National Power Grid Company TRANSELECTRICA S.A. - Romania: Refitting Strategy For Romanian Power System Substations
National Power Grid Company TRANSELECTRICA S.A. - Romania: Refitting Strategy For Romanian Power System Substations
• Mission:
Mission
– granting third party regulated access to Transmission
Power Grid
– safe and cost-effective operation within an
encreasing competitive market economy
• Target:
- hub of electricity transmission in S-E Europe
- interconnection to UCTE of Romanian Power System
- transboundary electricity connections on the regional
market
MARCIU_RO_author_Alpha5_Block1.ppt 2
Barcelona 12-15 May 2003
Codification
Electrical Substation
Transmission subsidiaries
ERBIA
MARCIU_RO_author_Alpha5_Block1.ppt 3
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 4
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 5
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 6
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 7
Barcelona 12-15 May 2003
GATHERED EXPERIENCE
with refitting/extending the electrical substations Portile de Fier, Tantareni,
Urechesti, Arad, Mintia
• ‘turn-key project’
• harmonising the Romanian norms and standards to the
suppliers’
• legislation and equipment solutions
• unity of technical solutions of a project
• simplifying of the substation one-line diagram
• finding and applying proper financing schemes
MARCIU_RO_author_Alpha5_Block1.ppt 8
Barcelona 12-15 May 2003
GATHERED EXPERIENCE
with refitting/extending the electrical substations Portile de Fier,
Tantareni, Urechesti, Arad, Mintia
MARCIU_RO_author_Alpha5_Block1.ppt 9
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 10
Codification
Barcelona 12-15 May 2003
-Refitted/extended substation
-Substations in different stage
of refitting/extending
- Substations to be refitted
MAP II after 2005
-Substations being refitted on
C&P (investments) completed
with advanced maintenance
works (including replacement o
primary equipments)
-Substations forseen to be
refitted by advanced
maintenance works completed
with investment works
-Substations with advanced
maintenance works underway
ERBIA
MARCIU_RO_author_Alpha5_Block1.ppt 11
Romania – Transelectrica S.A.
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 12
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 13
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 14
Barcelona 12-15 May 2003
MARCIU_RO_author_Alpha5_Block1.ppt 15
Barcelona 12-15 May 2003
CONCLUSIONS
The realistic approach to the refitting projects of the substations in the ETG
is based on a stable and modern strategy that:
• is conceptually structured in technical terms by means of advanced
equipping solutions and the control of the electrical technological
process at current world level
• is based on multi-criteria methods determining the sequence of
refitting projects start up
• uses the global solution of “turnkey project”
• provides an efficient project management carried on by the Project
managers
• monitors the project development at different competence levels
using a specialized software
• uses experience gained by already refitted substations in Romania
MARCIU_RO_author_Alpha5_Block1.ppt 16