CERC Tariff Regulations: 2019-24: Workshop at Mangalore - 27 June 2019
CERC Tariff Regulations: 2019-24: Workshop at Mangalore - 27 June 2019
CERC Tariff Regulations: 2019-24: Workshop at Mangalore - 27 June 2019
Security Exp.- Separate account to be kept. All CISF & other security Exp. (including housing, medical,
etc.©related
Copyright to security)
2016 Your Company to be booked separately / apportioned.
All Rights Reserved. 7
Target Availability – Reg. 42 - thermal
AFC (annual fixed cost) split into capacity charges for High Demand Season and Low Demand Season (w.e.f
01.04.2020)
Concerned RLDCs shall high / low demand months at least 6 months in advance.
Peak hours to be declared by RLDC at least 1 week in advance
High Demand Season Low Demand Season
3 months – (Consecutive or otherwise) 9 months –(consecutive or otherwise)
Peak Hours (4 hours in a day) Peak Hours (4 hours in a day)
Target Availability of 85% to be achieved on cumulative 85% Target Availability to be achieved. (on cumulative
basis for 3 months basis for 9 months)
Off-Peak Hours (20 hours in a day) Off-Peak Hours (20 hours in a day)
85% Target Availability to be achieved on cumulative 85% Target Availability to be achieved(on cumulative
basis for 3 months). basis for 9 months)
Any under achievement in availability during off-peak hrs Any under achievement in availability in off-peak hrs can
can be off-set by overachievement in peak hours during be off-set by overachievement in peak hours during low
high demand season. demand season.
In coal shortage scenario, stations can minimize under recovery of AFC by declaring higher DC (>85%) in peak hrs.
Annual Overhauling Planning Strategy – Most overhauling to be planned in low demand season.
Incentive Reg.- 42 (6)- thermal
Applicable on achieving Normative Annual Plant Loading Factor (NAPLF) of 85% on a
cumulative basis within each Season (High Demand or Low Demand Season) (wef
01.04.2020)
APC for ECS, Sewage Treatment Plant and External CHP (Jetty & associated infrastructure) to be
considered separately.
APC shall not include colony consumption, construction power and consumption by integrated coal mine.
However, CERC in the SOR has clarified that generating stations shall continue to draw power from the
station for colony consumption.
The beneficiary will have the first right of refusal to enter into agreement
On refusal, the generating shall be free to sell the electricity generated from such
station in a manner as it deems fit
Appropriate regulations shall be notified separately for computing input price of coal /
lignite for energy charges, which shall be applicable from 01.04.2019 or the COD of
integrated mine, whichever is later.
Till such time, the generating company shall continue to adopt notified price of Coal
India commensurate with the grade of the coal from integrated mine and in case of
lignite the Guidelines specified by MoC, GoI, shall continue.
Difference between the input price as per the above regulations and notified CIL price
shall be adjusted as per the above regulations.
Other Provisions
Mismatch in Generation & its associated transmission
Delay in COD of Generator & COD of associated transmission allowed by CERC:
Generator to pay transmission charges till COD of generator.
Delay in COD of transmission & Generator is ready: Transmission Licensee to
make alternate evacuation arrangement, failing which it shall pay transmission
charges to generator till COD of transmission.
Cut-off date – Last day of calendar month after 36 months from COD of
project.
Other Provisions
Late Payment Surcharge :
Applicable beyond a period of 45 days
1.50 % per month
Rebate:
1.5% within a period of 5 days of presentation of bills;
1% after 5 days within 30 days.
Sharing of Non-Tariff Income:
Non Tariff income to be shared with customers in the ratio of 50:50
Includes rent, sale of scrap, income from advertisements etc.
Shall not include interest/ dividend earned corresponding to regulated business
Landed Price of Reagents for ECS
Consumption on normative basis – To be notified separately.
Purchase price of reagent through competitive bidding plus applicable
statutory charges and transportation charges
29