Professional Documents
Culture Documents
Lecture 2 - Powerpoint
Lecture 2 - Powerpoint
LAW
HONG KONG
LECTURE 2
General Information
▪ The opinions expressed at or through this Presentation are the
opinions of the Presenter and may not reflect the opinions of the
Organizer or General Community at Large.
▪ This presentation is for educational purposes only.
▪ The Presenter made reference to a variety of articles and
Publications in compiling these slides.
▪ The Presenter would also like to take this opportunity to
acknowledge the references made within this presentation.
WHAT ARE THE MAIN SOURCES OF LAW THAT GOVERN AND
REGULATE CONTRACTS FOR THE DESIGN OR CARRYING OUT
OF BUILDING WORKS?
▪ Hong Kong is a common law jurisdiction, meaning that the law derives from judges' decisions and is
developed by the courts. In Hong Kong, there is also legislation governing issues relating to
construction safety and building works. In Hong Kong, construction law is made of five main bodies
of law:
▪ Contract law – governing agreements between the parties.
▪ Tort law – during the construction process, events may occur that affect people and/or their property
and economic interests outside the ambit of other relationships such as contract. Tort law is the law
which addresses, and provides remedies for, civil wrongs not arising out of contractual obligations.
▪ Legislation – various ordinances and subordinate legislation (i.e. regulations) which govern the
carrying out of construction operations.
▪ Law of restitution – this area of law is concerned with the award of remedies which have one
common function – to deprive the defendant of a gain, rather than to compensate the claimant for
loss suffered. It is not uncommon to see claims being made on the basis of quantum meruit (the
amount deserved) and/or the prevention of unjust enrichment.
▪ Criminal law – sanctions are imposed for acts and omissions which constitute criminal activity.
WHAT OFFICIAL PERMISSIONS, LICENCES OR CONSENTS ARE
REQUIRED BY A BUILDING OR ENGINEERING CONTRACTOR
BEFORE IT CAN START WORK?
▪ Under the Buildings Ordinance (Cap. 123 of the Laws of Hong Kong), the carrying out of large-scale building works or
works of a very simple nature (such as the erection of drying racks on the external walls of household apartments) are
governed by the same set of controls, including the requirements to obtain prior approval and consent from the Buildings
Department before commencement of works and to appoint Authorized Persons (APs) (architects, engineers and surveyors
registered under the Buildings Ordinance), and registered professionals to design and supervise the works as well as
registered contractors to carry out the works.
▪ The approval of plans takes approximately two months.
▪ Any person who intends to carry out building works is required by law to appoint an AP, and where necessary a registered
structural engineer and, if building works at any stage involve geotechnical elements, a registered geotechnical engineer, to
prepare and submit plans for the approval of Buildings Department under the Buildings Ordinance.
▪ Consent for commencement of work takes approximately 28 days.
▪ Consent to commence building works is required from the Buildings Department before the works start and the Buildings
Department will monitor sites with works in progress and inspect sites regularly, particularly at critical stages, for safety
assurance and for compliance with statutory requirements under law.
▪ The requirements of the above system are too stringent for minor works which are of a smaller scale and pose a lower level
of risk, so as a result the Hong Kong SAR Government introduced the Minor Works Control System, facilitating members of
the public to carry out minor works in private buildings lawfully through simplified procedures and thereby improve the
building safety in Hong Kong.
RULES RELATING TO HEALTH AND
SAFETY ON CONSTRUCTION SITES?
In Hong Kong, the following legislation is important regarding construction site safety:
• Factories and Industrial Undertakings Ordinance (Cap. 59 of the Laws of Hong Kong);
• Construction Site (Safety) Regulations (Cap. 59I of the Laws of Hong Kong);
• Factory and Industrial Undertakings (Safety Officers and Safety Supervisors) Regulations (Cap.
59Z of the Laws of Hong Kong);
• Factories and Industrial Undertakings (Safety Management) Regulations; and
• Occupational Safety and Health Ordinance (Cap. 509).
▪ These rules mainly relate to health and safety during the construction process and not the use of
the development after construction is completed.
▪ Statutory duties give rise to criminal liability which means that an offender can be prosecuted by
the enforcement agencies and brought before the courts to answer criminal charges in addition to
civil liability in tort (i.e. the law that addresses, and provides remedies for, civil wrongs not arising
out of contractual obligations).
