Professional Documents
Culture Documents
Mi Design of Concrete
Mi Design of Concrete
Mi Design of Concrete
Slump test
Compaction factor test
Flow table test
Vee-Bee test
Kelly ball test
Slump test
Tools and Apparatus used for Slump Test:
1. Standard Slump Cone (100 mm top diameter x 200 mm bottom diameter x 300 mm
height)
2. Bullet-nosed rod (600 mm long x 16 mm diameter)
3. Slump Plate (500 mm x 500 mm)
Procedure:
i. The mould in the form of a frustum of a cone is placed on a smooth surface with the
smaller opening at the top and filled with concrete in three layers.
ii. Each layer is tamped 25 times with a standard 16 mm φ steel rod.
iii. The top surface is struck off by means of a screeding and rolling motion of thetamping
rod.
iv. The mould must be firmly held against its base during the entire operation; this is
facilitated by handles or foot-rests brazed to the mould.
v. Immediately after filling, the cone is slowly lifted and the unsupported concrete will
now slump. The decrease in the height of the centre of the slumped concrete is called
slump.
Precautions:
The inside of the mould and its base should be moistened at the beginning of every
test.
The test should be repeated in case a shear slump is observed.
Slump Test is not suitable for too wet or too dry concrete.
Slump test is Done for medium to high workability
Table is then raised and droped 12.5 mm, 15 times in about 15 seconds
The diameter of spread concrete is measured in about 6 directions to the
nearest 5 mm and the average spread is determined
The flow of concrete is the percentage increase in the average diameter of the
spread concrete over the base diameter of the mould.
Flow percent = (spread diameter in cm-25)/25*100
According to Abrams, for any given condition of test, the strength of well
compacted concrete with good workability depends upon the w/c ratio.
Lesser the w/c ratio in the concrete greater will be the strength and vice
versa.
W/C conti….
From the figure, lower w/c ratio could be used when the concrete is
vibrated to achieve higher strength
Comparatively higher w/c is required when concrete is hand
compacted
In both insufficient compaction cases, when the water cement ratio
is below practical limit, the strength of concrete falls rapidly due to
introduction of air voids.
Introduction to Nominal Mix
the process of selecting suitable ingredients of concrete and determining
their relative quantities with the purpose of producing an economical
concrete which has certain minimum properties, notably workability,
strength and durability.
Mix Design is of three types:
(i) Nominal Mix
(ii) Design Mix
(iii) Standard Mix
In the past, the specifications for concrete prescribed the proportions of
cement, fine and coarse aggregates.
These mixes of fixed cement-aggregate ratio which ensures adequate
strength are termed nominal mixes.
Hence, nominal mix is prescriptive time aiming that adherence to such
prescriptive specification will result in satisfactory performance.
M10 = 1 : 3:6
M15 = 1 : 2:4
M20 = 1 : 1.5 : 3 – 60% construction in Nepal
M25 = 1 : 1:2
If the number of cube tests results are plotted on histogram, the results are
found to follow the bell shaped curve.
X/n
Standard deviation (σ)=
Coefficient of variation( C.V)= (σ/)*100
Where fm is the average strength obtained by dividing the sum of all strength by
the number of cubes
Characteristic strength (Fck)
The zone is determined by passing the sand through IS 600 micron sieve and obtaining the
data of passing.
Zone I = 15 to 39 %
Zone II = 40 – 59 %
Zone III = 60 – 79 %
Zone IV = 80 – 100 %
Figure 3. a) free w/c ratio for 10 mm aggregate
Step 7. Finally determine the proportion of mix w.r.t to the cement content.
For Sand
The sand lies in second zone.
From figure,
For maximum size of aggregates = 20 mm
% of fine aggregates = (42 + 32)/2 = 37% of fine aggregates
Hence, weight of fine aggregates = 37 % of 1763 = 652 kg for 1 m3 concrete
Weight of coarse aggregates = 1763 – 652 = 1111 kg for 1 m3 concrete
Finally the obtained results
MIX PROPORTION:
CEMENT SAND GRAVEL WATER for 1 m3 concrete
382 652 1111 210
1 1.71 2.91 0.55
1 : 1.71 : 2.91 @ 0.55
American Concrete Institute (ACI)
method for Mix Design
This method was suggested by ACI committee no. 211.
