Professional Documents
Culture Documents
Hydropower From Concept To Completion
Hydropower From Concept To Completion
to completion
Hydropower Project Concept to Completion Stages
Phase-6 Commissioning
• Performance testing
• Preparation of As Built Design
• Operation and Maintenance
• PC-IV and PC-V
Phase-7 De-commissioning
• Operation and Maintenance
HPP Project: map segment
4
Introduction to the specifics of Hydro Power Plants (HPP)
5 . Optimization of HPP
2
Typical Table Of Contents For A PFS For A Medium/Large HPP
1. Introduction
2. Description of project
3. Topography
4. Hydrological analysis and sediment transport
5. Geology and geotechnics
6. Assessment of seismic hazards
7. Preliminary environmental and social impact assessment
8. Examination and evaluation of layout alternatives
9. Expected power production
10. Civil engineering design
11. Electro-mechanical equipment
12. Grid connection
13. Cost estimation
14. Permitting and licensing process
15. Planning and project implementation
16. Preliminary financial analysis
17. Preliminary risk analysis
18. Conclusion and recommendation
Hydro power is a mature technology – make use of the experience!
» Use proven design solutions, study operating projects with similar head
and design flow
I f planned properly, hydropower offers the lowest generation cost of all RE technologies
at a very low risk and over an extremely long life time (>80 years)
» Use high quality equipment (turbine/generator and gates!) able to
withstand adverse conditions over the entire project lifetime
5
2. The major planning steps
5. Optimization of HPP
6
Three major planning steps not to be missed
7
3. Hydrology: the basis for HPP planning
5 . Optimization of HPP
8
Hydrology - the basis for planning
T h e hydrological study determines how much water will be available for electricity
generation over the year
» hence provides the basis for the optimal sizing and the generation of the plant
Daily run-off data over several years is the core data base the hydrological
study needs to be meaningful.
» Supporting information is precipitation data and geological formation of the
watershed in question
A s the planning process of a HPP can extend over more than a year, it is
highly recommended to start immediately with automated discharge
measurements at the intended intake site to optain first hand data.
» Appropriate data loggers are available
(http://www.geoscientific.com/dataloggers/AquaRod_Freeze_Tolerant_Water_Level_Recorder.html)
9
Hydrological study - Deliverables
Average flow duration curve as basis for the average annual generation and
determination of the optimal design discharge
F l o w duration curve of the driest year for the sensitivity analysis to check whether the
loan can be served even during dry spells
Correction factor considering quality of data base to assess the sensitivity against
variation of the water availability and the influence against missing or vague data
Estimated flood events and water levels to design the hydraulic structures safely
10
Example of Flow Duration Curve, interpreted
Optimum design
Residual flow
discharge
(60 days €
economic
optimum)
11
4. First approximation of HPP layout and electricty generation
5 . Optimization of HPP
12
First approximation of the average annual electricity generation
1. Choice of Q design based on the flow duration curve (Q60 for a start)
2. Choice of penstock diameter (5% head loss for a start) and determination
of the net head as function of the turbine flow
13
HPP Intake
14
HPP Penstock
15
Choice of Turbine for HPP
16
Hydro Power Physics at a glance: calculation of electricity generation
W t = Hn * Q * g * ηtot * t
Wt = electricity generation in time span “t” (kWh, MWh,
GWh)
Hn = net head (m) as f(Q)
17
Example:
annual production (1. approximation) with Qdesign = 3.6 m³/s
Exceedance Flow Residual flow Available flow Turbine flow Q/Qd Eff. Tot. Net head Power Generation
% m³/s m³/s m³/s m³/s % % m kW GWh
8.3 6.15 0.0468 6.11 3.60 100.0 86.5 111.5 3,406 2.49
16.7 4.84 0.0468 4.79 3.60 100.0 86.5 111.5 3,406 2.49
25.0 3.88 0.0468 3.84 3.60 100.0 86.5 111.5 3,406 2.49
