Quality Induction Training-No 1

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 22

TARGET LLC

WELCOME

QUALITY INDUCTION

COMMITTED TO BUILD OMAN’S TOMORROW 1


Project Details

Name of the Project:EPC Works for Permanent Staff Accommodation at Nimr.

Client :Oman Gas Company.

Consultant :NEO.

MEP Sub-Contractor: Al Rafa

COMMITTED TO BUILD OMAN’S TOMORROW 2


OGC Specification Details

1.SP 1279-Specification for Civil and Building Construction.

2.SP 1282-Specificaion for Reinforced Concrete.

3.SP 1274-Specification for Civil Engineering materials.

4.SP 1275-Specification for design of Civil &Building works.

COMMITTED TO BUILD OMAN’S TOMORROW 3


Basic requirements in Reinforcement

Grade of Steel :High yield strength-500 n/mm2.

Importance of concrete cover

Concrete cover for reinforcement is required


to protect the rebar against corrosion and to
provide resistance against fire. The thickness
of coverdepends on environmental
conditions and type of structural member.

COMMITTED TO BUILD OMAN’S TOMORROW 4


Required Cover For Various Elements

COMMITTED TO BUILD OMAN’S TOMORROW 5


Minimum Lap/Splice length =50 d means 50 x diameter of bar.

1.Butterfly tie should provide.

2.Binding wire:16Gauge black annealed wire.

3.Avoid binding wire knots in cover zone area.

4.Rebar Cleaning.

5.No kink/joggling without permission.

COMMITTED TO BUILD OMAN’S TOMORROW 6


Reinforcement Works Do’s &don’t’s

Avoid gas cutting &


welding of
reinforcement

Do not stack
reinforcement
steel on the bare
ground

COMMITTED TO BUILD OMAN’S TOMORROW 7


Excavation & Back filling works

 Prior to Excavation check for Approved drawing for Survey Coordinates.

 Back filling shall be of Type-B Material of PDO Standard.

 All back fill materials Borrow pits has to be witnessed by OGC Site team
before using at site.

 Backfilling has to be carried out in layers of 150mm thick.

COMMITTED TO BUILD OMAN’S TOMORROW 8


FORM WORK

Approved Formwork system to be used.

COMMITTED TO BUILD OMAN’S TOMORROW 9


Formwork
1. Formwork for concrete shall be rigidly constructed with an approved
material and shall be true to both shape and dimensions specified.

2. Joints shall be sufficiently tight to prevent leakage of cement grout and to


avoid formation of fins or other blemishes.

3. 25 mm chamfers shall be formed on all external exposed


corners of concrete members.

4. Formwork shall be cleared out of all dust, wood shavings, dirt and other
extraneous material near blowing-out with compressed air before any
concrete is placed.

5. Mould oil approved by the Company shall be applied to faces of formwork


to prevent adherence of concrete.

COMMITTED TO BUILD OMAN’S TOMORROW 10


Do’s:
 
 As per Scheme / form work drawings.

 Clean the formwork & ply surfaces before being used.

 Remove the concrete laitance if any from the shutter surface

 Apply form release oil on shutters adequately using sponge rollers or


sprayer.

 Check for plumb, level and alignment of formwork.

 Ensure tightness of tie rods, supports, bracings etc.

 Thoroughly remove all ply pieces, saw dust and other wastes.

 Plug all openings and gaps using adhesive tape or by plywood piece.

COMMITTED TO BUILD OMAN’S TOMORROW 11


Don’ts
 
 Do not deviate from scheme drawings .

 Do not Use damage or warped shutters.

 Do not rest supports on loose earth and or over the temporary


supports

 Do not apply excess oil on plywood surface

 Do not use hessian cloths, gunny bags or empty cement bags to


plug openings and gaps.

 Do not cut wood / plywood on form works.

COMMITTED TO BUILD OMAN’S TOMORROW 12


CONCRETE

COMMITTED TO BUILD OMAN’S TOMORROW 13


CONCRETE VIBRATION

 Proper Needle Should be used for vibration.

 60mm needle to be used for concrete and 40mm


used only for section having less than 250mm.

 Concrete should be placed in layers not more than


300mm.

 Vibrators shall be inserted vertically and the


spacing shall be 450mm for 60mm needle and
300mm for 40mm needle.

 Vibrator shall not kept more than 10-15seconds in


a place.

 While second layer vibration half of the previous


layer thickness vibrator to be inserted.
COMMITTED TO BUILD OMAN’S TOMORROW 14
COMMITTED TO BUILD OMAN’S TOMORROW 15
CONCRETE CURING

 All freshly deposited concrete shall be protected


from premature drying and rapid temperature
change by the use of hessian cloth or protective
membrane for minimum 7 days.Casting dates
are mentioned to ensure.

 During the curing period, and thereafter as


conditions may require, concrete shall be
protected from mechanical damage,
disturbance,

 For the sides of columns, beams and walls, on


removal of formwork, the concrete shall
beclosely wrapped with wet Hessian and
enclosed with pigmented polythene sheeting.
COMMITTED TO BUILD OMAN’S TOMORROW 16
BLOCK WORK

Do’s and Don’ts

COMMITTED TO BUILD OMAN’S TOMORROW 17


COMMITTED TO BUILD OMAN’S TOMORROW 18
Lessons learned are the documented information that reflects both the positive
and negative experiences of a project. They represent the organization's commitment
to project management excellence and the project manager's opportunity to learn
from the actual experiences of others. And the mistakes and errors can be avoided in the
future projects.

COMMITTED TO BUILD OMAN’S TOMORROW 19


COMMITTED TO BUILD OMAN’S TOMORROW 20
COMMITTED TO BUILD OMAN’S TOMORROW 21
Remember !
Quality is in our hands

THANK YOU

COMMITTED TO BUILD OMAN’S TOMORROW 22

You might also like