Professional Documents
Culture Documents
IM and S
IM and S
IM and S
MODULE 2
Definition of quality and it dimensions.
Quality planning- three prong approach.
Quality audit
Life
Reliability
Taste
Odour
Maintainability
FOUNTAIN PEN
It should hold sufficient quantity of ink.
It should regulate the flow of ink into the rib
Good appearance
serviceability
Perceived quality
Conformance to standards.
.
QUALITY OF DESIGN.
Type of customers in the market- conduct market survey.
1) Consuming habits of people
2) The prices thet are willing to pay.
3) The choice of design of the peroduct which neets the
needs of the customer.
Profit consideration
Environmental conditions
Product planning
Managerial and operational
planning.
Documentation
MANAGERIAL AND OPERATIONAL
PLANNING
Preparing organisational structure
Preparing organisational procedure
Preparing process.
Blue prints
Inspection instructions
Test procedures
Work instructions
Quality manual
QUALITY MANAGEMENT SYSTEM.
MANAGEMENT SYSTEM: a system to
establish policy and objectives and to
achieve those objectives.
Quality management system
Financial management system
Environmental management system.
System must clarify to the organization
What to do ?
Who will do it ?
How the work will be done?
When to do it??
etc……
TO ASSURE THE QUALITY ONE
HAS TO ENSURE THE
QUALITY….
QUALITY THUS BEGINS
WITH STANDARDS….
NEED FOR STANDARDIZATION
Standardization is temporary
crystallization of the best acceptable
solution to a recurring problem,
formulated in a scientific and
systematic fashion by pooling the
knowledge of all those who are
concerned with the problem, and is
subjected to review and revision by
common consent.
LEVELS OF
STANDARDIZATION….
Company/inplant standards
National standards like BIS
Regional standards like euro-
norms and
International standards like ISO
standardization
Company standardization is now an
important effective management tool for
improving quality and productivity.
Quality and standardiation are the to
essential pre-requistes for a company to
market its products and services in the
competitive business environment.
Quality thus begins with standards.
QUALITY MANAGEMENT SYSTEM
A management system to direct and control an
organization with regard to quality.
A system to establish quality policy and quality
objectives and to achieve those objectives.
QMS can assist organizations in enhancing
customer satisfaction.
The ISO 9000 family defines standards on
quality management systems which can assist
organizations in achieving this objective
S
QMS approach encourages
organizations to analyse customer
requirements, define the process that
contribute to the achievement of a
product which is acceptable to the
customer, and to keep these
processes under control.
CONCEPT AND ROLE OF ISO 9000
contract review
Design control
Document control
Purchasing
Purchaser-supplied product
Process control
Corrective action
Quality records
Training
Servicing
Statistical techniques.
The following criteria must be fulfilled:
The company has a brief but comprehensive Quality
Policy.
This Quality Policy should be included in the Quality
Manual as well as being on public display.
Quality Objectives have been established by
management and there is a statement outlining the intent
to deliver against these objectives.
The Quality Policy is communicated throughout the
organization.
All employees, at all levels, receive the same message
from management. All statements relating to quality that
are in documents, training manuals, advertising
literature, etc. must be consistent with the Quality
Statement.
Any changes must be issued in a controlled manner and
must be properly communicated to all employees.
Trained personnel are available to operate the necessary
procedures.
No unregistered or overdue equipment is used.
1. Preparatory step
2. Implementation step
3. Registration and certification
step.
PREPARATORY STEP.
Quality awareness training is conducted
Prepare necessary quality documents
3)concreting
PERT
CPM
UNETICS
LESS
TOPS
SCANS
Manufacturing
Maintenance planning
Inventory planning
marketing
DIFFERENT PHASES IN THE APPLICATION OF
NETWORK TECHNIQUE
PLANNING
SCHEDULING
CONTROLLING
RESOURCE ALLOCATION AND
UPDATING IN A NETWORK TECHNIQUE.
