Professional Documents
Culture Documents
L&L - Sandipan - Inlet Facilities LNG Projects
L&L - Sandipan - Inlet Facilities LNG Projects
Content
Introduction
Process Overview
Conclusion
Introduction: Inlet Separation Facilities
HIPPS
Pressure Feed Gas
Letdown Separator
Liquid
Filter To Stabiliser O/H
Slug Compressor
Catcher Liquid
Heater HC Liq to
B/L LNG Condensate
Facilities Stabilisation
Pressure 3 Phase
Letdown Separator Aq. Phase to
MEG Recovery
Feed
Pipeline
Flow Diagram: Condensate Stabilisation
To Feed Gas
From 3 Separator
Phase
Separator
Flash Gas
Compressor
HC Liquid from
Stabiliser
Separator
Column
Reboiler
Stabiliser
Feed Drum To Condensate
Storage Tank
Air Cooler
Slug Catcher: Introduction
Gas Heater
PZ
Feed Gas
ESD Letdown
Separator
valve Station
HIPPS
Slug Catcher
B/L LNG
Facilities
Feed Pipeline
Overpressure Protection: HIPPS
FEED Configuration
Two 100% PCVs (one working + one standby) for letting down
pressure
ESD valves will close and shut down flow in case of high
pressure downstream of the letdown station (2 out of 3 voting)
Pressure letdown: FEED Configuration
FEED Configuration
1500# 600#
2oo3
PC
PCV-B
PZ
FC
750mm
UZV -1 UZV -2
PCV-A
FC
Inlet Pressure Control
Size of the PCV at the required Design Pressure rating was outside
the experience range of the supplier
This failure mode would also result in the capacity of the wet gas
flare being exceeded, unless multiple, parallel PCV runs were
installed each sized to limit the flow to within the flare capacity.
Parallel PCV runs would also reduce the PCV size to that which is in
proven service
Alternative Solutions
Base Case:
1500# 600#
UZV-1A UZV-2A 2oo3
PCV-B PC
FC PZ
UZV-1B UZV-2B
PCV-A
FC
UZV-1C UZV-2C
HIPPS
Other alternatives considered
Atmospheric Vent
Accepted Solution:
Increase Wet Gas Flare Capacity for relief from Feed Gas
Separator relief valve on block discharge (e.g. Fail Closure of
outlet ESD valve
Each PCV to be sized such that flow through one PCV will
match the increased Wet Gas Flare capacity.
This would also reduce the size of the PCVs to a size which is
in proven service
Inlet Pressure Control: PCV sizing
The pressure upstream of the control valve is set by the HIPPS trip
set point. Pressure downstream of the control valve is the PSV set
pressure + accumulation + line losses.
The total available pressure drop can be adjusted between the line
losses and control valve pressure drop. Thus the number of PCV
runs can be optimised
Inlet Pressure Control: No. of PCV runs
Vendor feedback was also taken for determining the cost of the
options and working out the optimised solution
Min DT (based on Depressurisation)
The initial amount of cold gas has a very small mass compared to the
slug catcher metal mass and cannot significantly lower the metal
temperature. There could be localised cold spots like inlet piping and
nozzles, but this is allowed by the code
If the minimum temperature that the piping can see is lower than the
Minimum Design Temperature, this would be indicated in the Line
List as Flex Low temperature at coincident lower pressure
Reduction in Min Design Metal Temp
(Graph from ASME B31.3)
Case Study: Exchanger tube rupture
protection
Gas and Liquid Heaters are Shell & Tube exchangers. High
differential pressure between shell and tube sides
During FEED stage, the design pressure of the shell side was
46 barg
This was the accepted solution. During the EPC phase, the
shell side design pressure was increased to 10/13th of the tube
side design pressure (123.1barg).
Case Study: Exchanger tube rupture
protection
THANK YOU