This method takes into consideration the requirements for
workability, consistency, strength and durability.
Uses dry rodded density of coarse aggregates.
Uses fineness modulus of fine aggregates.
One method is based on the estimated weight of concrete per unit
volume whereas the other is based on calculation of the absolute
volume occupied by concrete ingredients
Differences between British Method and ACI Method:
British
This method is suitable to design normal concrete mixes, ( non air entrained) for
different grades of cement based on 28 days strength
IS method steps
Step 1. Determine the target mean strength based on characteristic strength
and standard deviation
Step 2. a) determine w/c ratio from curve of compressive strength vs w/c
ratio
b) check the w/c ratio from the durability requirement.
select the minimum value of w/c ratio
Figure 1: w/c ratio vs compressive strength curve
Table: 1 , w/c ratio from durability consideration
Grade A: 32.5-37.5 Mpa
Grade B: 37.5-42.5
Grade C: 42.5-47.5
Grade D: 47.5-52.5
Grade E: 52.5-57.5
Grade F: 57.5-62.5
Grade G: 62.5-64.9 Mpa
IS method…
Step 3. determine the amount of entrapped air for the maximum size of
aggregate from table
Table: 2
IS method
Step 4. find the water content Ww)i and percentage of sand ( Ps)i in total
aggregate from table:
Table 3 Table 4
IS method
Step 5. make adjustments in water content and percentage of sand for
different conditions of workability from table and calculate actual value of Ww
and Ps.
Table 5: Adjustment of values in water contents and sand percentage for other conditions
Step 6. Calculations of cement content (Wc)
6.a ) wc=
6. b minimum cement content from durability consideration
take the maximum value of a) and b)
Step 7. determination of net volume of fresh concrete ( V)
V= 1- Vea
Step 8. Determine the amount of aggregate
for fine aggregate:
V=1/1000 [ Ww+ + ]
For coarse aggregate:
V= 1/1000[ Ww+ + ]
V= Net volume of fresh concrete = 1 m3-volume of entrapped air
Sc= specific gravity of cement
Sfa= specific gravity of sand (SSD)
SCA= specific gravity of coarse aggregate (SSD)
Ww= Mass of water per m3of concrete
Wc= Mass of cement per m3of concrete
WCA= Mass of coarse aggregate per m3of concrete
P= ratio of fine aggregate to total aggregate by absolute volume
IS method..
Step 9. Obtain the actual amount of water to be added after making
correction for water absorption by aggregate and free moisture present
in the aggregate. Similarly, get actual quantities for fine aggregate and
coarse aggregate required.
aWfa= (1+Mf)Wfa
aWca= (1+Mc)Wca
aWw= Ww-(Mf*Wfa+Mc*Wca)
awc/wc :awfa/ wc :awca/ wc :aww/ wc
Step 10. Check the calculated mix proportions by means of trial batches
and make suitable modification, if required.
3.6 Segregation and Bleeding
SEGREGATION IN CONCRETE
Segregation can be defined as separation of the constituents of a
heterogeneous mixture so that their distribution is no longer uniform.
In the case of concrete, it is the difference in the size of particles (and
sometimes in the specific gravity of the mix constituents) that is the primary
cause of segregation, but its extent can be controlled by the choice of
suitable grading and by care in handling.
Segregation may be of two types: internal and external.
In internal segregation, coarsest or heaviest part of aggregates accumulates
on the bottom and lighter or finer ones accumulate at the top during
compaction.
External segregation, on the other hand, is caused by external forces due to
say improper handling.
Causes of segregation
Poor mixing of concrete
Insufficient or over w/c content in the mixture
Improper grading of aggregate
Improper handling of concrete
Excessive vibration
Improper placing of concrete
Effects of seggregation
Bleeding can be reduced by the use of finer cement( finer cement has more
surface area) and reduces bleeding. Rich mixes are less susceptible to
bleeding than lean mixes.
