Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 7

Re-order based MRP (Consumption based planning)

SD Overview 07/05/2021 Page 1


Objective

• To give overview of business processes mapped for Re-order based MRP


(Consumption based planning)

Page 2
Maintain the master data

• MRP 1 View
1. Maintain the MRP type “VB” Manual reorder point planning

2. Maintain the re-order point (If the stock falls below this quantity, the system
flags the material for requirements planning)

3. Lot sizing Procedure “HB” Replenishment to max stock.(Key that determines


which lot-sizing procedure the system uses within materials planning to
calculate the quantity to be procured or produced.)

4. Maximum Stock Level (Quantity of the material in this plant that may not be
exceeded)

Page 3
Process step for Re-order based MRP (Consumption based planning)

Maintain the master data

MRP 1 View

MRP Type “VB” Maintain the Reorder


Point

Maintain the lot size


Maintain the
maximum stock level

Page 4
Stock level

Stock is below the reorder


point

Page 5
Run the MRP for the Material ‘14000004' Bearing Case
System will create the purchase requisition of 7 quantity to maintain the
maximum stock of 10 quantity.

Purchase requisition created with 7


quantity

Once Purchase requisition is created, convert this PR


into Purchase order. Page 6
Thank You

Page 7

You might also like