33.3 3.11 0.0468 3.07 3.07 85.2 87.6 111.9 2,949 2.15
41.7 2.63 0.0468 2.58 2.58 71.7 86.9 112.2 2,471 1.80
50.0 2.16 0.0468 2.11 2.11 58.6 86.6 112.5 2,015 1.47
58.3 1.65 0.0468 1.60 1.60 44.4 86.9 112.7 1,536 1.12
66.7 1.16 0.0468 1.12 1.12 31.0 87.2 112.9 1,077 0.79
75.0 0.83 0.0468 0.78 0.78 21.8 86.2 112.9 749 0.55
83.3 0.53 0.0468 0.48 0.48 13.3 83.6 113.0 444 0.32
91.7 0.39 0.0468 0.34 0.34 9.5 81.7 113.0 310 0.23
100.0 0.31 0.0468 0.27 0.27 7.4 80.3 113.0 236 0.17
18
5. Optimization of HPP
c 5 . Optimization of HPP
19
Optimising the sizing of the HPP
After the first approximation an optimisation of the sizing of the HPP needs to be done to
obtain the most economic installed capacity. This requires the following steps:
1. Based on the data from the flow duration curve the exceedance and the flow are listed.
3. Varying the Q design and the penstock diameter will vary the investment cost but
at the same time the generation and with this the revenue. That Q design which yields
the highest NPV will result in the most economic size, the plant should be designed
for.
€ This optimisation step is very often omitted resulting in HPP too big for the river
or the available potential is under-utilised.
20
The planning process and its optimisation
21
Electro mechancial equipment approximate cost
A s first approximation the cost for the electro-mechanical equipment can be expressed
by the formula below
Where :
22
6. Determination of budgetary investment cost
c 5 . Optimization of HPP
23
Determining the budgetary investment cost as a basis for seeking
appropriate financing of the HPP
Once the optimum Q design is determined the investment cost can be determined in more
detail:
c T h e engineering design of the civil works component will yield a bill of quantity
(quantities of excavation, concrete, reinforcement steel, back filling etc).
» With the help of unit costs for these quantities the cost for the civil works
components can be determined to a high degree of accuracy.
c F o r all items which will be purchased, like gates, penstock and E&M equipment,
budgetary quotations need to be requested from renowned suppliers. These kind of
quotations can be received rather easily as they are not binding for the supplier. It is
accepted practice that the price quoted can fluctuate ±15%
c To consider any contingencies account for 10% of total investment at this stage
24
Description Euro
Head works
25
7. HPP bankable documents
c 5 . Optimization of HPP
26
„Bankable documents“ documents required for financing
cFeasibility study:
» This study determines the final technological choice and scope and proves its
technical, economic and environmental feasibility,
cLegal documentation:
» All project related permits, licenses and contracts, including the budgetary quotations.
» Documentation on the project sponsor
27
Feasibility Study and its objectives
» evaluates the economic and financial profitability and its sensitivity against
changes in the assumptions
28
DEFINITIONS
WORK
Work is the transferred energy and is the product of force and
distance moved. It is measured in lb-ft or Joules.
ENERGY
It is the capacity to do work. The energy from water can
either be potential energy (by virtue of position) or kinetic
energy (by virtue of the movement). The work done by water
in producing electrical energy is usually measured in kWh
(kilowatt hours).
POWER
Power is the rate of transferring energy or workdone per unit
of time. It is measured in kW (kilowatt) and hp (horsepower).
Power capacity is often used to refer rated capacity of the
plant.
(Watt is defined as one Joule of work done in one second.)
DEFINITIONS (CONTD.)
DEMAND
It is the amount of power needed or desired by the consumers connected
to a network or power system.
LOAD
Is the rate at which electrical energy is actually delivered to or by a
system.
PEAK LOAD
The electric load at the time of maximum demand.
LOAD FACTOR / PLANT FACTOR
It is defined as the ratio of annual energy output kWh / max power output
x 8760 hours. (Actual Energy / Theoretical Energy)
DEFINITIONS (CONTD.)
