Professional Documents
Culture Documents
Project MGT CH 1
Project MGT CH 1
Project MGT CH 1
Course content/focus
1. Project Management Concepts
2. Project plan
3. Resource Scheduling
4. Project Quality Management
5. Project performance Measurement and
Control
1. Overview of Project
Management
Introduction
Uniqueness
Projects involve doing something that has not been done
before.
Uniqueness-cont’d
The objectives of projects and operations
are fundamentally different
The purpose of a project is to attain the objective and close
the project
Project ceases when it declared objectives have been attained
A temporary nature
The duration of a project is finite; they are not ongoing
efforts
Temporary does not necessarily mean short in duration;
many projects last for several years
Temporary does not generally apply to product or service
created by the project
Most projects are undertaken to create a lasting result.
Ex: Grand Renaissance dam will create a result expected
to last centuries.
Characteristics of project-Cont’d
Progressive elaboration
Due to the uniqueness of project results, the precise details
in terms of the deliverables contributing to the results are
not known from the outset.
Progressive elaboration-Cont’d
The following example illustrates progressive elaboration:
The product of an economic development project may
initially be defined as:
i. ‘Improve the quality of life of the lowest income residents of
community X’
ii. As the project proceeds, the products may be described more
specifically as, for example: ‘ provide access to food and water
to 500 low income residents in community X’
iii. The next round of progressive elaboration might focus
exclusively on increasing agriculture production and
marketing, with provision of water deemed to be secondary
priority to be initiated once the agriculture component is well
under way.
1.3. Classification of project
With examples:
1. Aerospace/Defense Projects
1.1 .Space Satellite development/launch
1.2. Military operations Task force invasion
3. Event Projects
3.1 International events 2018 World Cup Match
3.2 National events
Classification of project-Cont’d
With examples:
With examples:
Government
programmes Priorities and
programmes of
non-state actors
Irrigation
is the discipline of
Planning;
Organizing;
Securing; and
Managing resources to achieve project goals.
What is Project Management?
Proposal
Appraisal development
4. Implementation
Financing
decision
3. Project
planning
Identification Potential projects emerge from specialists, local leaders and national development strategies.
Identification of potential stakeholders, particularly primary stakeholders.
Carry out problem assessment and decide upon key objectives.
Assess alternative strategies for meeting objective.
Preparation The technical, institutional, economic, environmental, and financial issues facing the
project studied and addressed —including whether there are alternative methods for
and Appraisal
achieving the same objectives.
Assessing feasibility as to whether and determining whether to carry out more advanced
planning.
Evaluation of all of the feasibility studies to determine the ability of the project to succeed
Evaluation On-going and final assessment of the success of the project against
& closure original objectives, to learn lessons to help improve future projects.
Roles and Responsibilities in Project
1. The Sponsor is the owner of the Project or any party who
provides funds to the project.
Define Project
g State need, problem or opportunity
Launch Plan
g Assign work
PM Process Summary
COSTS,
AND
RESOURCES
Project Planning and Scheduling
Work-breakdown
structure
Gantt chart
Network Techniques
Work breakdown structure (WBS)
A work breakdown structure describes the
components and subcomponents of the
project’s various work products as a “family tree.”
It represents a systematic and logical breakdown of the project
into its component parts.
A Hotel Building
project
Ac tiv ities
Tim e in week s f rom project s t art
10 20 30 40
Desig n
Pur chase of
par ts
Fabr ication
Assembl y
Example
1. 0 2. 0
Q uest io n na ire R epo rt
[A ] [D]
• Print
• Identify Target Consumers •Input Response Data
Questionnaire
Develop
• Develop Draft Software • Analyze Results
• Prepare
Questionnaire Mailing Labels • Prepare Report
• Mail
• Pilot-Test Questionnaire
Questionnaire
• Finalize Questionnaire
& Get
Responses
A Gantt Chart for a consumer market study
Activity Person 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
Responsible
Identify Target A
Consumers
Develop Draft A
Questionnaire
Pilot-Test A
Questionnaire
Finalize A
Questionnaire
Print B
Questionnaire
Prepare Mailing B
Labels
Mail B
Questionnaire
& Get
Responses
Develop Data C
Analysis
Software
Input Response D
Data
Analyze Results D
Prepare Report D
Load car.
Pack suitcases.
Purchase supplies.
Network diagrams provide a graphical view of the tasks and how they relate
to one another.
The network is developed from the information collected for the WBS
Network Techniques
In this technique, the
activities,
events, and
their relationships
Activity-on-Node (AON)
This is the form of Network diagrams most commonly
used
An activity is represented by a node , [a
rectangular box/ a circular].
