Professional Documents
Culture Documents
Unit 5 Planning & Schedule
Unit 5 Planning & Schedule
Unit 5
PROJECT PLANNING AND SCHEDULING
TIME = MONEY
: SCHEDULE
A time phased plan for a function
: Forms of Schedule
Written Schedule .1
Network Schedule .3
a. Critical Path Method (CPM) Networks
Merits
Demerits
: Network Techniques
Concreting Plastering
5 2
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Definition of terms
1. Project :
It denotes the entire structure
2. Activity :
It is an identifiable job which consumes time money and resources in
doing that job.
: Event .3
It is the beginning or end of an activity which does not consume time,
money and resources
: Predecessor Event .4
An event which occurs immediately before another event
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Definition of terms
: Successor Event .5
.An event which follows immediately after another event
6. Predecessor activity :
An activity which occurs immediately before another event
7. Successor Activity :
An activity that follows immediately after another event
: Dummy activity .8
An imaginary activity which does not require time money and resources.
.It is introduced to maintain network logic
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Definition of terms
: Current activity .9
.Activity under consideration
:Source .11
It is the starting or initial event of a project. It has only emerging
.activities and no entering activities
: Sink .12
It is the last or end event of a project. It has only entering activities and
.no emerging activities
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Example : Suppose in a project there are three activities
Numbering of events :
1. The number at the head is always greater that at the tail
Example 5.2
The activities and their predecessor relationships of a project are
denoted by their node numbers as below. Draw the network
Activity
Symbol A B C D E F G H K
Activity
Identificatio 1-2 1-3 2-4 2-5 3-6 4-7 5-7 6-8 7-8
n
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
C F
2 4 7
A
D
K
G
1
B 5
8
3 H
E
6
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Example 5.3
A project consists of the following activities. The precedence relationship
between the activities are as below.
Draw the network for this project and number the events
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
AOA
C F H
2 5 6 7
A
D
G
1
B 4
E
3
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
AON
C
F
A
D H
G
A and B are the initial activities
C and D follow A
B E B precedes E
F follows C
D and E precede G
H follows G and F
H is the last activity
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
:Forms of Schedule
Project planning steps:
5. Latest Start Time (LST) : Latest possible time at which an activity can
be started ( = L F T - Duration )
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
ES EF
activity
LS D LF
0 5 5 8
A B
0 5 5 5 3 8
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Activity Symbol A B C D E F G H J K
Predecessor Activity
Nil Nil Nil Nil A D E,B,C C C J,F
Duration (Days)
4 3 5 2 3 4 2 6 4 6
0 4 4 7 7 9
A E G
6 4 10 10 3 13 13 2 15
0 3 5 11
B H
10 3 13 9 6 15
0 5 5 9 9 15
C J
0 5 5 K
5 4 9 9 6 15
0 2
D 2 6
3 2 5
F
5 4 9
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Float
Float is the difference between the time available for
the performance of the activity and the actual
activity time.
