Professional Documents
Culture Documents
Capital Budgeting Techniques: All Rights Reserved
Capital Budgeting Techniques: All Rights Reserved
Capital Budgeting Techniques: All Rights Reserved
Capital
Budgeting
Techniques
10-2
What is capital budgeting?
Analysis of potential additions to fixed assets.
Long-term decisions; involve large
expenditures.
Very important to firm’s future.
Categories of Capital Budgeting:
Replacements needed to continue current operations.
For damaged assets.
Replacement for cost reduction due to obsolete assets.
Expansion of existing products or markets.
Expansion into new products and markets.
10-3
What is the difference between
independent and mutually exclusive
projects?
Independent projects – if the cash flows
of one are unaffected by the acceptance of
the other.
Mutually exclusive projects – if the
cash flows of one are adversely impacted
by the acceptance of the other.
10-4
What is the difference between normal
and nonnormal cash flow streams?
Normal cash flow stream – Cost (negative
CF) followed by a series of positive cash
inflows. One change of signs.
Nonnormal cash flow stream – Two or
more changes of signs. Most common:
Cost (negative CF), then string of positive
CFs, then cost to close project.
10-5
Criteria to evaluate Capital
Budgeting Projects
Five methods are used to evaluate projects:
(1) Payback
(2) Discounted payback
(3) Net Present Value (NPV)
(4) Internal Rate of Return (IRR)
(5) Modified Internal Rate of Return (MIRR)
10-6
What is the payback
period?
The number of years required to recover a
project’s cost by its net revenue, or “How
long does it take to get our money back?”
Calculated by adding project’s cash inflows to
its cost until the cumulative cash flow for the
project turns positive.
10-7
Calculating payback (when
uneven CF)
0 1 2 2.4 3
Project L
CFt -100 10 60 100 80
Cumulative -100 -90 -30 0 50
PaybackL == 2 + 30 / 80 = 2.375 years
0 1 1.6 2 3
Project S
CFt -100 70 100 50 20
Cumulative -100 -30 0 20 40
10-9
Payback Period Decision criteria:
The payback method is the amount of time required
for a firm to recover its initial investment in a project,
as calculated from cash inflows.
Decision criteria:
The length of the maximum acceptable payback
0 10% 1 2 2.7 3
CFt -100 10 60 80
PV of CFt -100 10/(1+.10)^1=9.09 49.59 60.11
Cumulative -100 -90.91 -41.32 18.79
Disc PaybackL = 2 + 41.32 / 60.11 = 2.7 years
10-12
Net Present Value (NPV)
Net present value (NPV) is a sophisticated capital
budgeting technique; found by subtracting a project’s
initial investment from the present value of its cash
inflows discounted at a rate equal to the firm’s cost
of capital.
NPV = Present value of cash inflows – Initial
investment
10-13
Net Present Value (NPV)
(cont.)
Decision criteria:
If the NPV is greater than $0, accept the
project.
If the NPV is less than $0, reject the project.
10-15
Project Decision based on NPV
NPV = PV of inflows – Cost
= Net gain in wealth
If projects are independent, accept if the project
NPV > 0.
If projects are mutually exclusive, accept projects
10-16
Internal Rate of Return
(IRR)
A project’s IRR is the discount rate that
forces the PV of cash inflows to equal the
cost (initial outlay).
This is equivalent to forcing the NPV to equal
zero .
The IRR is an estimate of the project’s rate of
return, and it is comparable to the YTM on a
bond.
10-17
Rationale for the IRR method
If IRR > WACC, the project’s rate of
return is greater than its costs.
There is some return left over to
boost stockholders’ returns.
10-18
Project decision based on IRR
Independent projects: If IRR exceeds
the project’s WACC (k) accept the
project and vice versa.
Mutually exclusive projects: Accept the
project with the highest IRR, provided
the IRR is greater than WACC. Reject all
projects if the best IRR does not exceed
WACC.
10-19
IRR Acceptance Criteria
If IRR > k, accept project.
If IRR < k, reject project.
10-21