SN Activity Date of Completion Revised D.O.C.
1 Topographic Survey Report 28 July Completed

2 Geotechnical Investigation 15 Aug Completed

3 Draft Horizontal Alignment 29 July Completed

4 First discussion with MD/CMRL 3rd to 6th Aug 1st to 3rd Aug

4a Second discussion with MD/CMRL -- 16th to 18th Aug

5 Vertical Profile 8th to 26th Aug 19th Aug - 09th Sept

6 Alignment Report 30th Aug 15th Sept

7 Utilities data collection 1st Aug - 20th Aug 19th Aug - 02nd Sept

8 Utilities Marking on Drawing 20th Aug - 26th Aug 05th Sept – 09th Sept

9 Land requirement 29th Aug – 02nd Sept 05th Sept – 14th Sept

10 Cost Estimate 29th Aug – 02nd Sept 16th Sept - 20th Sept

11 Chapter writing 02nd Sept – 15th Sept 30th Sept