WHAT TYPE OF LEGISLATION EXISTS DEALING WITH
ENVIRONMENTAL ISSUES AFFECTING BUILDING WORKS
AND WITH PROMOTING SUSTAINABLE DEVELOPMENTS?
There is Government control via:
• Licensing mechanisms e.g. noise control permits, discharge sciences;
• Town planning and building laws; and
• Criminal offences prosecuted by government authorities (e.g. Police, Environmental Protection Department, Labour Department).
▪ What arrangements are usually made with the local authorities and
utility suppliers in relation to infrastructure (new roads, sewers etc..) to
support a new development?
▪ Arrangements are usually made with the Hong Kong Police Force and the
Transport Department which are the agencies through which transport policy is
enforced.
▪ Developers also work closely with other departments such as the Water Supplies
Department, Drainage Services Department, Civil Engineering and Development
Department, Buildings Department, etc.., regarding roads and associated drainage.
▪ In performing building development works adjacent to public roads, developers
also have frequent and close contacts with the utility operators.
ARE ANY TERMS AND CONDITIONS IMPOSED OR IMPLIED BY
LAW OR MANDATORY IN CONTRACTS FOR THE DESIGN OR
CARRYING OUT OF BUILDING WORKS? [SLIDE 1 OF 2]
▪ Every contract must include an adequate mechanism for determining what payments become due, when they
become due and a final date for payment. A party is also entitled to payment by instalments, stage payments or
other periodical payments. Finally, a party also has the right to suspend performance for non-payment. If the
contract does not make adequate provision, the provisions of a statutory scheme will automatically apply to it.
▪ The Development Bureau of the Government of Hong Kong Special Administrative Region is consulted on an
important new legislation for the construction industry known as Security of Payment Legislation (SOPL).
The SOPL will apply to all contracts and sub-contracts for public sector works including maintenance and
renovation. In the private sector, SOPL will only apply to the procurement of new buildings at a cost over
HK$5 million or related consultancy services costing over HK$0.5 million. Private sector repair, maintenance
and renovation will not be covered.
▪ Under the proposed SOPL, parties will remain free to agree when claims for payment can be made for works,
services or supplies. Parties will also be free to agree how payments are valued. However, SOPL will prohibit
fundamentally unfair payment practices, including ‘pay when paid’ clauses (where a main contractor
withholds payment to a sub-contractor until the main contractor has been paid by the client) or unreasonably
long payment periods.
▪ The consultation stage of SOPL was completed on 31 August 2015 and the Report on Public Consultation was
issued in April 2016. In conclusion, there is positive support for SOPL and the Government intends to proceed
with the legislation.
ARE ANY TERMS AND CONDITIONS IMPOSED OR IMPLIED BY
LAW OR MANDATORY IN CONTRACTS FOR THE DESIGN OR
CARRYING OUT OF BUILDING WORKS? [SLIDE 2 OF 2]
▪ The Contracts (Rights of Third Parties) Ordinance, Cap 623, which came into force on 1
January 2016, also applies to construction contracts. Under this Ordinance, a third party
can enforce a term of the contract, if the contract expressly provides for this, or if, on the
proper construction of the contract, the term purports to confer a benefit on the third party.
▪ As far as the works themselves are concerned, the contractor must do the work with all
proper skill and care. Breach of this duty includes the use of materials containing patent
defects. There is also an implied warranty that the contractor will use materials that are
reasonably fit for the purpose for which they are to be used (whether or not that is a
purpose for which the materials are commonly supplied) and of good quality. If a contract
is silent in relation to liability for design, there is an implied term that the services will be
carried out with reasonable skill and care. The burden of proof falls on the party claiming
that the supplier of the service (design and build contractor, design sub-contractor or
consultant) has failed to use reasonable skill and care. These terms will be implied only if
the contract is silent on the issues; express terms are required to displace the implication
of these terms.
INDUSTRY FORMS OF AGREEMENT
Institutional standard forms are issued by public and local authorities and sanctioned by the
construction institutions.
