schedule.
How it works
• The process of Define Activities is often performed as soon as the scope
baseline has been created.
• The difference between work packages in a WBS and an activity list is that the
activity list is more granular and is decomposed into individual schedule
activities.
Scope Baseline
• Consists of the approved project scope statement, the WBS, and the WBS
dictionary
• Each resulting schedule activity should tie back to a specific deliverable in the
scope baseline
Expert Judgment
• May come from numerous sources, including team members, consultants and
functional managers
Activity Attributes
• May be stored with the activity list or in a separate document
• Typically created after the initial activity list has been created
Milestone List
• Key project milestones are produced as part of this process
• Milestones may be related to imposed dates or schedule constraints
Why it is important
• Sequence Activities is the planning process in which network diagrams are
produced
How it works
• A network diagram is a picture in which each activity is drawn in the order it must
be performed (including dependencies) and the amount of time each activity
takes is represented with numbers.
• The process of Sequence Activities must be performed after Define Activities
and before Develop Schedule
Activity List
• The activities to be arranged and sequenced into a diagram
Activity Attributes
• Contain additional information about each activity that may influence how it is sequenced
Milestone List
• May have scheduled dates for specific milestones, which may influence the way activities
are sequenced
4 1
A B
8
Start Finish
C
There are four types of logical relationships between activities using the
precedence diagramming method:
• Finish-to-start (FS)
• An activity must finish before the successor can start
• This is the most commonly used relationship
• Start-to-start (SS)
• An activity must start before the successor can start
• Finish-to-finish (FF)
• An activity must finish before the successor can finish
• Start-to-finish (SF)
• An activity must start before the successor can finish
• This dependency is rarely used.
Copyright © 2013 Deloitte Development LLC. All rights reserved. 26
Process 3: Sequence Activities – Tools & Techniques
Dependency Determination
• Dependencies are those things that influence which activities must be
performed first
• Mandatory Dependencies
• A mandatory dependency is one that cannot be broken
• Also known as Hard Logic,
• Discretionary Dependencies
• Are not always true and often are the result of best practices
• typically based on historical information, expert judgment and best practices
• Also known as Soft Logic or Preferred Logic
• External Dependencies
• Dependencies that must be considered but are outside of the project’s control and
scope
• Internal Dependencies
• Involve a precedence relationship between project activities and are generally inside
Copyright © 2013 Deloitte Development LLC. All rights reserved. 27
the project team’s control
Process 3: Sequence Activities – Tools & Techniques
Leads and Lags
• A lead is one activity being able to start before an activity preceding it is finished
• Leads and lags, and the rationale behind them, must be clearly explained and
documented
Why it is important
• Provides an understanding of the number of resources required to complete an activity
and determine how long they will be used for that activity
How it works
• Uses the activity list and activity attributes, so the process must follow the Define
Activities process
• Output is used to build the project schedule
• Process often goes hand in hand with Estimate Costs, since cost and time are so
closely linked
7. Enterprise Environmental
Factors
8. Organizational Process
Assets
Activity List
• Each activity will be evaluated and the resources will be estimated for it
Activity Attributes
• Contains additional information about each activity that may influence how
resources are estimated
Resource Calendars
• Resources may include both physical and human resources and their availability
needs to be factored into the process
• Provides dates when resources will be available
Risk Register
• Risk events may impact the resource selection and availability
Copyright © 2013 Deloitte Development LLC. All rights reserved. 33
Process 4: Estimate Activity Resources – Inputs
Activity cost estimates
• Cost of resources may impact resource selection
Alternative Analysis
• Identifying alternative ways to complete the activity
• Example: Purchasing software vs. building in house
Bottom-Up Estimating
• Analyzing individual activities to estimate their resource requirements, then
aggregating those resources requirements
Why it is important
• Primary input into creating the schedule
How it works
• Performed after the activity resource requirements have been gathered and
before the schedule has been developed
Activity List
• Each activity will be evaluated to determine its duration
Activity Attributes
• Contain additional information about each activity
Resource Calendars
• Influence the duration of schedule activities due to the availability of specific
resources, type of resources, and resources with specific attributes
Copyright © 2013 Deloitte Development LLC. All rights reserved. 43
Process 5: Estimate Activity Durations – Inputs
Project Scope Statement
• Contains the constraints and assumptions for the project that can affect duration
estimation
Risk Register
• Risk register provides list of risks, along with the results of risk analysis and risk
response planning
Analogous Estimating
• Also known as Top-Down Estimating
• Where an activity from a project previously performed within the organization is
used to help estimate another activity duration
• Used to estimate project duration when there is a limited amount of detailed
information about the project
Parametric Estimating
• An algorithm is used to calculate cost or duration based on historical data and
project parameters
• Uses a statistical relationship between historical data and other variables
• Works well for activities that are either linear or easily scaled
• Example: If one team can install 100 feet of fence in one day, then it would take 10
teams to install 1,000 feet of fence in one day
Copyright © 2013 Deloitte Development LLC. All rights reserved. 45
Process 5: Estimate Activity Durations – Tools & Techniques
Three-Point Estimating (PERT)
• A method to determine the expected duration of a project or activity
• Uses three data points for the duration: Optimistic (O), Pessimistic (P), Most Likely (M)
• Based on assumed distribution, two methods are used: Beta distribution and Triangular
distribution
• On the exam, assume a Beta Distribution unless otherwise specified in a question
• Standard deviation identifies a range of time an activity may take (e.g. 4 weeks +/- 3 days)
• A larger standard deviation means more risk and more unknowns,
Sample Exercise: Project consists of two activities (A & B) - What’s the project duration,
standard deviation, and variance?
