Professional Documents
Culture Documents
Project Management Training
Project Management Training
TRAINING
Lecture 01
Basic Concepts
• Project: According to PMBOK “ project is a
temporary endeavor undertaken to create a
unique product, service, or result”
• Project Management: According to PMBOK
“project management is application of
knowledge, skills, tools, and techniques to
project activities to meet the project
requirements”
Session 1 Overview
1 • Schedule Management
2 • Cost Management
• Communication and
3 Team Management
1. Schedule and Time Management
• Schedule Estimation
Tools & Techniques
• Critical Path Method
• Resource
Optimization
• Schedule
Compression
Techniques
Estimation Tools & Techniques
• EXPERT JUDGMENT
• Expertise should be considered from individuals or groups with specialized knowledge
or training in the following topics:
o Schedule development, management, and control;
o Expertise in estimating; and
o Discipline or application knowledge.
• ANALOGOUS ESTIMATING
o Analogous estimating is a technique for estimating the duration or cost of an
activity or a project using historical data from a similar activity or project.
o Analogous estimating uses parameters from a previous, similar project, such as
duration, budget, size, weight, and complexity, as the basis for estimating the
same parameter or measure for a future project.
o Analogous estimating is generally less costly and less time-consuming than other
techniques, but it is also less accurate.
Estimation Tools & Techniques
• BOTTOM-UP ESTIMATING
• Most likely (tM). This estimate is based on the duration of the activity, given the resources likely to be assigned,
their productivity, realistic expectations of availability for the activity, dependencies on other participants, and
interruptions.
• Optimistic (tO). The activity duration based on analysis of the best-case scenario for the activity.
• Pessimistic (tP). The duration based on analysis of the worst-case scenario for the activity.
• Depending on the assumed distribution of values within the range of the three estimates, the expected duration,
tE, can be calculated. One commonly used formula is triangular distribution: tE = (tO + tM + tP) / 3.
• Triangular distribution is used when there is insufficient historical data or when using judgmental data.
• Duration estimates based on three points with an assumed distribution provide an expected duration and clarify
the range of uncertainty around the expected duration.
Critical Path Method-Objectives
Plan for the fastest completion of the project
1 1 1 1 1 I
2
G H
1 5 6 8 9 0
1 1 1 1 1 2
5 3 2
B 6 C 8 1 5 6 8 9 0
1 A 2 3 5
Sta
rt 1 1
1 2 2 3 3 5 6 3 8 F
6 6
2 2
1 1
9 D 0 0
0
1
20
9 2
0
1 Finis
9 E h
1
1 2
3 0
8
20
A B C G F = 16
ABCDGHI=
20
ABCDGF=
16
A B C E =11
Resource Optimization
• Resource leveling
Resource Leveling is primarily driven by resource constraints, like
you do not have more than 45 hours of the given resource for a
week.
Resource Leveling is primarily driven by resource constraints, like
you do not have more than 45 hours of the given resource for a
week.
The allocation limits identified in resource leveling must be
applied.
The resource leveling is done first and then we do the resource
smoothing. Since we need to first accommodate the resource
constraints before we can optimize it.
Resource Optimization
• Resource Smoothing
We apply resource smoothing after doing resource leveling
and we make use of slack and will not result in change of
project duration.
Resource smoothing is more to do with desired limits, like we
do have 45 hours available for given resource, but we wish
that we allocate 38 hours per week, so we have some
breathing space.
The desired limit identified in resource smoothing may not be
applied in some cases, if we do not have slack.
We apply resource smoothing after applying resource leveling.
SCHEDULE COMPRESSION Techniques
Attached
Sources of Cost Information
• Current Records usually from a database
(organized & protected)
• Subcontractor Quotations
• Vendor Quotations
• Published Cost Data
• Old Estimates
• Experience
Construction Cost Types
Direct Costs
Indirect Costs
• Make sure that the information has not only been received by the
receiver but it also has been understood.
• Make sure there are no barriers to interactions and communications
among stakeholders other than confidentiality or legal constraints, if any.
• Information exchange media should be chosen according to the situation.
For example, it must be carefully decided whether the medium should be
informal verbal or formal written.
• Project communications standards usually include a consistent writing
style, which must be followed for all written communications.
• Meeting management, facilitation, and presentation techniques must be
in compliance with project communications standards
Team Conflict Management