Professional Documents
Culture Documents
IPMEA Power Standard Guide - Draft
IPMEA Power Standard Guide - Draft
Power Standard
Implementation Guide
IPMEA, June 2012
Purpose & Objective
•This guide was developed by IPMEA in an effort to promote and
facilitate the implementation of the power standard
http://10.231.0.210/industrydata/headershc.asp
•To facilitate the implementation, each golden rule is detailed with its
reference documents
IPM 2
Content (click on each chapter for link)
How to complete the self assessment and tracker file
How to implement the golden rules
1: Optimize Cement Mill Power
7: Production Management
Kpi Calculation Power Cost Ratio
8: Mastering Quality Impact on Power Consumption
9: Mill Feed Size Control
10: Minimize Compressed Air
Prioritization
Mapping of main improvement plans-prioritize
IPM 3 3
How to complete the self assessment and
tracker file
Back to Content
IPM 4
Format Instructions
IPM 5
The date, champion name and the plant must be presented.
IPM 6
TheFormat of the numbers must be
percentage with 2 digits after comma.
IPM 7
The file should be contained the sheets of KPI’s and
action plan even empty.
IPM 8
Thenumber of columns and rows of
each workshop must be exactly the
same as the updated File
(PWR_tracker.xls) has published.
IPM 9
10 GR implementation Guide
IPM 101
10 Golden Rules Implementation
1: Optimize Ball Mill Power
Back to Content
IPM 1
10 Golden Rules Implementation
1: Optimize Ball Mill Power
•Plant has to set target of mill main drive KW according to filling degree and make top up not to loose
more than 2.5 % target mill KW
•Mill discharge bucket load target ( KW ) to be set by plant by optimizing circulating load of each
workshop on each product if workshop is close circuit. No target of bucket elevator load if workshop is
open circuit.
•Separator Feed to air ratio should be < 2.0 Kg/m3 but 1 st generation feed to air ratio couldn’t be
calculated because gas flow couldn’t be measured.
By Pass is calculated by Tromp curve, Tromp curve is plotted by Particle size distribution using laser of separator feed, fine
and reject material.
IPM 1
10 Golden Rules Implementation
1: Optimize Ball Mill Power
How to’s:
Links:
http://
http:// lo.lafarge.com/wps/myportal/InternalWebSite
lo.lafarge.com/wps/myportal/InternalWebSite? ?url
url
=http%3A%2F%2Fwebcementportal.lafarge.
=http%3A%2F%2Fwebcementportal.lafarge.co com+
m+
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
Status
2- Minimize False Air (0-100%)
Frequency Evaluation Criteria References
Set false air levels for each major equipment, inline with typical
100.00% % of equipment with targets (all kilns and mills) Training : Gas handling Training
ranges provided in 10 Golden Rules Booklet
Procedures : 1)
Check O2 level (or flow or temperature, etc, where O2 cannot How to measure false air
be used) with existing sensors and calculate false air level. 2) How to manage false air in the preheater
Ensure that full inspection of the preheater is done monthly
Conduct regular overall measurements, inspections and
100.00% monthly and any seal, open doors, leaking flaps are repaired.
repairs at least monthly
If O2 level check only or inspection only max 25%
No target set Max score 50%
If inspection & repairs max 75%
Back to Content
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
Doors
Seals
Flanges
Missing bolts Doors
Kiln Hood Seals
Tie Rod Seals Isolation
Clinker Chute Kiln Inlet Seal dampers
Feeding Point
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
Manage False Air
Prerequisite
Teamwork – Process, Maintenance and Production
Actions
Set target false air levels Typical Values
Preheater < 5%
Raw mill 20 - 40% *
Coal mill 20 - 30% *
Cement mills 30 - 50% *
Cooler exhaust < 10%
Develop inspection plan
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
Manage False Air
Conduct regular overall measurements, inspections and repairs (minimum monthly)
Measurement methods
• By oxygen difference where possible
• By temperature difference on mills and filters
• Direct measurement by volume flow difference
Support
Cement portal procedures
• How to measure false air
• How to control false air in the preheater
• How to adjust cooling air level & distribution
• How to measure gas composition by gas analyser
• How to check the air flow through the mill
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
CHECK LIST OF RECOMMENDATIONS IN PREHEATER
•minimize build-ups because false air amount generally increases with more negative pressure. Therefore, the pressure
-Before every shutdown in leaks are mapped and report sent to the maintenance team, work orders are made, O2 done
to check the in leaks situation. Continuous process
- Visual check A detailed optical check of all fittings and openings has to be done during a longer kiln stoppage.
