Professional Documents
Culture Documents
CERC Draft Regulations 11.02.2019-PMI
CERC Draft Regulations 11.02.2019-PMI
Corporate
Centre
Return on Equity
Provisions 2014-19 2019-24
Return on Equity 15.50% 15.50%
D/E ratio 70:30 70:30
Additional RoE @ 0.5% for timely a r
commissioning of new projects
Modified GFA r a
Stations that have completed their useful
life as on or after 01.04.2019, the
depreciation recovered shall be adjusted
against cumulative repayment and balance
shall be used for reduction of equity.
• Security expenses have been excluded from O&M expenses and shall be
allowed separately as water charges and spares are being allowed presently.
• Additional O&M of 3% of the capital cost for FGD, etc. sought form CERC
Coal stock for working capital maintained at 15 days in pithead stations and reduced to
20 days in non-pithead stations against 30 Days in 2014-19 regulations.
For units commissioned after 2009: For units commissioned after 2009:
• Operating Margin of 4.5% over design • Operating Margin of 5 % over design heat rate.
heat rate
A margin of 85 kcal/kg has been allowed in GCV from ‘as received’ to ‘as fired’
stage in Draft regulation 2019-24 which is not available in 2014-19 Regulations
Copyright © 2016 Your Company All Rights Reserved. 11
Operating Norms – APC, SFC, T&H
Losses 2014-19 2019-24
APC APC
200 MW : 8.5% 200 MW : 8.5%
500 MW % Above : 5.25% 500 MW % Above : 5.75%
Additional APC : Additional APC :
0.5% for IDCT 0.5% for IDCT
0.8% for Tube Type Coal Mills
SFC SFC
0.5 Ml/kwh all stations 0.5 Ml/kwh all stations
Transit & Handling losses: Transit & Handling losses:
• Pit head - 0.2%, • Pit head - 0.2%,
• Non-pithead – 0.8% • Non-pithead –
0.8% (up to 1000 km)
1.2% (Above 1000 km)
Sharing of gains in the ratio of 60:40 Sharing of gains in the ratio of 50:50
Special allowance won’t be available for units of Kahalgaon-1, Talcher-1, NCTPP-1 etc
completing 25 years in next tariff period, now to go for actual R&M expenditure (with
NFA).
In erstwhile Tariff Regulation compensation allowance given for stations/units having expired
life of more than 10 years to meet out capital expenditure in nature of MBOA, minor assets
etc.
On completion of useful life of station, the equity base to Major Negative Impact
be reduced to 5% of capital cost (NFA)
In respect of a thermal generating station that has completed 25 years of operation from COD, the
generating company and the beneficiary may agree on an arrangement where the total cost
inclusive of the fixed cost and the variable cost for the generating station as determined under these
regulations, shall be payable on scheduled generation instead of the pre-existing arrangement of
separate payment of fixed cost based on availability and energy charge based on schedule
The beneficiary will have the first right of refusal and upon its refusal to enter into an arrangement
as above the generating company shall be free to sell the electricity generated from such station in a
manner as it deems fit