Device Management Improvement Plan FY19 - 20
Device Management Improvement Plan FY19 - 20
Device Management Improvement Plan FY19 - 20
July 2019 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Download 38,800 38,930 38,930 38,930 38,930
Read 35,639 36,204 36,983 37,762 38,151
Performance 91.85% 93.00% 95.00% 97.00% 98.00%
PROJECTED PERFORMANCE
o The table reflects actual performance for July 2019 and projected performance for the FY 2019/20.
o The forecast indicates that LPU meter reading performance will improve to 98% by the 3rd quarter.
Resources
Region/ Category Daily Target Weekly Monthly
available
25 1 20 100 400
35 1 20 100 400
45 1 20 100 400
55 1 20 100 400
65 1 20 100 400
75 2 40 200 800
85 1 20 100 400
8 160 800 3200
Monitor data quality controls and data flow process enhancements (including creation of job cards where necessary) in between
the Field and Device Management to ensure resolution is fast-tracked – this include the following:
Meters not on IEE
Meters on IEE under Different installation
Same Installation but Meter differ SAP&IEE / Meter on SAP under different Installation Code
Same Installation but Meter Differ SAP&IEE / SAP Meter not on IEE
7% LPU Improvement breakdown plan
• The above table reflects the exceptions that will be tracked on a daily basis, priority will be given to 1026 offline meters. Below
is the breakdown as follows
o 353 meters that have been offline from January – June 2019 (2.67%)
o 121 meters that have been offline from January – December 2018 (0.91%)
o 187 meters that have been offline beyond 2018 (1.41%)
o 142 System update (1.07%)
o 208 meter updated on a different address on SAP ISU (1.57%)
o Total contribution of offline meters is 7.64%
PRE-BILLING PROCESS
We have institutionalised the pre-billing process A total of 12 resources from 4 departments have been
committed to optimising the pre-billing process .
2 Revenue Management 2
3 Device Management 1
4 Revenue Management 1
4 5
On receiving approval on removal On receiving manual and 6
5 Smart Centre 2
of missing customers a separate automated reading, Pre-billing List of Flagged accounts must be
meter reading database must be flagging must occur prior to sent to Device Management for
compiled to test that no feeding consumption through to data validation 6 Device Management 1
consumption occurs MRQC
7 Device Management 1
8 Smart Centre 2
7
8
Upon resolution of flags
MRQC data to be uploaded to
consumption must be feed onto
SAP
MRQC
7
PRE-BILLING EXCEPTION
Field/Device/Smart
Baseline LPU TOU Business Residential
Centre
Risk Risk Risk Risk Risk Risk Risk Risk Risk Risk
Risk Level Risk
Level Level Level Level Level Level Level Level Level Level
High Level Low
Medium Low High Medium Low High Medium High Medium Low
Average Selling Price 50 50 50
Energy Mix 54 45 9
Load factor 4957 1287 25 75 58 1622 123 187 1416 39 74
Missing Readings 546 144 4 215 179
Trend consumption 5890 970 426 70 42 7 2 1181 635 63 1525 895 48
Possible Ghost
658 186 297 164
Accounts
Stuck Meters 634 168 2 246 214
2257 831 195 145 20 2 2803 1270 250 2941 1277 122
3283 167 4323 4340
8 10 50 150
4 10 50 150 5 10 50 150 4 10 50 150
Total 80 400 1200
Total 40 200 600 Total 40 200 750 Total 40 200 600
Monitor data quality controls and data flow process enhancements (including creation of job cards where necessary) in between the Field and Device
Management to ensure resolution is fast-tracked – this include the following:
o Acquiring the meter change information i.e. job card daily
o Validating the information on the system
o Updating the new meters on the billing system
o Run a daily report of interface errors and send to Revenue Shared Services Centre to clear the interface errors.
Operational SLA with COJ has been developed to ensure that interface errors are cleared daily and a weekly sign-off on files received vs. Updated.
o The total of 903 System Updates (3%) backlog will be cleared in the 1st Quarter and current system updates from Project (Region B,C and G) will
updated immediately.
o The plan is that Faulty meters (2%) and Bypassed meters (1%) that are not in Region B,C and G will be replaced by Field Maintenance within
the meter reading cycle.
o For actioning of Inaccessible meters (15%) it has been agreed with Revenue Protection that feedback will be provided daily ,and update of the
readings is done by Device Management on MRQC. Inaccessible meters includes problematic areas (NewClare,Waterval,Claremont,Noordgesig,
Kensington) which will be tracked separately.
o Rollout of smart meters will focus on Region B ,C and G to further improve the meter reading performance-thus ensuring that final readings can
be utilized for billing purposes and stabilize the performance. A total of 14299 meters are in these regions, out of these meters 3640 are sitting under
exceptions. Engineering Services will be converting 2400 meters for this quarter.
