Professional Documents
Culture Documents
Project Time Management: Ilija Stojanović, PH.D., PMP
Project Time Management: Ilija Stojanović, PH.D., PMP
Project Time Management: Ilija Stojanović, PH.D., PMP
• A lead is the amount of time whereby a successor activity can be advanced with
respect to a predecessor activity.
FS FS - 2
• A lag is the amount of time whereby a successor activity will be delayed with respect to
a predecessor activity.
FS + 2
Estimate activity resources
The key benefit of this process is
Estimate Activity Resources is the that it identifies the type, quantity
process of estimating the type and (not financial resources at this
quantities of material, human process), and characteristics of
resources, equipment, or supplies resources required to complete the
required to perform each activity. activity which allows more accurate
cost and duration estimates.
• Analogous estimating is a technique for estimating the duration or cost of an activity or a project
using historical data from a similar activity or project.
• Three-Point Estimating - improved by considering estimation uncertainty and risk. This concept
originated with the program evaluation and review technique (PERT):
• Most likely (tM). This estimate is based on the duration of the activity, given the resources likely to be
assigned, their productivity, realistic expectations of availability for the activity, dependencies on other
participants, and interruptions.
• Optimistic (tO). The activity duration based on analysis of the best-case scenario for the activity.
• Pessimistic (tP). The activity duration based on analysis of the worst-case scenario for the activity.
A Excavate 7 12 9 9,3
• Try at home: Beta Distribution (from the traditional PERT technique). Triangular Distribution
tE = (tO + 4tM + tP) /6
tE = (tO + tM + tP) / 3
Develop project schedule
• Critical Path Method - CPM is a network diagramming technique used to predict total project
duration
• A critical path for a project is the series of activities that determines the earliest time by which the
project can be completed and is the longest path through the network diagram with the least amount
of slack or float
• Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity
or the project finish date
• Steps:
• develop a good network diagram
• add the duration estimates for all activities on each path through the network diagram
• find your critical path
Note: If one or more of the activities on the critical path takes longer than planned, the whole project
schedule will slip unless the project manager takes corrective action
Critical path
31
Project float
• Early start (ES): the earliest possible point in time
when the uncompleted portions of a schedule activity
can start based on the schedule network logic, the data
date, and any schedule constraints.
• Early finish (EF): the earliest possible point in time when the uncompleted portions of a schedule
activity can finish based on the schedule network logic, the data date, and any schedule constraints.
• Late Start (LS): the latest possible point in time when the uncompleted portions of a schedule
activity can start based on the schedule network logic, the project completion date, and any
schedule constraints.
• Late Finish (LF): the latest possible point in time when the uncompleted portions of a schedule
activity can finish based on the schedule network logic, the project completion date, and any
schedule constraints.
• A forward pass through the network diagram determines the early start and early finish dates
• A backward pass determines the late start and finish dates
• Free slack or free float is the amount of time an activity can be delayed without delaying the early
start of any immediately following activities
• Total slack or total float is the amount of time an activity may be delayed from its early start
without delaying the planned project finish date
Schedule compression
• Three main techniques for shortening schedules
• Shortening durations of critical activities/tasks by adding more resources or
changing their scope
• Fast tracking activities by doing them in parallel or overlapping them
• Crashing activities by obtaining the greatest amount of schedule compression for
the least incremental cost by adding resouces
Gantt Charts
A bar chart of schedule information where activities are listed on the vertical axis, dates are
shown on the horizontal axis, and activity durations are shown as horizontal bars placed
according to start and finish dates.
Tr
y so
m
et
h in
gc
om
pl
ex
Solution!