Professional Documents
Culture Documents
Internship Report Presentation
Internship Report Presentation
Internship Report Presentation
Analysis
WORKFLOW
Stability
Checks
Co-ordination
Design &
with Architect,
Execution at Detailing,
Contractors,
Site DBR
Other
consultants
WORKFLOW EXPLANATION
• Create Basic Framing Plan- Studying Drawings and create plans using AutoCAD
• Mathematical Modelling- Basic Modelling, assigning loads(DL,LL, Earthquake, Wind,
Temp.) properties using Etabs
• Analysis- Static as well as Dynamic Analysis using Etabs
• Stability Checks- Drift, Deflection, Stress Limits using Etabs (Refernce Various IS Codes)
• Design & Detailing- Slabs, Beams, Columns, Shear walls, foundations, bracings etc.
using Etabs and CSI Detailing
• DBR- Design Basis Report to be submitted and approved from government
departments such as HRC, Mumbai and local municipality
• Co-ordination with Architect, Contractors, Other consultants- Providing Drawings for
execution and 3D Modelling, BOQ etc.
STRUCTURAL ANALYSIS
STATIC DYNAMIC
Geometric Material
Modal
P-Delta Buckling Response
Spectrum Time
Shrinkage History
Material
Creep
Strength
List of Projects Worked on
1. G+2 Residential Project, Tumkur, Karnataka
2. B+G+2 Office Space, Neelmangla
3. G+16 Commercial Building, Navi Mumbai( Flat Slab)
4. B+Podium+G+9 Residential Building, Mysuru (Tower+Non Tower)
5. Underground Water Tank, 2 lac liters
6. Bungee Jumping, Goa (Steel Structure)
7. G+27 Residential Project, Mumbai (Case Study)
PROJECT IMAGES
CASE STUDY
RAUNAK RESIDENCY
VARTAKNAGAR, MUMBAI
RAUNAK RESIDENCY
Location Estimated
Vartak Nagar, Cost Of the Dimensions
Mumbai Project of
(Maharashtra ) 50 Crores Project
TRANSFER SLAB
SLAB PROPERTIES
1. Gym area 2 4
2. Lobby 2 4
3. WC/Bath 3 2
4. Staircase 3 3
5. Terrace 3 2
6. O.H.T 21 0.75
7. LMR 9 0.75
EARTHQUAKE PARAMETERS
PARAMETERS VALUE REMARK
Based on the IS 1893 (Part 1) 2016
Seismic Zone Factor 0.16 (IS 1893:2016 (Part 1) Table no.- 3
(Z) Clause 6.4.2)
Zone-3
Site Type I (IS 1893:2016 (Part 1) Table no.- 4
Clause 6.4.2.1)
Importance Factor 1.2 (Because occupancy is greater than
200 persons.) (IS 1893:2016 (Part 1)
Table no.- 8 Clause 7.2.3)
Eccentricities Ratio 0.05
Response Reduction 4 (Because of Structural wall system).
Factor (IS 1893:2016 (Part 1), Table no.- 9
Clause 7.2.6)
Mass source D=1, Table no.- 9 (IS 1893:2016 (Part-1)
L=0.5, L=0.25
(Live Load>3)
Live Load<3)
Time period in X 1.03 sec
direction
Time period in y direction 1.71 sec
WIND PARAMETERS
TOPOGRAPHY 1 Appendix-c
X Dir.0.7,
WIND COEFFICIENT 0.4 Table - 4
Y Dir.
0.8,0.1
GUST FACTOR ANALYSIS
•• Formula to calculate:
• (Maximum deflection - Axial Shortening) Creep Coefficient < Span / 350 or 20-mm. Span length =
1.61 m.
• Calculation = (22.155 – 21.279) 3 = 2.628 < 4.6 mm or 20 mm.
• So, allowable deflection is greater than actual deflection,
Hence passed
STABILITY CHECKS
Check name Permissible value Check in Uncracked Check in Code
Model Service
Model
Drift 0.004 SPECX=0.002 SPECX=0.004 1. CLAUSE 7.11.1, IS1893
SPECY=0.0006 SPECY=0.001 PART (I) 2016
2. CLAUSE 5.4.1,
IS16700:2017
1. CLAUSE 5.4, IS
Displacement =H/500 WX=0.314 WX=0.41 16700:2017
due to wind =90000/500 WY=8.71 WY=10.01 2. CLAUSE 20.5, IS
(mm) =180 456:2000
3. TABLE-6, NBC 2016
(VOL-1)
Displacement =H/250 EX=28.70 EX=40.75 1. CLAUSE 5.4, IS 16700
due to =90000/250 EY=26.07 EY=36.985
earthquake =360 SPECX=30.09 SPECX=305.57
(mm) SPECY=45.45 SPECY=85.26
40
60
80
100
120
Resultant Moment (M11) Detailing (Plan)
PROJECT MANAGEMENT AND PLANNING CONSULTANCY
Understanding of
Civil
the Architectural 3D Modelling
engineering
Design and
Inputs
drawings
MEP
Works
WORKFLOW
IRR
Analysis
Execution at Contracts
BOQ, Scheduling
Site
WORKFLOW EXPLANATION
• Civil engineering Inputs- Ideas about framing plan, column location, Typical Structures
like dome etc, Parabolic Balconies etc.
• 3D Modelling- Creating realistic 3D Model using Revit Architecture and resolving
clashes
• MEP Works- Mechanical, electrical, Plumbing fittings and drawings along with clash
detection using Revit Architecture
• IRR Analysis- Internal Rate of Return is measure of investment’s expected rate of
return. Cost vs Benefit Analysis
• Contracts- Preparing contracts between client and various contractors with proper
incentives for both sides.
• BOQ- Preparing Bill of quantities of for all components to be circulated for tenders
• Scheduling- Preparing time liner, Gannt charts etc to measure and see progress of
project.
ARCHITECHTURAL FLOOR PLAN
SECTION VIEW 3D VIEW
PLUMBING FLOOR PLAN
3D PLUMBING VIEW SECTION OF PLUMBING VIEW
CLASH DETECTION BETWEEN BEAM AND PIPE
CLASHES RESOLVED
CLASHES BETWEEN FLOOR AND PIPE
TIME LINER
SCHEDULING
COST ANALYSIS AND BOQ
Cost Analysis
Miscellaneous
Painting According to the BOQ prepared,
7% 4%
Concrete we can see the costs involved in
Flooring 18%
16% various components of
construction.
Blockwork
15% Steel
28%
Shuttering
5%
RATE ANALYSIS
CONCRETE
STEEL
FLOORING
According to section 11.41, DAR,2016
Vol 1 prepared by CPWD
Average rate per Sqft for selling in Vartak Nagar, Mumbai= Rs 16000/-
Reading and Analysing Various CPWD and Working on real-time projects with timelines
govt. documents