Three types of Float
1. Total Float
2. Free Float
3. Independent Float
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
1. Total Float
2. Free Float
3. Independent Float
Critical Path
0 4 4 7 7 9
A E G
6 4 10 10 3 13 13 2 15
0 3 5 11
B H
10 3 13 9 6 15
0 5 5 9 9 15
C J
0 5 5 K
5 4 9 9 6 15
0 2
D 2 6
3 2 5
F
5 4 9
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
ES EF
activity
LS D LF
0 5 5 8
A B
0 5 5 5 3 8
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Event Time estimates
Early Event Time (EET) : The earliest time at which each event may .1
occur
2. Late Event Time (LET) : The latest possible time at which each
event may occur without changing the
project duration
Activity
EET EET
ES EF
1 2
LS LF
LET LET
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Example 5.4
Draw network for the following activities. Calculate EET and LET for
all the events
Activity
Symbol A B C D E F G H J K
Predecessor E,B
Nil Nil Nil Nil A D C C J,F
Activity ,C
Duration
4 3 5 2 3 4 2 6 4 6
(Days)
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Event Time estimates
4 7
E
2 3 5
G
A 2
4 B
0 3 15
1 C
5 H 7
5 3 6
J K
D 6
4 9
2
2
F 6
4 4
If there are more than one activity meeting at an event, the largest value of possible
early event time is chosen
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Event Time estimates
7
4
E
2 3 5
13
10 G
A 2
4 B
0 3 15
1 C
5 H 7
0
5 3 6 15
5
J K
D 6
4 9
2
2
F 6
4 4
9
5
If there are more than one activity meeting at an event, the smallest value of possible late
event time is chosen
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Calculate E S T of all the activities for Example 5.4
7
4 E
4
2 5
G
B 3 13 7
A 10
0
0 2
0 15
4 3
H
1 0
C 5 5 7
0
3 J 6
15
5 K
D 5 5
0 9
4 9 6
2 F
2
2 6
4 9
4
5
EST
EST of
of Activity B
GA
D
K
C
JH
Activity F
E = EE TE of
E T of
Event 1=
Event
2 54
63
4 0
= =27
95
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Calculate E F T of all the activities for Example 5.4
4 7
E
4 7
2 5
G
B 3 13 7
A 10 9
4 3
0 0
2
0 15
4 3
H
1 0
C 5 5 11 7
5
0
3 J 6
15
5 K
D 5 5 9 15
0 9
2
4 9 6
2 F
2
2 6 6
4 9
4
5
EE FF TT of
of Activity FK
E
C
B
D
Activity H
AG
J E S T of Activity H
F
E
C
B
D
G +
JK +
A Duration
+ Duration of
of JFE
Duration of C
B
D=
H
G
A
K =
=5240
= 0+
95
7 +
+4434
+ 5
66
2==
=9673
= 5
2======
11
9
4
15
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Calculate L F T of all the activities for Example 5.4
4 7
E
4 7
2 13
5
G
B 3 13 7
A 10 9
4 3 15
0 10 0
13 2
15
0
4 3
H
1 0
C 5 5 11 7
5
15
0 5 3 J 6
15
5 K
D 5 5 9 15
0
15
2 9 9
5 4 9 6
2 F
2
2 6 6
4 9
9
4
5
LLLFFFTTTLof
FActivity
ofof GKH
TActivity J E
of Activity A
F =
B
C
D LELLEE
LL= EE TT of
of event
event32547=
6 =
7= 15
=913===9
Activity L= L=ET
LTETETof
of
T
LofE
T Tevent
event
of event
of
event
ofof event
event
event 5=
=
7 =10
13
5
5=6
= 15
=
15
=
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Calculate L S T of all the activities for Example 5.4
4 7
E
4 7
2 10 13
5
G
B 3 13 7
A
4 10 3 13 9
0 0 15
0 10 10 1
3 2
15
6 3
4
H
1 0
C 5 5 11 7
5
0 3 9 15 15
0 5 J 6
5 K
D 5 5 9 15
0 5
15
3 2 9 9
4 9 6
9
5
2 F
2
2 6 6
4 5 9
9
4
5
L S T of Activity A
of Activity E
B
F
G
KH === L F T
JD
C of Activity A
T of E
B
F
G
KH --- Duration
JD
C Duration of
Duration of Activity
ActivityA
ofActivity E
JF
C
B
H
D
G
K
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Example 5.5
The duration for the various activities of the network are shown
below. Draw the network and tabulate EST, EFT, LFT, LST, Total
Float, Free Float for all the activities
Activity
Symbol A B C D E F G H J K L
Predecessor
Nil Nil B B A,C A,C A,C D,F E D,F H,G,J
Activity
Duration
9 11 4 7 16 18 3 1 3 2 5
(Weeks)
Time-Grid Diagrams
A B C
0 1 2 3 4 5 6
5 7 8 9 10 11
4/11/2020
Wed
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
0 4 4 7 7 9
A E G
6 4 10 10 3 13 13 2 15
0 3 5 11
B H
10 3 13 9 6 15
0 5 5 9 9 15
C J
0 5 5 K
5 4 9 9 6 15
0 2
D 2 6
3 2 5
F
5 4 9
A E G
FF
B
H
C J K
FF
D F
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
15
11/2020
16 17 18 19 21 22 23 24 25 26 28 29 30 1 2
Sun
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Resource Planning
Resource : A resource is a physical variable such as man power,
materials, and equipments that is required to
complete various activities of the project.