Examples include the:
• Agreement and Schedule of Conditions of Building Contract for Use in Hong Kong – Standard
Form of Building Contract (Private Edition), issued under the sanction of the Hong Kong Institute
of Architects / Hong Kong Institute of Surveyors ("HKIS");
• Joint Contracts Committee (JCC);
• Standard Form of Building Contract (JCT);
• Institute of Civil Engineers (ICE) Conditions of Contract Measurement Version;
• ICE Design and Construct Conditions of Contract;
• ICE New Engineering Contract; and
• International Federation of Consulting Engineers – Conditions of Contract for Building and
Engineering works designed by the Employer
PARTIES TO A CONSTRUCTION
OR
ENGINEERING CONTRACT
[PART1 OF 3]
The term ‘force majeure’ is used with reference to all circumstances independent of the will of
man and which are not in his power to control. Unlike most industry forms, the Standard
Form of Building Contract often used in Hong Kong do contain a force majeure clause
allowing the contractor additional time to complete the works. The term ‘force majeure’ must
be construed as a whole with the rest of the contract and with regard to the nature and other
terms of the contract.
COVID-19 AND FORCE MAJEURE
▪ The term ‘Force Majeure’ is not used in all the commonly used standard forms
of construction contract, perhaps reflecting the fact that it is not an established
concept in many common law jurisdictions.
▪ However, the standard form contracts do all contain provisions that deal in one
form or another with the impact of unforeseen and exceptional events such as
Covid-19.
▪ These provisions are included to provide a mechanism for controlling the effect
of unforeseen supervening events, such as Covid-19.
▪ The parties, however, frequently amend standard form Force Majeure clauses,
meaning contracts must be considered individually. A common amendment, for
example, is to include an exhaustive list of force majeure events, or to perhaps
exclude the impact of a Force Majeure event on labour or other resource
availability.
THIS TABLE ON THE NEXT SLIDE CONSIDERS HOW:
▪ For contracts which have yet to be entered into Covid-19 is no longer ‘unforeseeable’ and as a result
it will not be a Force Majeure event (save perhaps for JCT contracts which do not contain a
foreseeability test for force majeure). For future contracts it is therefore essential to expressly
provide for the time and cost risk of Covid-19 in the contract.
THE PRACTICAL IMPLICATIONS OF
COVID-19 AS A FORCE MAJEURE
EVENT FOR CURRENT PROJECTS
THE PRACTICAL IMPLICATIONS OF
COVID-19 AS A FORCE MAJEURE
EVENT FOR FUTURE PROJECTS
COVID-19 AND CHANGE IN LAW
▪ Whilst contractual provisions dealing with Force Majeure are an obvious place to
begin when considering entitlement for the impact of Covid-19, there may be scope
for a contractor to argue that other contract provisions are relevant – particularly those
dealing with Change in Law, variations or suspension. Some contracts grant
additional time, but not costs, for Force Majeure – but will grant both forms of relief
for a Change in Law. Future bulletins will return to variations and suspension in
relation to Covid-19, but this bulletin focuses on the relief available for Change in
Law.
▪ Covid-19 is such an unprecedented threat that it has led to the introduction of a raft of
governmental actions (i.e. ‘advice’ or ‘recommendations’) as well as new legislation
around the world. There is therefore a strong possibility that the Covid-19 impact on
projects may trigger Change in Law entitlement under many construction contracts.
As is the case with Force Majeure, the concept of a Change in Law and the available
contractual relief is dealt with in different ways under the major standard-form
constructions contracts.
▪ As with Force Majeure provisions, it is likely that the standard form contracts will have been heavily amended in
terms of applicable change in law provisions. It is therefore important to check each contract carefully. For example, a
common amendment is to allocate the risk of reasonably foreseeable changes in law to the contractor.
▪ In practice, whether a contractor is entitled to additional costs due to a Change in Laws will be fact specific and
decided on a contract-by-contract basis.
▪ Where the Government has introduced legislation to require the closure of construction sites, contractors may be entitled to rely on the relief available for a
Change in Law.
PUBLIC PROCUREMENT
▪ Payment is usually made when the works are completed. However, it is common for the
contractor to have the right of payment by instalment or interim payment in the progress of the
construction as it gives the contractor funding for the performance of works and supply of
materials during construction.
▪ As an alternative to the interim payment, a lump sum contract may provide for milestone
payment. The employer will make periodic payments to the contactor by reference to certain
stages of the work or stated intervals. In other words, the milestone payment approach makes
interim payments subject to achievement of predetermined progress milestones.