HYDRAULIC HEAD
It is the elevation difference the water falls in passing through the plant.
GROSS HEAD
It is the difference between headwater (water in the forebay or
impoundment supplying the turbine) elevation and tail water (water at draft
tube exit) elevation.
NET HEAD
It is the effective head on the turbine and is equal to the gross head minus
the hydraulic losses before entrance to the turbine and outlet losses.
DESIGN HEAD
Refers to the effective head for which the turbine is designed for best
speed and efficiency.
DEFINITIONS (CONTD.)
FOREBAY
A pond or basin of enlarged water surface and depth, usually at the end of a
canal, from where a penstock leads to a powerhouse.
PENSTOCK
A pipe (usually of steel, concrete or cast iron) that conveys water under
pressure from the forebay to the turbine.
DRAFT TUBE
A tube full of water extending from below the turbine to below the minimum
water tailrace level.
TAILRACE
The discharge channel from a turbine before joining the main river channel.
CLASSIFICATION OF HYDRO POWER
PLANTS
CLASSIFICATION OF
HYDRO POWER PLANTS
SINGLE
PUMP STORAGE
ENERGY ENERGY PURPOSE LOW HEAD
DISTRIBUTION GENERATED LOW LAND <15 m
MULTI PLANTS
TIDAL PLANTS
PURPOSE MEDIUM
ENERGY
HILLY AREA HEAD 15-50
DEMAND
PLANTS
PLANT UTILIZING
HIGH HEAD
ENERGY OF FLOWING SUBSIDIARY
MOUNTAINO > 50m
WATER ISOLATED
US REGION
BASE PLANTS
WITHOUT
CO-
STORAGE
OPERATION
PEAK G
DIVERSION
MICRO MINI 100-5000 Medium 15000- HIGH
STORAGE
<100 kW Kw 50000 kW >50000kW
NON Small 500-
DIVERSION 15000 Kw
CLASSIFICATION ON THE BASIS OF
TECHNOLOGICAL ASPECTS
2. Pumped-storage plants.
NON-DIVERSION DEVELOPMENT
• A barrage or dam is built across the river
• The natural flow of the river is passed through the penstock to
turbines
• energy output depends on the flow of the river
Examples
Warsak hydropower station on Kabul river
Chashma hydropower project
Non-Diversion Development (run-of-river)
PLANTS WITHOUT STORAGE (run-of-river)
Non-Diversion Development
a dam across the river/stream creates storage
The storage can be daily, weekly, seasonal or annual
Examples
Tarbela Dam
Mangla Dam
Storage Plants - Non Diversion Development
PLANTS WITH STORAGE
Diversion Development
A diversion structure such as a dam across the river/stream is built
water is diverted to the turbine through an intake, pressure tunnel
and penstock
The storage can be daily, weekly, seasonal or annual
Examples
Duber Khawr HPP
Allai Khawr HPP
Khan Khawr HPP
Storage Plants - Diversion Development
PUMPED STORAGE PLANTS
Access tunnel
Lower reservoir
Pump/turbine
TIDAL POWER PLANTS
• The tidal fluctuations in some coastal parts of the world are
relatively high.
• The power is produced by utilising the potential offered by
the tidal cycles.
• Such plants work on water flowing back and forth.
BASE-LOAD PLANTS
Base load plants are those, which are meeting the firm demand
of the network. Energy available at all times (low flow) is called
Firm Power.
PEAK-LOAD PLANTS
Peak load plants are those, which due to water availability
produce their maximum capacity during the peaking hours.
Tarbela and Mangla are being operated to cover the peak
demands of the interconnected system in Pakistan.
Classification on the Basis of Energy
Generated
Micro Capacity Plants < 100 kW
Head
Low-Head Plants <15 m
Medium-Head Plants 15-50 m
High-Head Plants >50 m
HIGH HEAD POWER PLANT
MEDIUM HEAD POWER PLANT
LOW HEAD POWER PLANT
CLASSIFICATION ON BASIS OF
TOPOGRAPHY
---------------------------------------------------------------------
…………….
