Assignment Submission

Name: Moataz A.Azzam

ESS ID: 700203416

AUC Course name: Quality Dimension in Project Management

AUC Course ID: PCQM 050


Project Schedule Network Diagram
0 4 4 12
Activity D Activity E
1 4 5 5 8 13 13 18 18 25 25 33

0 0 Activity G Activity H Activity C


Start 13 5 18 18 7 25 25 8 33
0 0 0 6 13 33 33
Activity F End
0 6
6 7 13 33 0 33
Activity A
13 18
0 6 6
Activity B
28 5 33

Critical Path: Start->A->F->G->H->C->End


Critical Path Duration:33
Float of Activity B: 28-13=15

Float of Activity E: 5-4=1

Float of Activity D: 1-0=1

Removing Activity E causes a change in Activity D’s float=2

0 4
Activity D
2 4 6 13 18 18 25 25 33
0 0 Activity G Activity H Activity C
Start 13 5 18 18 7 25 25 8 33
0 0 0 6 13 33 33
Activity F End
0 6
6 7 13 33 0 33
Activity A
13 18
0 6 6
Activity B
28 5 33