Professional Documents
Culture Documents
Capacity Requirement Planning
Capacity Requirement Planning
Planning
1
Capacity
Capacity is the maximum output or volume a system can
produce, the maximum work that a system is capable of
doing in a given period of time.
2
Capacity
The basic questions in capacity planning are:
3
What is Capacity?
4
What is Capacity?
5
Capacity
Total (design) capacity
Maximum output rate or service capacity an operation,
process, or facility is designed
Effective capacity
Design capacity minus planned losses such as
meetings, preventive maintenance, lunch / natural call
breaks
Actual output
Rate of output actually achieved, cannot exceed
effective capacity. It minus all unplanned losses such as
accidents, machine / tool breakdown, fire, etc. 6
Capacity
Capacity Cushion:
The amount of reserved capacity that a firm
maintains to handle sudden increases in demand
or temporary losses of production capacity.
7
Efficiency and Utilization
Efficiency: It is the measure of how well a facility or
machine is performing when used
Actual output
Efficiency =
Effective capacity
10
Capacity Planning
Companies with less flexibility and higher costs would
probably choose to maintain a smaller cushion to maintain
a higher profit margin. If the product has a very short life or
would become outdated very quickly, the company would
choose to have a small cushion.
11
Capacity Requirement Planning
Capacity Requirement Planning is a computerized technique for
projecting resource requirements for critical work stations.
Inputs:
Planned order releases
(forecasted & customer orders)
Routing file
(equipment & labour)
Open orders file
Outputs:
Load Profile for each work center
12
Capacity Requirement Planning
• A tool for:
– determining capacity that is available and required.
– Alleviating bottleneck work centers.
13
Terminologies
• Planned Order Releases: Information from the
Material Requirements Planning which tells when to
start the order so it can be completed on time.
14
What is CRP Used For?
To determine the capability of a system or resource to produce a
quantity of output in a particular time period.
For example:
15
Capacity Strategy Formulation
16
In the real world, we need to manage this
capacity …
17
How to learn capacity management by
meditating about …
Funnel Sand
18
The Metaphor
RAW
MATERIALS
FACTORY CAPACITY =
CAPACITY 200 grains of sand/minute
FACTORY
OUTPUT
19
What are the problems with these two
production systems?
DEMAND = 200 grains/minute DEMAND = 100 grains/minute
200 grains/minute
100 grains/minute
100 grains/minute
200 grains/minute
20
Creating a balanced production system can be fairly
easy in simple systems
200 grains/minute
each
100 grains/minute
200 grains/minute
200 grains/minute
21
How to identify Bottleneck processing stage in
the following cases …….
100 200
100 grains/minute 400
200
100
200 grains/minute
200
400 400
400 grains/minute
100
22
Easy to identify the bottleneck stage(s) by observing
where inventory builds up …
200 400
100
200
100
200
400 400
100
23
Basic funnel management questions of
interest?
• How much sand should we allow into the system
of funnels?
– Should we limit the amount of sand that we
put in?
• How many funnels should we have?
• How big should our funnels be?
• What kind of funnels should they be?
• When should we add funnels?
24
There are several ways to increase capacity …
100 grains/minute
“scale up”
modify your funnel or
get a bigger funnel
400 grains/minute
“scale out”
change technology
to big-mouth funnel
400 grains/minute 4 funnels X 100 grains/minute = 400 grains/minute 25
Adjustments to Capacity
Increase capacity by:
• Adding extra shifts
• Scheduling overtime or weekends
• Adding equipment and/or personnel
26
Adjustments to Capacity
27
Economies of Scale
Economies of scale is the best operating level.
It is the point where it costs less per unit to
produce high levels of output.
It occurs when fixed costs are spread over large
number of units
The more products a work center can produce
while not increasing the fixed costs maximizes
the profit.
28
Economies & Diseconomies of
Scale
250-bed 750-bed
hospital hospital
(dollars per patient)
500-bed
Average unit cost
hospital
Economies Diseconomies
of scale of scale
29
Diseconomies of Scale
• Diseconomies of scale occurs when fixed costs increase
with number of units being produced, examples:
• Higher rework
• More equipment breakdown
• It occurs when higher production results in
increased costs.
• For example, by operating the machinery at 100%
of the time may increase profits for a period of
time, if the practice is continued the machinery will
eventually break down which will ultimately
increase costs.
