DOUBLE FLOW IP IN 660MW
– The decision for single or double-flow is primarily made on blading design and efficiency.
– Double-flow casing for IP turbine has the advantage of eliminating the rotor gland at the high pressure end.
– The Axial force balanced by two identical Turbine flows with opposite orientation on common axle (no thrust balance piston)can auto balance
the rotor.
– The high pressure Gland steam entering the Rotor for sealing can be avoided and the same quantity of Steam can be converted to work.
– For 660MW and above the following companies use double flow IP turbine configuration.
1.Siemens.
2.Doosan Skoda Power.
3.G.E Power.
4.Toshiba Power.
LSB SIZE OF OTHER OEM IN RECENT PROJECTS
SKODA Power TOSHIBA Power GE Hitachi
TO HP HEATER 7
TO DEAERATOR
• For every 1Mpa(10 bar) improvement in main steam Pressure the Turbine heat rate could be
reduced by 0.13%-0.15%.
• For every 10% improvement of Main Steam Temperature Turbine Heat rate could be reduced
by 0.25%-0.30%.
• For every 10% improvement of Reheat Steam Temperature, Turbine Heat rate could be
reduced by 0.15% -0.20%.