PROJECT REPORT

Establishing a newly retail outlet


petrol pump/CNG station

Company Name: Total Parco Petrol


Pump
PC-1
It is an filling station located in
islamabad sector E-11

Provides Fuel and CNG gas

E-11 is a populated area having no facilty of a


petrol pump
TIME DURATION: One year(2015-2016)

SECTOR:
It comes under Public sector . Where
people will be facilitated a lot and their
transportation problems can be solved
PC- 2
AIMS AND OBJECTIVES:
Established in 1972

It was a successful joint venture between the two


brotherly countries pakistan and saudi Arabia

To meet the increasing demands of people for fuel and


gas

Also paying handsome dividends to the stakeholders


It can look with confidence to a much bright
future

Have started a mission of establishing


filling stations in every part of country and
especially islamabad.
STEPS :
Request to CDA to lease out a piece of land
(5kanal)

After approving a filling station liscence


from oil marketting company TOTAL
PARCO PAKISTAN LIMITED

Then permission from OGRA is taken


After these steps we will go for NOC (no
objection certificate)to Deputy
Commissioner (DC) of islamabad. (4-5)
months

After all these steps we go for construction


phase.
PC- 3
Lease period is for 33 years

Rent for first ten years is 3 lac

For second ten years is 4 lac

For remainning period is 4 lac 50 thousand


TOTAL COST is 41,446,800
approximately 41 million

Approved by CDWP (Central


Development Working Party)
ACCOUNT TYPE:

The account used will be pre-audit account


maintained by AGPR .
WORK/CASH PLAN
Building : Office block 1500 sqft cost 2400000

Tyre shop : 144 sqft cost 172800

Mosque: 625 sqft cost 1000000

4 washrooms: 120 sqft cost 144000

Ground T-tile: cost 2720000


Electrification: lumsum 1600000

Sanitary fitting work: Bore expences lumsum


1200000

Wapda transformer : 200KVA cost 1400000

Canopy: 4500 sqft cost 3510000 million

Dispencer units : 3800000


All the responsibilty of work is given to
contractor.
Item First Second Third Fourth month
descrip month month month
tion

Covere 40000 400000 800000 800000


d area 0 lac lac lac lac
sanitar _ _ _ 1200000
y

Tyre _ _ 172800 _
shop
Transfo _ _ _ 1400000
rmer
Mosqu _ 100000 _ _
e
COLLECTION OF FUNDS

Some part of funds (self investment ) about


60%.

Some part from loan (MCB bank) about


40%.The payback period is five years.
DESCRIPTION OF PROBLEMS IN E-11
No petrol pump facility
Illegal outlets (low quality water mixed fuel.
Ladies facing problems
No cabb facility
Drivers demanding high fares
sustainanbility
Life have become normal
Public transport have return
Satisfactory fares
Useful at time of emergency
No need to go to far places
Washing of cars from near place.
PC-4
Total cost : 41 million
Funds are utilized completely
Report is prepared and forwarded project
wing
Contractor to hand over the responsibility
to owner
Supplies are closed/stopped
Work is stopped and completed
INPUT OUTPUT BASELINE TARGETS TARGET
INDICATOR AFTER IMPACT
COMPL
41 million, To establish Due to People After
Total Parco a newly absence of would get establishing a
petrol retail outlet petrol pump fuel and gas petrol pump
pump. petrol in E-11 without any ,life of the
pump/CNG islamabad, struggle and people living in
station of people search. It E-11 islamabad
Total Parco living there will be a will become
Company in are facing successful normal. They
islamabad many retail outlet can easily fill
E-11 serious resulting in their cars and
problems. profit motorcycles
At time of women and with fuel and
emergency children gas. In general
they go to would not the drivers will
far places in go to far no longer
search of places in demand high
petrol pump search of fares.
Public public
transport is transport.
also absent.
PC-5
Report of completion of project is
submitted to Planning and development
division in order to let them know that
project is ready for providing its services to
public.

Now the owner will hire responsible and


qualified management for the running of
petrol pump .
THANK YOU FOR
LISTENING