MANUAL DOMESTIC PROJECTED PERFORMANCE
Projected Performance
• The above table reflects actual performance for July 2019 and projected performance for the FY 2019/20. The performance will
improve to 90% in March 2020.
• Our plan is to increase the meter reading performance by 3% from September, for us to achieve 90%.The above plan also shows that
during the months of December and January the performance will drop due to the festive holidays and unavailability of customers.
SMART METER ROLL OUT PLAN
• The Rollout project will focus on Region B, C and G for the 1st quarter and ensure that all manual read meters are
changed on these regions.
• The plan is that all meters will be replaced within the meter reading cycle – thus ensuring that final readings can be
utilized for billing purposes and updates are completed before the next download file is created .
• A total of 2400 smart meters will be installed in the 1st quarter, weekly meetings will be held between Device
Management and Execution to be monitor progress and mitigate any challenges.
PROBLEMATIC AREAS
• Region B file has a total of 9669 meters and the problematic areas above are contributing 8% of the performance for the region. Stakeholder
Management and Revenue Protection will be assisting in order to improve Meter Reading Performance.
REG ITRON PERFORMANCE -June-2019 Plan is to increase monthly AMI reading performance by 1,5% monthly so
Region Itron (19) Read N15 Perfomance %
that by end of Q1 we are at 98% from current 95%.
97.63%
Region A 6,713 6,554 159 In order for us to achieve this, the following needs to happen:
96.20%
Region B 27,918 26,856 1,062 • 277 and 53 non smart Meters need to be reassigned to the correct
97.31% reader ID. Device Management will assist with the correction of the
Region C 27,423 26,685 738 reader ID.
80.09%
Region D 924 740 184 • 246/1686 unread meters include a backlog from Q4 baseline which
95.58% consist of no go areas. JMPD will assist with security management.
Region E 14,943 14,283 660
• The above table reflects actual vending performance for affluent and non affluent areas per Depot
• Lenasia is the lowest performing depot, the improvement plan for the 1 st quarter will focus on Lenasia
which will increase the overall vending performance by 5%.
PREPAID REGISTRATIONS
Region G - PLAN
• 3000 L&G smart meters will be installed
Power Park
27
in Region G in the 1st Quarter.
Zakariya Park 394
Mid-Ennerdale 221
performance in Lenasia Depot by 7% in
the 1st Quarter.
Lenasia South 1,746
- 500 1,000 1,500 2,000 2,500 3,000 • Risk: The engagements with the
Regional Director and Councillor might
No. of active customers in Sales for June 2019 Number of Suburbs delay the process
Region G Affluent
• Business Customers will be monitored closely to improve vending performance to 90% in the 1 st Quarter.
• Device Management will work closely with Revenue Protection on the non vending customers, performance will be tracked on a weekly
basis. 458 non vending customers have been forwarded to Revenue Protection for disconnection.
P R E PA I D D ATA C O M P L E T E N E S S P L A N
SGID % July % 1st Quarter % 2nd Quarter % 3rd Quarter % 4th Quarter %
2019 2019 2019 2019 2019
VALID
SGID'S
55% 132986 55% 138986 57% 144486 59% 153486 62% 162486 66%
NO SGID'S 45% 110668 45% 104668 43% 99168 41% 96168 38% 87168 34%
Projected Performance
RSSC is overseeing the billing completeness Integration between them and Device Management Meetings
Revenue Shared Services Centre
process. It is them who are tasked with management to ensure meters are Operational Meetings
service delivery and changing in a positive timeously updated on the system through Telephone
manner the lives of the people of the interface. Emails
Johannesburg Readings provided are not deleted
Minimise estimated accounts beyond bylaw
Engineering Services – Capital Execution is responsible for the Installation of smart meter in the City of Management Meetings
installation of Smart Meters which will improve
Capital Execution Johannesburg. Operational Meetings
meter reading performance and provide Integration between them and Device Telephone
revenue assurance. management to ensure meters are Emails
timeously updated on the system
Meter
Meter Reading
Reading Policy
Policy Vending
Vending Policy
Policy Pre
Pre Billing
Billing Policy
Policy
BoardApproved:
Board Approved: BoardApproved:
Board Approved:
New
New
FY2014/15
FY 2014/15 FY2014/15
FY 2014/15
Tobe
To bereviewed
reviewedby:
by: Tobe
To bereviewed
reviewedby:
by: Tobe
To bedeveloped
developedby:
by:
July2020
July 2020 July2020
July 2020 July2020
July 2020
Plan
Plan for
for submission:
submission: Q3
Q3 Plan
Plan for
for submission:
submission: Q3
Q3 Plan
Plan for
for submission:
submission: Q4
Q4
24