Professional Documents
Culture Documents
Capital Budgeting: Value (Brigham and Ehrhardt, 2005)
Capital Budgeting: Value (Brigham and Ehrhardt, 2005)
Payback = 3 + 0.33
= 3.33 years
Payback Period
• One major drawback of the payback period
criterion is that it ignores the time value of
money and does not discount these free cash
flows back to the present.
Discounted Payback
• The discounted payback approach is a
variation of the original payback period
approach. It is similar to the regular payback
period except that the expected cash flow are
discounted by the project’s cost of capital.
• This method is defined as the number of years
needed to recover the initial cash outlay from
the discounted free cash flows.
Discounted Payback
• The accept-reject criterion then becomes
whether the projects discounted payback
period is less than or equal to the firm’s
maximum desired discounted payback period.
• Assuming that the required rate of return on
project’s A and B is 17% the discounted free
cash flows would be as shown in the tables
below.
Project A
• To solve for IRR is not as easy as our calculation with the NPV criterion.
• To find IRR we use the above equation to solve for the discount rate that causes
the equation and the NPV to be equal to zero. We solve using trial and error .
Internal Rate of return (IRR)
• After trying some discount rates we eventually
find the answer to be 14.5%. This is the
discount rate that causes the NPV to be equal
to zero and is represented by IRR in the
formula.
Internal Rate of return (IRR)
• The logic behind IRR is that it represents the
expected rate of return.
• A surplus is provided when the IRR exceeds the
cost of the funds used to support the project.
This surplus will accrue to the firms
shareholders.
• Therefore accepting a project whose IRR
exceeds the cost of capital increases
shareholder wealth.
Profitability Index (PI)
• Also called the benefit or cost ratio.
• Refers to the ratio of present value of the
future free cash flows to the initial outlay
• That is, the ratio of the present value of the
future benefits to its initial cost.
Profitability Index (PI)
n
PI = ∑ FCFt
t=1 (1 +k)t
IO
Profitability Index (PI)
• Where,
FCF – the annual free cash flow in time period t
(this can take on either a positive or
negative values)
k - the appropriate discount rate; that is, the
required rate of return or cost of capital.
IO – the initial cash outlay
n – the projects expected life.
Profitability Index (PI)
• The decision criterion is this; Accept the
project if the PI is greater than or equal to
1.00, and reject the project if the PI is less
than 1.00.
• PI ≥ 1.00 ; Accept
• PI ≤ 1.00 ; Reject
Profitability Index (PI)
• The Profitability index criterion yields the same accept-reject
decision as the NPV criterion.
• Whenever the PV of the projects net cash flow is greater than
its initial cash outlay the project’s NPV will be positively
signaling a decision to accept. When this happens, the
projects profitability will be greater than 1.
• Thus these two decision criteria will always yield the same
accept-reject decision.
• Note however, that they will not necessarily rank acceptable
projects in the same order.
• END