Quality control in site
Concrete is usually produced in batches at the site with the locally available
materials of various characteristics
Quality control is therefore likely to vary from one batch to another batch
variations depends upon the factors like:
Variations in quality in materials
Variations in mix proportion
Variations in quality in batching
In mixing equipments
Quality of overall workmanship and supervision at site
thus the major aim of quality control is to reduce these different variations and
produce uniform materials providing desirable characteristics
Quality control in site : Batching, Mixing,
handling, placing, compaction and curing
a) Batching
Batching is the process of measuring concrete mix ingredients
either by volume or by mass and introducing them into the
mixture. Traditionally batching is done by volume but most
specifications require that batching be done by mass rather
than volume. Percentage of accuracy for measurement of
concrete materials as follows
Quality control at site: Batching, MIXING,
handling, placing, compacting and curing
MIXING
Thorough mixing of the materials is essential for the production of uniform
concrete.
The mixing should ensure that the mass becomes homogeneous, uniform in
colour and consistency.
There are two methods adopted for mixing concrete:
i. Hand Mixing
ii. Machine Mixing
Hand Mixing
Hand Mixing is practiced for small scale unimportant concrete works. As the
mixing cannot be thorough and efficient, it is desirable to add 10 percent
more cement to cater for the inferior concrete produced by this method.
Hand mixing should be done over an impervious concrete or brick floor of
sufficiently large size to take one bag of cement.
Machine mixing
If instead of being batched and mixed on site, concrete is delivered for placing
from a central plant. It is referred to as ready-mixed or pre-mixed concrete.
This type of concrete is used extensively abroad as it offers numerous
advantages in comparison with other methods of manufacture:
(a) Close quality control of batching which reduces the variability of the
desired properties of hardened concrete.
(b) Use on congested sites or in highway construction where there is little
space for a
mixing plant and aggregate stockpiles;
(c) Use of agitator trucks to ensure care in transportation, thus prevention
segregation and maintaining workability
(d) Convenience when small quantities of concrete or intermittent placing are
required.
Agitator truck
Handling of concrete
There are many methods of transporting of concrete from mixture to site like
mortar pan
Wheel borrow
Crane, bucket, and ropeway
Truck, mixtures and dumpers
Belt conveyors
Chute
Skip hoister
Pump and piping
Transit mixture
Mortar pan
Wheel barrow
Belt conveyors
chute
PLACING AND COMPACTION OF CONCRETE
The operation of placing and compaction are interdependent and are carried
out simultaneously.
They are most important for the purpose of ensuring the requirements of
strength, impermeability and durability of hardened concrete in the actual
structure.
As for as placing is concerned, the main objective is to deposit the concrete as
close as possible to its final position so that segregation is avoided and the
concrete can be fully compacted.
It is to get the concrete into position at a speed, and in a condition, that allow
it to be compacted properly
Rules to be kept in mind before placing
The concrete should be placed in uniform layers, not in large heaps or
sloping layers.
The thickness of the layer should be compatible with the method of
vibration so that
entrapped air can be removed from the bottom of each layer.
The rate of placing and of compaction should be equal.
Each layer should be fully compacted before placing the next one,
and each subsequent layer should be placed whilst the underlying
layer is still plastic so that monolithic construction is achieved
Collision between concrete and formwork or reinforcement should be
avoided.
For deep sections, a long down pipe ensures accuracy of location of
concrete and minimum segregation.
CURING OF CONCRETE
Maintaining the presence of mixing water during the early hardening period
methods used include ponding or immersion, spraying,
Preventing loss of mixing water from the surface by sealing
Accelerating strength gain by supplying heat and additional moisture to the
concrete. This may be accomplished using stream curing, insulting blankets or
covers
Concreting in extreme weather
temperature
Concreting in extreme weather temperature
a) Concreting in hot weather
b) Concreting in cold weather
Concreting in hot weather
It is difficult to define what hot weather condition is. However just for convenience, it is
regarded that the concrete placed at an atmospheric temperature above 40 degree
centigrade is considered as hot weather concreting
Problems
Rapid rate of hydration of cement, quick setting and early stiffening.