DELAY
Is it possible for the parties to a construction contract to agree that the time/date for completion of the
works is to be fixed? How would delay be dealt with?
Date for completion
▪ Most construction contracts provide a date or stipulate a period for the contractor(s) to complete the
works. The failure to achieve completion by the date or within the stipulated period is a breach of
contract.
Ways to deal with delay
EXTENSION OF TIME
▪ Clauses for extension of time for completion can be inserted into the contract. Most construction contracts set out a
mechanism for the architect to award extensions of time. Under the Agreement and Schedule of Conditions of Building
Contract for Use in Hong Kong – Standard Form of Building Contract (Private Edition) (HKIS), it is for the
contractor(s) to first give notice of delay, and then for the architect to assess, in his opinion whether there was any
actual delay caused by the events as specified. These events include, inter alia, inclement weather, variations, and late
receipt of instructions or drawings.
There are many causes for variations in construction projects. Below are some of the reasons for variations.
However for specific projects, you should refer the contract document to find specific terms and clauses
that are relevant to your project.
▪ Variations can be due to,
• Addition or omission from the scope of works
• Changes to the quantity of work in the form of increase or decrease
• Change of dimension, level or position of the works that affect the construction cost.
• Changes to the construction quality including material quality changes.
• Removal of part of the scope or demolition of part of the work scope by the Employer which affects the
total scope of work.
Due to changes in the schedule of completion. That is, if there is a necessity arises to complete the work or
part of the work earlier than the agreed Time for Completion, then it affects the work completion. As a
result, variations to the contract may occur.
Simply, variation to the contract means any changes to the original scope of work which can be in the form
of addition or omission and such changes can create impact on project cost and completion time.
WHAT IS A VARIATION ORDER?
▪ Below are the most common practices in valuation of variations. However, it is necessary to refer your
contract agreement and related variation clauses for exact details. Contractual provisions are different in
different countries. It also can be different according to your contract agreement. Therefore below is a
guideline only to understand how valuation is done.
▪ Usually Valuation of Variations is carried out as below.
• If the variation work is an omission, then the rate or amount mentioned in the contract is used to evaluate the omitted amount.
• If the variation work is an addition, below are the methods for valuation of variation.
• If the variation of work is due to the changes in quantity of similar work which is under the contract scope, then the same rate in
contract is used for valuing of the variation.
• If there is a similar work to the variation work is in the contract scope, however the variation work is carried out in different
conditions then the rates in the contract for similar character work is considered as a basis of valuation.
• However there should have fair allowances added to the different conditions which the variation work occurred.
• If any of the above situations are not met, then it is necessary to check market rates. It is necessary to obtain at least 3 quotations
to establish the fair market rate for the variation work. In this situation, contractor needs to submit quotations from few different
suppliers and contractors to the consultants to evaluate. He needs to submit his quotations together with his variation claim.
• If the parties to the contract cannot come into a decision of fair valuation using any of the above methods, then it is necessary to
evaluate actual material, machinery and labour costs needed to carry out the work.
• For such evaluation, it is necessary to use all the necessary site records including labour hours and machinery hours used for the
work. After the valuation is done using resources used at site, it is necessary to add a reasonable overhead and profit percentage
in order to compensate the contractor for his time on supervision.
SUBMISSION OF VARIATION CLAIM
▪ When there is a variation to the works and once it is instructed in writing, the contractor needs
to carry out the work as per instructions.
After the work is completed, he needs to submit his variation claim at the time when he
submits the progress claim. Together with his claim, it is necessary to submit the necessary
documents and details to support his claim.
▪ There may have situations which contractor receives instructions to carry out the work under
daywork. In such times, contractor should inform the Contract administrator, superintendent
officer or the respective clients representative of the time the work being carried out.
▪ It is necessary for the contractor to keep signed day work records in order to submit with his
claim.
In general, this is how to conduct valuation of variations. Also it is contractor’s responsibility
to submit his variation claim with all necessary details in order to get the payment certified
within a reasonable time period.
▪ These conditions and method of evaluation of claim can be different depending on your
contract.
HOW TO PERFORM VALUATION OF VARIATIONS