The activities are connected by arrows between these boxes.
The arrows represent the dependencies between
the different activities and the specific sequence in
which the estimated tasks must be accomplished.
Task A is the predecessor activity for task B and activity A and B are
the predecessor tasks for activity C
activities Y and Z have to wait until the task X is ready. In this case
activity Y and activity Z can be done in parallel (to save time).
The activity X is called burst activity because more than one arrow
bursts from its node.
Activity On Node Network Techniques
Task A Task K
Task B Task L
Errors in Logic
Errors in Logic
Dummy activity: an activity that
does not consume time or resources.
To answer:
What is the total time to complete the project?
What are the scheduled start and finish dates for each
specific activity?
TASK A TASK B
AON Diagrams
Any activity may:
Be performed concurrently – Task C can be
performed at the same time as Task D
TASK C
TASK D TASK E
AON Diagrams –Rules
Direction
Arrows should always go forward
The flow of work is from left to right
TASK C
TASK C
TASK C
TASK C
TASK C TASK F
TASK D TASK F
TASK D TASK E
TASK E
AON Diagrams –Rules
If overlapping can not be avoided use bridges
TASK C
TASK D TASK E
TASK D
AON Diagrams –Rules
There should be one starting node (Start
Project) and one finishing node (Project
Complete)
TASK C TASK D
TASK D TASK E
AON Diagrams –Rules
Using the WBS, identify the order that tasks must be done
task order
Example: Building a House (Dependency Graph)
Install Install Install
Interior Interior Wallboard
The activity Plumbing Electrical
„Lay foundation“
Install
Interior
Install Doors
Flooring
Lay Build
START Survey Excava Buy FINISH
Founda Outside
ing tion Material
tion Wall Install
Roofing
Install
Exterior
Doors
Request
Paint
Exterior
Key questions:
what is the expected duration of the project?
What are the earliest start and finish dates for each activity?
What are the latest start and finish dates for each activity that
does not interfere with the project completion time?
· Critical Path –
– The series of activities all of which must
finish on time for the whole project to finish
on time
– Sometimes described as the longest path
through a network, hence the shortest
project time
Computing Critical Path
· Calculate the Forward Pass by adding the
durations along each path in your network:
to establish the earliest start (ES) and finish (EF) dates
for each activity
What are the scheduled start and finish dates for each specific
activity?
Which activities are critical and must be completed exactly as
scheduled to keep the project on schedule?
How long can noncritical activities be delayed before they cause
an increase in the project completion time?
Example 1: AON Network Diagrams: Installation of
air-pollution control equipment @ M Company
Consider the following table of activities; immediate
predecessor(s) (I.P.); and duration (week) for each activity
Immediate Duration
Activity Description Predecessor (week)
A build internal components ___
2
B modify roof and floor ___
3
C construct collection stack A2
D pour concrete and install frame B4
E build hi-temp burner 4
C
F install control system 3
C
G install air-pollution control device D,E
5
H inspect and test F,G
2
Find the project completion time
Feedback
1. Forward pass
EF = ES + duration
ES= EF- Duration
2. Backward pass
LS= LF – duration
LF = LS +duration
18
Feedback
• E(arly) S(tarts)/ F(inishes) and L(ate) S(tarts)/F(inishes) for the project.
4 F 7
0 A 2 2 C 4 EF
10 3 13
0 2 2 2 2 4
ES
13 H 15
4 E 8
B 13 2 15
0 3 3 D 7 4 4 8
1 LS
3 4 4 4 8
LF
8 G 13
critical path 8 5 13
AON-Example 2: simplified activities that have to be done to install a new
suspension bridge.
Activity Description Preceding Duration (in
activity days)
I. Activity times are subtracted along each path starting with the
project end activity (LF – Dur = LS)
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Feedback
Calculate the Path Completion
Times
Paths Path duration
ABDEGHJK 40
ABDEGIJK 41
ACFGHJK 22
ACFGIJK 23
The longest path (ABDEGIJK) limits the project’s
duration (project cannot finish in less time than its
longest path)
ABDEGIJK is the project’s critical path
The advantages of network
technique:
It can effectively handle inter relationships
among project activities
It identify the activities which are critical to the
completion of the project on time ad indicate
the float (spare time ) for other activities
It can handle very large and complex projects
and
It can be easily computerized and updated
Drawbacks of network technique
Being more complicated than the
traditional bar chart it is not easily
understood by the project
personnel, and
It does not define an operational
schedule which tells who does what
and when.