Matla OHS Performance

(Week 13)

2021/06/29
Achievements - Projection(as at (29 June 2021)

KPI Actual Tolerance Achievement


Level Dates
0.30 26 Feb 2022
0.66 0.00 05 May 2022
LTIR
TRIR 1.09 0.90 11 Oct 2021

Gx Employee LTI Free Man- 54 Days 100 Days 14 Aug 2021


Days

Gx Permanent Contractors 88 Days 100 Days 31 Jul 2021


LTI Free Man-Days

LTI-Free Man-hours 261,298 1 000 000 29 Nov 2021

2
Matla Health & Safety Performance

12 M Prog. Periods

Health and Safety Performance

Prev Week YTD Current Previous


Eskom 0 1 1 4
Near Miss Contractors - Gx 0 2 2 3
Contractors - Outage 0 5 5 17
Eskom - Gx 0 1 1 0
First Aid
Contractors - Gx 0 4 4 1
Injuries
Contractors - Outage 0 1 1 5
Eskom 0 6 6 8
Medical
Contractors - Gx 0 8 8 3
Injuries
Contractors - Outage 0 2 2 8
Eskom 0 6 6 5
Lost Time
Contractors - Gx 0 2 2 2
Injuries
Contractors - Outage 0 0 0 0 3