This check can be supported by a light test of the finally sealed and repaired cyclone: either enter in the cyclone
during daylight and detecting leakage from inside or lighten the cyclone inside during night and detecting leakage
from outside.
-All leakages allowing for false air entrance such as poke holes, inspection doors, kiln sealing, downcomer cold air
damper, air cannons, process & online measurements point e.t.c. Should be located and properly sealed-up at any
available opportunity by the maintenance department in conjunction with Production and Process.
IPM 1
10 Golden Rules Implementation
2: Minimize False Air
By measuring oxygen:
Analysis on dry basis
2 points of measurement at the same time
If not possible, refer to a reliable plant O2 continuous monitoring
Plant sensor to be calibrated prior to measurements
Adapted sampling probe
Sampling in balloons
Air in-leaks calculation: valid when oxygen is not too high (don’t use if oxygen is 15% or over not
accurate)
Is there any combustion between the 2 measurement points?
IPM 2
10 Golden Rules Implementation
2: Minimize False Air
IPM 2
10 Golden Rules Implementation
3: Manage Idle Running
Back to Content
IPM 2
10 Golden Rules Implementation
3: Manage Idle Running
2. Work to reduce stops – stops & starts (monitor MTBF and RF KPIs)
increase power consumption significantly
6. Review shop SOPs during Shop shutdown or shop stopped , to limit essential working equipment.
Mainly concerns are fans, transport equipment and filters (but also check compressed air purging and air
blaster sequences)
Before making changes assess any potential negative impacts to be sure that no safety and or reliability
risks are introduced.
Roberta Power
Reduction program Nov2009
IPM 2
10 Golden Rules Implementation
Kpi Calculation Equipment Idling
Where :
Nominal Load Capacity = Power consumption measured at nominal shop production in KWH
Calculated once and recorded
Idle Load Capacity = Power consumption measured when the shop is down in KWH
There should be a meter in the control system to integrate the power consumed in workshop while
Main drive of workshop is down
http://
lo.lafarge.com/wps/myportal/InternalWeb
Site?url
=http%3A%2F%2Fwebcementportal.lafar
ge.com++
Back to Content
IPM 2
10 Golden Rules Implementation
4: Optimize Vertical Mill Power
Frequency
•Weekly
Evaluation Criteria
•If followed only with no corrective actions Max score 50%
•If followed closely with corrective actions taken as necessary Max score 100%
Reference Document
•How to monitor the performance of a VRM
Guidelines
1.First step is to identify which operating parameters are essential and required to track mill performance.
These parameters are sufficient to give a picture of the mill performance.
( A reference of this list of parameters are identified in the supporting document : How to monitor performance of a vertical mill)
2.Identify the target values for each of these parameters (Setting the reference targets are based on
experience, or from supplier documents)
3.Extract the values of the parameters (using IP 21 or other control system) on hourly average basis
4.On weekly basis perform an analysis of the data against the target values
5.Assess the possible reasons for any drift in values from target
6.Based on the assessment results, identify the required corrective actions and communicate with
concerned teams.
