Progress Civil 09.08.16
Progress Civil 09.08.16
Progress Civil 09.08.16
2016)
SN Activity Date of Completion Revised D.O.C.
1 Topographic Survey Report 28 July Completed
4 First discussion with MD/CMRL 3rd to 6th Aug 1st to 3rd Aug
7 Utilities data collection 1st Aug - 20th Aug 19th Aug - 02nd Sept
8 Utilities Marking on Drawing 20th Aug - 26th Aug 05th Sept – 09th Sept
9 Land requirement 29th Aug – 02nd Sept 05th Sept – 14th Sept
10 Cost Estimate 29th Aug – 02nd Sept 16th Sept - 20th Sept