1. Resource Smoothing.
2. Resource leveling
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Resource Planning
1. Resource Smoothing.
2. Resource Leveling.
Exercise 5.9 :
The network of a project is shown below. The requirement of the masons of each
activity is shown in the table. Level out the requirement of resources, if the
maximum number of masons on any day has to be limited to 7
2 G
A 5
2
B D F
1 6 3 4
5 5 6
C E
4 4
Activity A B C D E F G
Requirement of
4 3 4 3 4 3 4
Mason
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Resource Planning
Exercise 5.9 :
Activ- Dura-
EST EFT LFT LST TF
ity tion
A 2 0 2 10 8 8
B 6 0 6 6 0 0
C 4 0 4 10 6
6
D 4 6 10 10 6
0
E 4 4 8 15 11
7
F 5 10 15 15 10
0
G 5 2 7 15 10
8
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Resource Planning
Exercise 5.9 :
Days
Activ-
ity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
4 4
A
3 3 3 3 3 3
B
4 4 4 4
C
3 3 3 3
D
E 4 4 4 4
F 3 3 3 3 3
G 4 4 4 4 4
Total
11 11 11 11 11 11 11 7 3 3 3 3 3 3 3
There is maximum demand of labors for the first 7 days and minimum
demand after that. So for leveling the resources, we can delay some
activities having sufficient float.
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
Resource Planning
Exercise 5.9 :
Days
Activ-
ity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
4 4 4 4
A
3 3 3 3 3 3
B
C 4 4 4 4
D 3 3 3 3
E 4 4 4 4
F
3 3 3 3 3
G
4 4 4 4 4 4 4 4 4 4
Total
11 11 11 11 11 11 11 7 3 3 3 3 3 3 3
Total 7 7 11 11 11 11 11 7 7 7 3 3 3 3 3
Total 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Activity
Activity
By this Gadjustment,
A is
is having
having aathe
float
float
demand
of
of 88 days.
days.
on masons
So
So delay
delay
become
itit by
by 88 days
days
7
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
PER ( Program Evaluation and Review Techniques )
T
PERT is a tool used in management for planning, controlling and
reviewing the progress of a project
TIME ESTIMATES
Taking all uncertainties into account there are three time estimates
Expected time :
PERT is calculated using a Weighted Average. It is based
on Beta Distribution. The Mean can be determined by the
following formula.
𝑡 𝑝 +𝑡 𝑜+(4 × 𝑡 𝐿 )
𝑚𝑒𝑎𝑛 ( 𝑃𝐸𝑅𝑇 ) =
6
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
PERT
In actual execution of a project, the expected time of an activity is
likely to vary due to various uncertainties.
40
10 20 50 60
30
CONSTRUCTION MANAGEMENT
Unit 5
PROJECT PLANNING AND SCHEDULING
PERT
Time Estimates
Activity S V
t0 tL tp tE
10 - 20 2 5 14 6 2 4
10 – 30 3 12 21 12 3 9
10 – 40 2 5 8
5 1 1
20 – 40 5 14 17
13 2 4
20 – 50 6 15 30
16 4 16
30 – 50 1 4 7
6 1 1
30 – 60 3 6 21
40 – 60 3 6 9 8 3 9
50 – 60 5 8 17 6 1 1
9 2 4
𝑡 +𝑡 +(4 × 𝑡 𝐿 )
t p to
𝑚𝑒𝑎𝑛 ( 𝑃𝐸𝑅𝑇 ) = 𝑝 𝑜 s
6 6