Professional Documents
Culture Documents
Project Management Lec 09
Project Management Lec 09
Project Management Lec 09
Lect#9
Scheduling
Activity Relationships
Layman’s Definition: Once this task finishes, we can start the next one.
Abbreviation: FS
Finish to Start
Start to Start
PMBOK® Definition: The logical relationship where initiation of the work of the
successor schedule activity depends upon the initiation of the work of the
predecessor schedule activity.
Layman’s Definition: We want these two tasks to start at the same time.
Practical Definition: Once the predecessor task starts, we can start the successor
task.
Abbreviation: SS
Start to Start
Finish to Finish
Layman’s Definition: We want these two tasks to finish at the same time.
Practical Definition: Once the predecessor task finishes, the successor task can
finish.
Abbreviation: FF
Finish to Finish
Start to Finish
Layman’s Definition: This task finishes when the next one starts, but not before
then.
Practical Definition: Once the predecessor task starts, the successor task
finishes.
Abbreviation: SF
Start to Finish
PERT
Program Evaluation and Review Technique
PERT
• Pessimistic time (P): the maximum possible time required to accomplish a task,
assuming everything goes wrong. (Worst case scenario)
• Most likely time (M): the best estimate of the time required to accomplish a
task, assuming everything proceeds as normal.
Activity a m b Predecessors
a 1 4 7 -
b 2 2 2 -
c 2 5 8 a
d 3 4 5 a
e 4 6 8 c,b
f 0 0 6 c,b
g 3 6 9 d,e