Pemboran Air Tanah Salatiga

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 2

PROGRESS

June July August September


No Well Name W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15
Plan
1 Well-01 Local People
2 Well SCI-01 SCI Factory
3 Well SCI-02 SCI Factory

Progress (actual)
Duration
Problem Solution Start End
(day)
Well-01 12 June 19-Sep 99
Slow progress due to water loss-
Drilling 0 - 80 m depth, 6 inch clay material was used
porous rock, non tech : Idul Fitri 12 June 19 August 68
well to inhibit water loss
Holiday, Payment delay
Well construction, 4 inch pipe 20 August 21 August 2
1 After 2 minutes pumping, water
Pumping Test
discharge stop
Continue Drilling, 3 inch well,
08-Sep 17-Sep 10
from 80 to 120 m
Pumping Test, water level 78
m, pump 0,75 PK, 100 m 19-Sep 1
depth, 2,5 m3/hour
Well SCI-01 10-Sep
Drilling 0 - 45 m depth, 6 inch
2
well, then enlarged with 8 inch 10-Sep 9
bit
WELL PROFILE

You might also like