IPM 2
10 Golden Rules Implementation
4: Optimize Vertical Mill Power
Frequency
•Monthly
Evaluation Criteria
•If inspection only with no corrective actions Max score 50%
•If done with corrective actions taken as necessary Max score 100%
Reference Document
•How to do an on-stop vertical mill inspection
How to do an
on-stop vertical mill inspe
Guidelines
IPM 2
10 Golden Rules Implementation
4: Optimize Vertical Mill Power
Frequency
•Yearly (minimum)
Evaluation Criteria
•Wear measurement only max score 50%
•Wear measured and Dam ring adjusted correctly max score 100%
Reference Document
•How to adjust the dam ring of a vertical mill
Guidelines
IPM 2
10 Golden Rules Implementation
5: Efficient Gas Handling
Status
5- Handle Gas efficiently (0-100%)
Frequency Evaluation Criteria References
Inspect fans and dampers for build-ups, wear, Minimum Target : once per year during major Training : Gas
100.00%
misalignment etc… yearly repair. Handling Training
Target :Investigate any drift in
performance
Procedures :
if followed only and no drift correction
max 50% 1) How to measure
Follow power consumption for major fans 100.00% Monthly
if followed with no drift / drift corrected the efficiency of the main
then max 100% fans
TOTAL 100.00%
Back to Content
IPM 2
10 Golden Rules Implementation
5: Efficient Gas Handling
Introduction:
Gas handling is one of the most power consumable processes
across cement plant
• ID fan
• Mill fan
• Main fan
IPM 3
10 Golden Rules Implementation
5: Efficient Gas Handling
Frequency
Minimum Yearly
Evaluation Criteria
Reference Document
IPM 3
10 Golden Rules Implementation
5: Efficient Gas Handling
Frequency
Monthly
Evaluation Criteria
IPM 3
10 Golden Rules Implementation
5: Efficient Gas Handling
Frequency
Evaluation Criteria
Draw fan curves for the main fans every 2 years or less in case of
drift in performance
Reference Document
Fan-curve-example How to measure
Fan efficiency calculation sheet fan efficiency
IPM 3
10 Golden Rules Implementation
6: Power Monitoring
Back to Content
IPM 3
10 Golden Rules Implementation
7: Production Management
Back to Content
IPM 3
10 Golden Rules Implementation
Kpi Calculation Power Cost Ratio
Introduction
Power cost ratio is one of the Power
standards implementation KPI’s.
Definition
IPM 3
10 Golden Rules Implementation
Kpi Calculation Power Cost Ratio
Calculations
IPM 3
10 Golden Rules Implementation
Kpi Calculation Power Cost Ratio
Calculations Examples
Calculating the PCR for four tariffs contract; fixing the total
consumption while varying consumption allover the tariffs
intervals in each case
1.4
1.2
1
0.8
PCR
0.6
0.4
0.2
0
1 2 3 4 5 6 7 8
Cases
Microsoft Excel
Worksheet
Source or Foote note
IPM 3
10 Golden Rules Implementation
Kpi Calculation Power Cost Ratio
Conclusion
Lower values of the PCR mean that the plant is getting more
benefits from the different tariffs in the power contract.
IPM 3
10 Golden Rules Implementation
8: Mastering Quality Impact on Power Consumption
Other Guideline:
10 Golden Rules of raw mix
Back to Content
10 Golden Rules for Quarry
IPM 4
10 Golden Rules Implementation
9: Mill Feed Size Control
Other Document:
Ball mill operation for Cement and Raw Mix feed size limits
Back to Content
IPM 4
10 Golden Rules Implementation
10: Minimize Compressed Air
Back to Content
IPM 4
10 Golden Rules Implementation
10: Minimize Compressed Air
Improvement opportunities
Replace elbows by sweeping bends
Systematic leaks inspection, tagging & repair Monitor pressure at usage points
Monitor filter ΔP Variable speed compressor for control ? Change outlet filter elements regularly
Replace intake filters Control dryer using moisture sensor Condensate trap control – minimise leakage
IPM 4
10 Golden Rules Implementation
10: Minimize Compressed Air
Cooler Cleaning
IPM 4
10 Golden Rules Implementation
10: Minimize Compressed Air
Specific Cases
Homogenising compressors
Check effectiveness of blending
Consider conversion of high energy to low energy design
Pneumatic conveying
Check conveying velocity /pipe size / conveying air volume
Number of bends
Pipeline route
Bag filters
Optimisation of pulsing cycles
Check for leaking purge valves
EXAMPLE
Back to Content
Time/Cost of Implementation
IPM 474