H
P=ŋ*9.81*Q*H
( KWatt)
Q→
HEAD LOSSES
The net head is calculated by subtracting losses from gross
head. The losses may be such as;
Hydropower
Civil
Hydrology
Geology
Electrical
Mechanical
Environment
Economics
PLANNING STAGES OF HYDROPOWER PROJECTS
DESK STUDIES
RECONNAISSANCE SURVEY
APPRAISAL REPORTS
RANKING STUDIES
PRE-FEASIBILITY STUDIES
FEASIBILITY REPORT
DETAIL ENGINEERING DESIGN
PREPARATION OF TENDER DOCUMENTS
High Head Hydropower Projects - Types
73
Dam Station Development
74
High Head Projects Canal Diversion
77
COMPONENTS OF DIVERSION TUNNEL
Dam or weir
Power Intake
Low Pressure tunnel
Surge tank
Penstock (with valve chamber) or pressure shaft
External powerhouse or underground station
Tailrace or tail water tunnel
Switchyard or underground switchgear equipment .
78
Diversion Tunnel Project - Bunji Layout
GILGIT
BUNJI
79
Bunji Dam Layout
80
Bunji Dam Cross Section
81
Reservoir
OBJECTIVE
- Storage to increase firm capacity of Power plant.
- To increase water availability and annual energy for
hydropower generation
TYPES
- Mainstream reservoir located along the river upstream
of dam. Tarbela, Mangla etc.
- Off stream reservoir: reservoir which is located outside
of the river by means of excavating a large portion of
land. Like: Akhori Dam
- Daily or weekly storage like Warsak, GB HEP, Dasu,Bunji
etc. 82
Lateral Weir/Small Dam - Layout
83
Diversion Canal – Phandar Hpp
84
Small Dam – Over flow and Under sluices Sections
85
Small Dam – Embankment and Cross Sections
86
Tyrolean Weir
88
Spillway - Types
• Overflow spillway
• Gated overflow spillway
• Orifice spillway
• Side Channel Spillway
• Morning Glory with tunnel
89
SPILLWAY – ENERGY DISSIPATORS
91
Penstock
1. Surface or Embedded Penstock
92
Penstock - Manifold
93
Powerhouse
95
POWERHOUSE – Horizontal Francis
1.Turbine 4.Generator
2 Valve 5. Pump
3.Bifurcation 6. Coupling
96
POWERHOUSE – Vertical Francis
97
POWERHOUSE – Horizontal Pelton
98
Types of Turbines
99
Hydropower in Pakistan
World Hydropower Production
RATIO OF HYDEL-THERMAL MIX IN PAKISTAN
1 1960 44:56
2 1970 50:50
Ideal for Economic
3 1980 58:42 Development of the
Country
4 1985 67:33
5 1990 45:55
6 2000 33:67
7 2005 37:63
8 2015 33:67
PAKISTAN’S HYDROPOWER POTENTIAL
Sr. No. River/ Tributary Power (MW)
A Hydropower Projects above 50 MW
1 Indus River 39558
2 Tributaries of Indus in Gilgit-Baltistan 1698
3 Tributaries of Indus in Khyber-Pakhtunkhwa 4028
Sub Total (1-3) 45284
4 Jhelum River 4341
5 Kunhar River 1455
6 Neelum River & its Tributaries 1769
7 Poonch River 462
Sub Total (4-7) 8027
8 Swat River & its Tributaries 2297
9 Chitral River & its Tributaries 2285
Sub Total (8-9) 4582
Total A 57893
B. Hydropower Projects below 50 MW
1 On Tributaries 1591
2 On Canals 674
Total B 2265 103
PAKISTAN’S HYDROPOWER POTENTIAL
104
EXISTING HYDEL POWER STATIONS