Pulse Line OEE 2.7.x: Quick Intro & Admin Guide: For Training Purposes - MA Learning Bite
Pulse Line OEE 2.7.x: Quick Intro & Admin Guide: For Training Purposes - MA Learning Bite
Pulse Line OEE 2.7.x: Quick Intro & Admin Guide: For Training Purposes - MA Learning Bite
www.continental-corporation.com
All Rights Reserved
A IT MA
Table of Content
a Key Performance Indicator (KPI) for production and areas close to production
Availability
OEE
Quality Performance
EquipmentAvailability
OperatingTime
LoadingTime....
Performance
( IdealCycleTime PartsProduced )
OperatingTime
QualityRate
TotalPartsProduced FailureParts
TotalPartsProduced
Allows to Categorized Recorded Downtimes (with an web based user front end)
Time and Failure Analysis (recipe execution time, material tracking etc.)
Effective Online Monitoring, Reporting and Tracking with up-to-date WEB technology
OEE Reporting is based on cumulated values under Line OEE Trend Analysis is based on the Output and
the knode “BS1.1” (sum of all down and up time) Reference Equipment
* Note: Line OEE Reporting is available since Pulse Baseline 1 which is WW rolled out in 63 Locations
http://connext.conti.de/wikis/home?lang=en-us#!/wiki/W2ee58e8bb46c_4444_a969_a84ce9953c29/page/PULSE%20Ba
seline%20I%20-%20Complete
› Line OEE shows you the typical OEE key figures, but line based
The production line is defined through several single equipment and system border System border
IdealCT_EQ3.1 OK
Equipment 1 Equipment 2 Equipment 4 Equipment 5 Equipment 6 Equipment 7
GoodParts
OutputEQ
IdealCT_EQ1 IdealCT_EQ2 IdealCT_EQ4 IdealCT_EQ5 IdealCT_EQ6 IdealCT_EQ7
Equipment 3.2
IdealCT_EQ3.2
FailurePartsLine
› The availability will be calculated like for single equipment based on the defined line
reference equipment (EQ_REF).
OperatingTimeEQ _ REF
LineAvaila bility
LoadingTimeEQ _ REF
› The quality rate will be calculated with all fail parts of the line
LineQualityRate
GoodParts OutputEQ
GoodParts OutputEQ
GoodParts NOKParts
OutputEQ EQ
GoodParts OutputEQ FailurePartsLine
System border
The production line is defined through several single equipment and system border
EQ_REF EQ_OUT
OK GoodParts
Input Equipment 1 Equipment 2 Equipment 3 Equipment 4 Equipment 5 Equipment 6 OutputEQ =
988 parts
FailurePartsLine = 12 parts
Legend:
Data collection point
FailurePartsLine: NOK parts (runs) from all stations
GoodPartsEQ_OUT: OK parts (runs) from the defined Output Equipment
Quality Rate = 98,8 %
› The Performance will be calculated against the Operating Time of the defined Line
reference Equipment (EQ_REF).
› As ideal cycle time the maximum cycle time of all line related equipments. Parallel
equipments have to be considered.
OperatingTimeEQ _ REF
› In the following example the ct would be 20 sec. For parallel equipment, the ct has to be
divided through number of equipments: ct = 1/(1/30sec + 1/30sec + 1/30sec) = 10 sec
Line Equipment Ideal Cycle Time
Line 1 Equipment 1 OP10 10,0
Line 1 Equipment 2 OP20 30,0
Line 1 Equipment 3 OP20 30,0 Parallel machines
Line 1 Equipment 4 OP20 30,0 reference ct =10 sec
Line 1 Equipment 5 OP30 20,0
Line 1 Equipment 6 OP40 15,0 Highest cycle time in the OP
e.g. Product A = 20,0 sec/Line
Line 1 Equipment 7 OP50 8,0
Ct 30sec
1
IdealCycle Time Paralell
1 1 1
Ct 10 sec Ct 30sec Ct 20sec
CT PEQ 1 CT PEQ 2 CT PEQN
junction Ct 30sec
Parts Produced: Amount related to the product and selected time period
Operating Time: Total time related to the product and selected time period
A IT MA CEP 01/04/2021
Public P. Gal © Continental AG 34