30
Capacity Timing and Sizing
Following are the common capacity strategies:
31
Capacity Lead Strategy
• In anticipation of demand, capacity is increased.
• This is an aggressive strategy and is used to lure
customers away from competitors.
Units
Capacity
Demand
Time
33
Capacity Lag Strategy
• Increase capacity after demand has increased.
• This is a conservative strategy and may result in loss of
customers.
• You assume customers will return after capacity has
been met.
• Maintains little or no capacity cushion
Units
Demand
Capacity
Time
Capacity lag strategy 34
Capacity Lag Strategy
If the output of the company is unique and competition is very
weak, the company may choose to use this strategy. If
competition is great and the customer would have other options to
obtain the product from, the company would benefit from using a
different strategy.
35
Average Capacity Strategy
• Average expected demand is calculated and capacity is
increased accordingly.
• This is the most moderate strategy.
• Trying to match capacity and demand
Units
Time
Average capacity strategy
36
CRP Produces Load Profile
CRP uses the information to produce a load profile for each
machine or work center.
A load profile:
37
What is a load?
Load refers to the standard hours of work (or equivalent units of production) assigned to a facility.
Load
Load percent = x 100%
Capacity
38
Example - 1
A local road construction company needs to develop engineering
specifications prior to doing any pre-surfacing preparation. The
company has been awarded the bid on four projects. They have one
engineer. It takes 4 hours per mile to develop the engineering
specifications. The first project is 30 miles long and must be completed
by March 15th. The second project is 20 miles long and must be
completed by April 1st. The third project is 5 miles long and must be
completed by May 1st. The fourth project is 15 miles long and must be
completed by May 23rd. It is now February 15th. The engineer works a
40 hours week and is very experienced so he operates at 100%
efficiency. Assume one project can not be started until the previous
project is completed.
39
Engineering Calculations (Capacity)
Numbers of hours = 40
Shifts = 1
Efficiency = 100%
Utilization = 80% (allowing lunch breaks, meetings etc.)
Capacity = 40 x 1 x 0.8 x 1.00 = 32 hours
40
Engineering Calculations (Load)
41
Engineering Calculations (Load %)
• Project 1 = 120/128 = 94%
– Can be completed
• Project 2 = 80/64 = 125%
– Can not be completed on schedule unless load/capacity
adjustments are made.
• Project 3 = 20/128 = 16%
– Can be completed
• Project 4 = 60/96 = 63%
– Can be completed
42
Solutions to Overloaded Conditions
• Eliminate unnecessary requirements.
• Reroute jobs or labor.
• Splitting the job between two systems.
• Increase normal capacity.
• Subcontract.
• Increase efficiency.
43
Steps in the Capacity Planning
Process
1. Estimate capacity requirements
2. Evaluate capacity gaps
3. Identify alternatives
4. Conduct financial analysis
5. Assess key qualitative issues
6. Select one alternative and implement
7. Monitor results
44
Systematic Approach to Capacity
Decisions
If one service or product is produced, the capacity
requirement, M, is
46
Example – 2 : Estimate Capacity
Requirements
• A copy center prepares bound reports for 2 clients. The center
makes multiple copies of each report. The processing time to run,
collate, and bind each copy depends on the number of pages.
• The center operates 250 days/year, 8 hours/day. Management
believes that a capacity cushion of 15% is best.
• Based on the following table of information, determine how many
machines are needed at the copy center?
48
Estimate Capacity Requirements
M
D1 p1 D1 / Q1 S1 D2 p 2 D2 / Q2 S2
N (1 C )
100
M
2,000 0.5 2,000 / 20 0.25 6,000 0.7 6,000 / 30 0.40
3.12 4.
(250 days / yr.) (8 hours / day) (1 15 )
100
49
Example-3: Identify Gaps
Ginsoy is experiencing a boom in business. The owner
expects to serve a total of 80,000 meals this year. Although
the kitchen is operating at 100% capacity, the dining room can
handle a total of 105,000 diners/year. Forecasted demand for
the next 5 years is as follows:
50
Example-3: Identify Gaps
Solution: The kitchen is currently the bottleneck at a capacity
of 80,000 meals/year. Based on the forecast, the capacity gap
for the kitchen is:
Year 1 90,000-80,000 =10,000 Year 4 120,000-80,000 =40,000
Year 2 100,000-80,000 =20,000 Year 5 130,000-80,000 =50,000
Year 3 110,000-80,000 =30,000
52