Labour
Finance
Equipment
space
ACTIVITY
An activity is a task associated with a project.
It is a physically identifiable part of a project
which consumes time and resources.
Activity is the work to be undertaken to
materialise a specific event.
Therefore an activity is the actual performance
of a task.
Ex: lay pipe line is an activity.
Mix concrete
Assemble parts
Prepare estimate
Install pump
EXAMPLES FOR EVENTS
Design completed
Material received at site
Lathe installed
Payment made
Specifications prepared.
SYMBOLS USED IN PERT AND CPM
NETWORK RULES
Between 2 events one and only one activity can be
shown.
Starting event is called tail event.
LFT=L3
LATEST START TIME (LST)
LST of an activity is the latest time by
which an activity can be started
without delaying the completion of
the project.
LST=LFT-activity duration;
SLACK AND FLOAT
Slack is the term associated with events.
It denotes the flexibility range within
which an event can occur.
ie, slack of an event is the difference
between the earliest event time and latest
event time
Slack of the event 2 is L2-E2.
The term float is associated with the
activity times.
Float denotes the range within which activity
starts time or finish time may fluctuate without
affecting the completion of the project
1) Total float
2) Free float
3) Independent float
4) Interfering float
TOTAL FLOAT
Total float is the time spent by which the
starting(or finishing) of an activity can be
delayed without delaying the completion of the
project.
In certain activities, it will be found that there is
a difference between maximum time available
and the actual time required to perform the
activity. The difference is known ad the total
float.
Total float of an activity is the excess of the
maximum available time over the activity time.
Thus, total float= LFT-EFT OR LST-EST
FREE FLOAT
Free float is that portion of positive float that can be used
by an activity without delaying any succeeding activity.
The concept of free float is based on the possibility that all
the events occur at their earalist time.( i,e all activity
start as early as possible.)
Free float= EST OF SUCCESSOR- EFT of the present
activity.
Thus it is excess of the available time over the required
time when the activity, as well as its successor activity
start as early as possible.
INDEPENDENT FLOAT
The independent float is defined as the excess of
minimum available time over the required activity
duration.
That is independent float is the amount of time an
activity could be delayed if preceding activities finish at
their latest and subsequent activities start at their
earliast.
Independent float is equal to the free float minus tail
event slack.
If the tail event slack is zero, free float and independent
float are equal
Itis to be noted if a negative value of
independent floaat is obtained, then
independent float is taen as zero.
Independent float=EST for subsequent
activity-LFT for preceding activity-
duration
INTERFERING FLOAT
Itis just another number given to the head
event slack specially in CPM networks
which are activity oriented.
Interfering float is equal to the difference
between total float and the freefloat.
CRITICAL PATH
While analysing a network of activities, it is often
necessary to estimate the total project time.
The total project time is the maximum of the elapsed
times among all paths originating from the initial event
and terminating event, indicating completion of the
project.
Therefore critical path is that sequence of activites which
determines the total project time.
In a project network there may be a number of paths
starting from the intial event and ending in terminal
event.
these paths connects activity.
Among these paths that which is
longer on the basis of final
duration is called the critical path.
a critical path is one which
connects activities having zero
float.
CRITICAL ACTIVITY
An activity whose float is zero is called
critical activity.
So any delay in the start of critical will
cause a further delay in the completion of
entire project.
Activities lying on the critical path are
critical activities.
CRITICAL PATH METHOD (CPM)
1)List all the activities and draw a network diagram.
2)Find the earliest event time and latest event time of each
event and show in the network diagram.
3) Calculate earliest start time, earliest finish time, latest
start time, and latest finish time for each activity.
4)Determine the float for each activity.
5) Identify the critical activity.( having zero floats.)
6) Draw double lines in the network diagram passing
through critical activities. The double lines shows the
critical path.
Calculate the total project duration which is the sum of
durations of critical activities.
