Professional Documents
Culture Documents
Brief Presentation FOR MARAFIQ CONTRACT#7200040904: Project Title
Brief Presentation FOR MARAFIQ CONTRACT#7200040904: Project Title
BRIEF PRESENTATION
FOR
MARAFIQ CONTRACT#7200040904
PROJECT TITLE
REPLACEMENT OF CONCRETE PIPES WITH FRP PIPES IN CANAL 1, 2 &
3 FLOW METER CHAMBERS.
MEETING AGENDA
1. What is an FRP pipe?
2. Advantages of FRP
3. Pipe Joining Systems
4. Project Purpose
5. Project Background
6. Brief Scope of Work
7. Project Implementation Plan
8. Site Photos
9. 90 Days Look Ahead Plan
10.Project Organization Chart
WHAT IS AN FRP PIPE?
• FRP-FIBRE REINFORCED PLASTIC
2. Non-restrained joints
• Where gasketed joints are installed.
• Can be used only in underground systems where
soil stiffness & thrust blocks resolve the axial forces
generated by internal pressure and thermal loads.
• Cannot be used for directly buried pipe under road
crossings.
• Unrestrained gasketed joints may be bell-and-
spigot type utilizing double O-rings or double bell
couplings with specialized gaskets.
PIPE JOINING SYSTEMS
PROJECT PURPOSE
• The purpose of this contract is to replace the damaged concrete pipes with FRP
pipes in Canal 1,2 & 3 Flowmeter Chambers, SWC-Jubail.
• Replacement will be done within the chamber of Flowmeter which are located
along the bank of supply and Return canals.
PROJECT BACKGROUND
• Seawater canals-------------Supply Sea Water---------13 Sabic Affiliates
PROJECT BACKGROUND
BRIEF SOW
S/N PROJECT PHASE JOB SEQUENCE
• Check extent of Damage of Exisiting Concrete Pipes.
• Check Functionality of Existing Transducers.
• Physical inspection of existing Junction box and Instrumentation
Detailed Site Survey and Data signal cabling condition.
1
Collection • Physical inspection of Flow meter chamber walls.
• Preparation of Survey Report and submit to Marafiq for review
and approval.
• Based on Collected Data.
• Design Criteria.
2 Detailed Design and Engineering • Design Calculations shall be based on relevant RC standards
(Section 02086, Guideline Spec. for FRP Pipes) and AWWA M-
45.
• Setup site offices and laydown area.
3 Mobilization • Mobilization of Project Management Personnel.
• Erection of Project Signboard.
• FRP Spool Pipes, Fittings, SS straps etc.
• Reinforced Concrete
3 Procurement of Material • Material-Grouting, surface reconditioning and Epoxy Resins.
• Galvanized Cable Trays
BRIEF SOW CONT.
S/N PROJECT JOB SEQUENCE
PHASE
• Isolation of the flow meter chamber.
• Removal of roof shed.
• Removal of Walkway.
• Removal of exisiting transducers from housing and 3rd party calibration to check for reusability.
• Installing barriers on each side of the lateral chamber for isolating it.
• Dewatering the inside lateral chamber for making it suitable for installation works.
• Cutting of the concrete pipe.
• Demolition of existing concrete pad.
• Erection of reinforced concrete pedestals.
• Lowering of middle FRP spool piece on the concrete support using hoist cranes.
• Installation of end spools using FRP pipes with puddle flanges and drilling holes into the concrete
4 Construction walls for inserting the threaded rods.
• Installation of bell couplings at the joining ends of both end spools.
• Check Alignment of these FRP spool pieces.
• Pouring of Grouting material in the annular spacing between FRP spool and existing Concrete
pipe.
• Re-Installation of transducers after certifying their functionality over the FRP nozzles.
• Laying of coaxial signal cabling from the junction box till these transducers.
• Terminating these signal cables at the junction boxes.
• Reinstatement works
BRIEF SOW CONT.
S/N PROJECT PHASE ACTIONS
• Gravity testing of the installed FRP spool piece.
Testing and • Testing and commissioning of complete system for measurement of flow after
4
Commissioning programing the system by third-party vendor i.e. Transducer manufacturer.
Installation of Transducer in FRP nozzles and its alignment & its programming
Flood test/Gravity Test of FRP system and commissioning of Flow meter System
Handover of documentation to Marafiq BU including As-Built drawings, Red Line, O&M manuals, certificates and reports