Rapid evaporation of mixing water
Greater plastic shrinkage
Reduce relative humidity ( this point is positive from corrosion point of view but required
more curing)
Concreting in extreme weather temperature-
Concreting in hot weather
Problems
Absorption of water from the concrete by the sub grade and formwork
Difficult in continuous curing due to being more hot in less time
Difficult in incorporation of air entrainment
Precautions
Kept temperature as low as possible by shading the aggregate piles and the
mixture
Reduce the temperature of aggregate by sprinkling water on it. The evaporation
of sprinkled water will cool the aggregate
Keep water supply cool by insulating or shading pipes and tanks
Use crushed ice with mixing water
Effect of hot weathering can also be reduced by working at night time
For curing, covering with wet burlap (jut bag) or by sprinkling or by other
moisture retaining materials has been found better as it has a definite cooling
value.
Concreting in extreme weather temperature-
Concreting in cold weather
Concreting in cold weather
The Temperature generally freezing temperature is considered as cold weather
for concreting
Problems
Delay in setting and hardening
Freezing of concrete at early age
Freezing and thawing: setting of concrete is suspended if concrete freezes
immediately after it has been placed. If concrete freezes after it has sets but
before it has attained sufficient strength, the expansion due to the formation of
ice causes disruption and loss of strength. If freezing takes place when concrete
has developed sufficient strength ,it can resist freezing effect without damage
not only by virtue of the higher resistance to the pressure of ice but also due to
the fact that large parts of the mixing water will have combined with the
cement or located in the gel pores and thus would not freeze.
Concreting in extreme weather temperature-
Concreting in cold weather
Precaution
Heat mixing water, to increase temperature of fresh
concrete
Heat aggregate, if water (hot water) alone does not
raise the temperature of concrete
Use of cement of high rate of heat generation (i.e.
cement having high C3S and C3A produced high heat
during reaction)
CURING UNDER DIFFERENT WEATHER CONDITIONS:
Under normal weather, the key concerns in curing will be the maintenance of a
moist environment around the concrete.
Temperature variations are not a major problem, provided the concrete
temperature is maintained above 5 degrees Celsius.
Curing can therefore be achieved either through maintaining mixing water in
the concrete during early hardening or by preventing moisture loss from the
surface by sealing. The ultimate choice of the particular method to use will take
into consideration factors such as economy, esthetics, member shape, etc.
Under hot weather conditions, the high temperatures are likely to result in
excessive moisture loss. Maintaining mixing water in the concrete is the major
concern. Continuous moist curing should be done for the entire curing period.
If this is not possible, the concrete surfaces should be protected from drying out
using any of the previously mentioned methods and the surfaces kept damp.
Surfaces should dry out slowly after curing to reduce possibility of surface
cracking.
Curing….
Curing in cold weather will be different as in this case the biggest concern will be the maintaining
of an adequate and conducive temperature for hydration.
For massive members, the heat generated by the concrete during hydration will be adequate to
provide a satisfactory curing temperature.
For non-massive members, a good alternative is steam curing, which provides both moisture and
heat. In any case, a minimum favorable temperature in the range of 10 - 21º C must be maintained
in the concrete for the minimum required curing period.
Where moist curing is not done, very low temperatures may be avoided by insulating the member
appropriately.
CURING PERIOD AND TEMPERATURE:
The curing period depends upon the type of cement used, mixture proportions,
required strength, size and shape of member, ambient weather, future exposure
conditions, and method of curing. Since all desirable properties are improved
with curing, the period should be as long as practical.
For most concrete structures, the curing period at temperatures above 5º C (40º
F) should be a minimum of 7 days or until 70% of the specified compressive or
flexural strength is attained.
The period can be reduced to 3 days if high early strength concrete is used and
the temperature is above 10º C (50º F).