FORWARD PASS(EARLIEST START TIME
RULE)
1) EARLIEST OCCURRENCE OF INITIAL EVENT=
0, as there is no predecessor event.
E1=0
2) earliest occurrence of an event when
there is only one immediate predecessor
activity= earliest occurrence of
predecessor event+ duration of the
predecessor activity.
E3= E2+ duration of the activity B
3) earliest occurrence of an event when there are
many predecessor activities= maximum value
selected from the (earliest occurences of all the
predecessor events+ duration of each of the
corresponding predecessor activity.)
4) earliest start time of an activity = earliest
occurrence of the tail event.
BACKWARD PASS( LATEST FINISH TIME
RULE)
Latest occurrence of terminal event= earliest occurrence
of the terminal event, if there is no successor event.
L10=E10, WWHWNE LAST EVENT IS 10
3)optimistic time, to
QUANTITATIVE
TECHNIQUES
IN
MANAGEMENT
LINEAR PROGRAMMING
PROBLEM
MATHEMATICAL
FORMULATION AND
SOLUTION BY GRAPHIC
METHOD.
programming problem in general deals with
determining optimal allocation of limited
resources to meet given objectives.
A LLP includes a set of simultaneous linear
equations or inequalities which represent the
restrictions related to the limited resources and
a linear function which expresses the objective
function representing the total profit or cost.
The term linear means that all the relations in
the problem are linear and the term
programming refers to the process of
determining a particular programme or plan of
action.
Linear programming may be defined as a
method of determining an optimum programme
of interdependent activities in view of available
resources.
The objective of LPP is to maximise profit or
minimise cost, as the case may be, subject to a
number of limitations known as constraints.
For this an objective function is constructed
which represents total profit or total cost as the
case may be.
The constraints are expressed in the form of in
equalities or equations.
Booth the objective function and constraints are
linear relationship between the variables.
The solution to a linear programming
problem shows how much should be
produced or sold or purchased which will
optimize the objective function and satisfy
the constraints.
Linear programming technique is used to
achieve the best allocation of available
resources.
Available resources may be man hours,
machine hours raw materials etc.
APPLICATIONS OF LINEAR
PROGRAMMING IN INDUSTRY AND
MANAGEMENT
Product mix
Product smoothing
Media selection
Capital investment
Transportation problem
Assignment problem
Blending problem
Communication industry
Staffing problem
BASIC ASSUMPTIONS
Proportionality
Additivity
Divisibility
Certainty
Finiteness
optimality
REQUIREMENTS FOR EMPLOYING LPP
Definition of the objective
Quantitative measurement of the elements of problem
Alternatives
Constraints
Linearity
finiteness
ESSENTILAL INGRADIENTS OR
CHARACTERICTICS OF LPP.
OBJECTIVE FUNCTION
LINEAR CONSTRAINTS
FEASIBLE SOLUTION
OPTIMAL SOLUTION
QUESTION 1
A manufacturer of furniture makes two
products, chairs and tables. Processing of
these products is done on two machines A
and B. A chair requires 2 hours on machine A
and 6 hours on machine B. A table requires 5
hours on machine A and no time on machine
B. There are 16 hours of time per day
available on machine A and 30 hours on
machine B. Profit gained by the manufacturer
from a chair is Rs 1 and from a table is Rs 5
respectively. Formulate the problem into a
LPP in order to maximize the total profit.
QUESTION 2
A home resourceful decorator manufactures
two types of lamps say A and B. Both lamps
go through two technicians first a cutter and
second a finisher. Lamp A requires 2 hours
of the cutter’s time and 1 hour of the
finisher’s time. Lamp B requires 1 hour of
cutter’s and 2 hours of finisher’s time. The
cutter has 104 hours and finisher has 76
hours of available time each month. Profit n
the lamp A is Rs. 6 and on the B lamp is Rs.
11. Formulate a mathematical model.
QUESTION 3