Professional Documents
Culture Documents
Lecture 7f
Lecture 7f
Lecture 7f
1
Preliminary Estimates
Needs:
PFD,
vessel sketches,
preliminary plot plan and elevation diagrams
Accuracy is +25% to -15%
Chilton Method
• Delivered equipment cost
• Installed equipment cost
• Process piping (solid, fluid or both)
• Instrumentation
• Buildings and site development
• Auxiliaries
• Outside lines
• Engineering and construction
• Contingencies
• Size factor
Problem: A small fluid processing plant is to be built at an existing
plant site. The delivered equipment costs are:
Equipment COST
Distillation tower 500,000
Trays and internals 435,000
Receivers 320 000
Accumulator drum 175 000
Heat Exchangers 62 0 000
Pumps 215 000
Automatic control 300000
Miscellaneous equipment 150000
Solution:
Since this is a high-cost product due to the raw materials and the
fact that little fixed capital is required, the working capital
should be based on a percentage of annual sales. A mean value
of 35% of sales will be used.