Activity A Activity B
P=7, M=4, O=1 P=14, M=8, O =2
Reserve Analysis
• Contingency reserves, sometimes referred to as time reserves or buffers, are
added into the project schedule to account for schedule uncertainty
• Contingency reserves are for “known-unknowns” and are included in the
schedule baseline
• Management reserves are for “unknown-unknowns” and are not included in the
schedule baseline
Why it is important
• The schedule is one of the most important parts of the project plan (it is
not the project plan though)
How it works
• Performed after all the other time management planning processes
• Prior to Determine Budget
Activity List
• Activities that will be included in the schedule model
Activity Attributes
• Accompanies the activity list and includes expanded activity information
Resource Calendars
• Contain information on the availability of resources during the project
Risk Register
• Contains risk characteristics that will affect the schedule model
Scheduling Tool
• Contain the schedule model
• Expedite the scheduling process by generating start and finish dates based on
the inputs of activities, network diagrams, resources and activity durations
Project Schedule
• An output of a schedule model that presents linked activities with planned dates,
durations, milestones, and resources
• Includes a planned start and finish date for each activity
• The project schedule is often presented in one of the following forms:
• Bar Charts (Gantt Charts): Activities are represented as horizontal bars along an x-axis
calendar
• Milestone Chart: Similar to a bar chart, but only represents key events/deliverables for
the project
• Project Network Diagram: Presented in the activity-on-node diagram format showing
activities and relationships with or without a time scale
Start End
Project Calendars
• Identifies the working days and shifts that are available for activities
Why it is important
• The schedule should be monitored continuously against the actual work
performed to ensure that things stay on target
How it works
• Schedule changes are not only reacted to, but the schedule is controlled
proactively
• PM should be proactive and influence changes before they affect the project
• Performed throughout the life of the project from the moment the schedule is
developed until all scheduled activities have been completed
Project Schedule
• The most recent version, including updates, completed activities, and started
activities as of the report date
Schedule Data
• Data that is reviewed and updated in the Control Schedule process
Schedule Compression
• Used to find ways to bring project activities that are behind into alignment with
the plan by fast tracking or crashing the schedule
Scheduling Tool
• Used in conjunction with manual methods or other project management
software to perform schedule network analysis to generate an updated project
schedule
Schedule Forecasts
• Based on the project’s past performance and expected future performance
• Includes earned value performance indicators that could impact the project
Change Requests
• May be needed due to schedule variance analysis, along with review of progress reports,
results of performance measures, and modifications to the project scope or project
schedule
4 8 3
Activity Activity Activity
5 B D E
Start
Activity Float = 3 Float = 0 Float = 0 Finish
A 7 4
Float = 0 Activity Activity
C F
Float = 0 Float = 7
Copyright © 2013 Deloitte Development LLC. All rights reserved. 71
Project Network Diagram– Example 3
4 6 9
1 4 5 10 13 21
A C E
8 11 12 17 18 26
7 5 12 2
1 7 8 12 13 24 25 26
B D F G
1 7 8 12 13 24 25 26
Float = 0 Float = 0 Float = 0 Float = 0
Start-A-C-E-Finish = 19
Start-B-D-E-Finish = 21
Start-B-D-F-G-Finish = 26
Copyright © 2013 Deloitte Development LLC. All rights reserved. 72
Debrief
Quiz
Please complete:
Time Management – Quiz 1