POWER AND AUXILIARY CIRCUIT

OF 3-PHASE LOCOMOTIVES
10.08.16
OHE PARAMETERS
• Nominal Voltage: 25 kV
• Maximum Voltage: 30 kV
• Minimum Voltage: 17.5 kV
• Frequency: 50 Hz ± 3%
ROOF EQUIPMENTS
ROOF EQUIPMENTS
ROOF EQUIPMENTS
TRANSFORMER (6500 LOT)
TRANSFORMER (7500 LOT)
TRANSFORMER (7500 LOT)
TRANSFORMER
Winding Power (kVA) Voltage (V) Current (A)
Primary 6531 25 k 261.25
Traction 4x1449 1269 4x1142
Auxiliary 334 1000 334
Filter 400 1154 347
Hotel Load 2x622.5 960 2x648

Weight of TFP: 9500 ± 3%


TERMINAL ARRANGEMENT
TRACTION CONVERTER
SOD TERMINAL
DC-LINK
• Nominal DC-Link Voltage is 2800 V.
• DC-Link of Traction Converter is consist of DC-Link Capacitor, Harmonic Filter and Soft
Crow-Bar Protection (Over Voltage Protection).
• The DC-link capacitor is used to stabilize the DC-link voltage and act as an energy reservoir.
• The DC-link capacitor neutralises power differences between the motor and the line side
• The DC-link capacitor also absorbs the harmonic currents produced by the line converters and
drive converters.
• Each power modules requires a capacitor to limit IGBT switching over-voltages
• The single-phase supply generates a power oscillation at twice its fundamental frequency on the
DC-Link.
• A tuned second harmonic filter (100Hz) is used to shunt this dominant second harmonic
frequency component.
IGBT CONVERTER POWER CIRCUIT
SOFT CROW-BAR PROTECTION

• It is also termed as Voltage Limiting Unit (VLU).


• It consists of a DC-DC chopper, a current sensor and a resistor.
• It used to suppress transient DC-Link over voltages and actively
discharging the DC-link during converter shut-down.
• The duty-cycle controlled chopper is operated at a fixed frequency.
POWER MODULES (ABB)
I/P Coolant
Gate Drive Unit

O/P Coolant

Heat Sink

Bus Bar
IGBTs
POWER MODULES (BHEL)

O/P Coolant
I/P Coolant

Heat Sink IGBTs


COOLING SYSTEM
COOLING SYSTEM
• The IGBT based traction converter is designed for water cooling (mixture of water and
glycol).
• It is integrated into the overall cooling circuit of the vehicle.
• All power semiconductors transfer their losses to the coolant via an aluminium water
cooler.
• The temperature of the coolant is lowered by an external water-to-air heat exchanger
which is part of existing Oil Cooling Unit (OCU).
• To prevent reactions with the coolant, the only materials used inside the cooling circuit
are aluminium, stainless steel and plastic.
• The used coolant is antifrogen-N, a mixture of water and glycol blended with
inhibitors to provide protection against corrosion.
COOLING SYSTEM
• Coolant is circulated in Traction Converter using Cooling pump.
• 415 VAC, 3-phase, 50 Hz supply is provided to cooling pump from
Auxiliary Converter.
• The power rating of cooling pump is 5 kW.
• The losses from the passive components, such as capacitors, bus bars,
and power cables are transferred to the inside air of the traction
converter.
• Internal fans in the cabinets ensure forced air circulation inside the
traction converter.
COOLING PUMP

BHEL Traction Converter


COOLING SYSTEM CONNECTION TO OCU

CGL Traction Converter


AUXILIARY CONVERTER
IGBT AUXILIARY CIRCUIT
IGBT AUXILIARY CONVERTER
• A total of 3 Auxiliary Converters (BUR1, BUR2 & BUR3) in two
cubicles are provide in a locomotive.
• Each Auxiliary Converters has 130 kVA capacity.
• All three Auxiliary Converters are fed from single transformer
winding of rating 1000V, 334 kVA.
• Auxiliary Converter provides 3-phase AC output of 415 V (L-L) and
DC output of 110V, 80 A.
• Minimum efficiency of Auxiliary Converter in 92 % at rated load of
130 kVA (0.8 pf)
GOD TERMINAL
LOAD DISTRIBUTION ON BURS
BUR1
Oil cooler blower-1 25 kW
Oil cooler blower-2 25 kW
Total 50 kW

BUR2
BUR3
Traction motor blower-1 25 kW
Traction motor blower-2 Scavenge blower-1 3 kW
25 kW Scavenge blower-2
3 kW
Oil pump transformer – 1 4.7 kW
Oil pump transformer – 2 4.7 kW Compressor – 1 15 kW
Oil pump converter – 1 11 kW Compressor– 2 15 kW
Oil pump converter – 2 11 kW Battery Charger 12 kW
Total 81.4 kW
Total 48 kW
LOAD DISTRIBUTION (BUR1 ISOLATED)

BUR2
BUR3

Traction motor blower-1 25 kW


Oil pump transformer – 1 4.7 kW
Traction motor blower-2 25 kW
Oil pump transformer – 2 4.7 kW

Oil cooler blower-1 25 kW Oil pump converter – 1 11 kW

Oil cooler blower-2 25 kW Oil pump converter – 2 11 kW

Compressor – 1 15 kW
Scavenge blower-1 3 kW
Compressor– 2 15 kW
Scavenge blower-2 3 kW
Battery Charger 12 kW

Total 106 kW Total 73.4 kW


Normal Condition

BUR-1 Isolated
LOAD DISTRIBUTION (BUR2 ISOLATED)

BUR1
BUR3

Traction motor blower-1 25 kW


Oil pump transformer – 1 4.7 kW
Traction motor blower-2 25 kW
Oil pump transformer – 2 4.7 kW

Oil cooler blower-1 25 kW Oil pump converter – 1 11 kW

Oil cooler blower-2 25 kW Oil pump converter – 2 11 kW

Compressor – 1 15 kW
Scavenge blower-1 3 kW
Compressor– 2 15 kW
Scavenge blower-2 3 kW
Battery Charger 12 kW

Total 106 kW Total 73.4 kW


Normal Condition

BUR-2 Isolated
LOAD DISTRIBUTION (BUR3 ISOLATED)

BUR1
BUR2

Traction motor blower-1 25 kW


Oil pump transformer – 1 4.7 kW
Traction motor blower-2 25 kW
Oil pump transformer – 2 4.7 kW

Oil cooler blower-1 25 kW Oil pump converter – 1 11 kW

Oil cooler blower-2 25 kW Oil pump converter – 2 11 kW

Compressor – 1 15 kW
Scavenge blower-1 3 kW
Compressor– 2 15 kW
Scavenge blower-2 3 kW
Battery Charger 12 kW

Total 106 kW Total 73.4 kW


Normal Condition

BUR-3 Isolated
AUXILIARY TRANSFORMER (HB-1)
HOTEL LOAD CONVERTER FOR WAP-7

LOT-7500 (DUAL HOTEL LOAD WINDING)