AREA TEAM PRESENTATION

TEAM NO : 07
MONTH : NOVEMBER 2020
AREA / SCOPE OF WORK

TG FLOOR 9MTR
GSC FLOOR 4.5 MTR
DEAERATOR FLOOR
TRANSFARMER ROOF
COOLING TOWER AND DM TANK
CONTROL ROOM
BFP AREA
ACC AREA
ATTENDANCE OF TEAM MEMBERS

S.NO. NAME DEPARTMENT 2/11/2020 9/11/2020 16/11/2020 23/11/2020 30/11/2020


1 RAVINDRA SONGRA WHRS (WCL) P P P

2 RAJESH PADIWAL WHRS (WCL) P P P

3 SACHIN CHUAUBEY WHRS (WCL) P P P

4 ANAND SHUKLA WHRS (WCL) P P P

5 BHERU LAL WHRS (U/E) P P P

6 MAHESH JAIN WHRS (U/E) P P P

7 SHUBHAM MAROO WHRS (U/E) P P P

8 UTTAM WHRS (U/E) P P P


CATEGORY OF OBSERVATIONS- YTD
STATUS
CATEGORY SUB CATEGORY TOTAL (OPEN/CLOSE) REMARK

SCRAP MATERIAL  02 CLOSE FOUND OK

HOUSEKEEPING REQUIRMENTS DEBRIS 01 CLOSE FOUND OK


(5S CONCEPT)
OTHERS (SCAFFOLDING MATERIAL, 01 OPEN (4.5MTR) HP WARM UP VENT
CABLE DRESSING, MATERIAL STACKING) LINE SPOT.

  TOE GUARD AND HAND RAILING  00 CLOSE FOUND OK


 
FLOOR OPENINGS  00 CLOSE FOUND OK
SAFETY RELATED
ABNORMALITIES ACCESS STAIR AND PLATFORMS  00 CLOSE FOUND OK

ABNORMAL INSTALLATIONS  00 CLOSE FOUND OK


AIR, WATER, MATERIAL,OIL ETC  04  OPEN GOVERNING,SARVO
SPILLAGE/LEAKAGE MOTOR,GERNETOR
REAR BEARING , JOP
PERFORMANCE 00 CLOSE FOUND OK
EQUIPMENT RELATED BASIC CONDITION
ABNORMALITIES DESIGN RELATED
OVERVIEW OF OBSERVATIONS - YTD

Oil leakage to be
09 04 05 closed during
shutdown

09 04 05
STATUS OF CURRENT MONTH OBSERVATIONS

Scrap to be
1 Scrap at TG 0 mtr area Yes removed 18/11 Close

Scrap at Aqc-1 zero mtr Scrap to be


2 Yes removed 18/11 Close

Drain clearing
3 CT area drain cleaning Yes for avoiding 25/11 IN PR
water spillages

4 number of Oil leakages at Shutdown


4 Yes Open
9m and 4.5 m

Cleaning of
5 Air tapping provide for Yes Turbine & 15/11 Close
cleaning Auxiliary
Assessors Observation

01 01
02 02
04 00 04

01 00 01

00

00
00

00

08 03 05
PHOTOGRAPHS (Before/After) OF ASSESSORS
OBSERVATION

BEFORE AFTER
Drench cleaning done to flow drain water
BEFORE AFTER
AQC-1 SCRAP REMOVED FROM '0' MTR
TURBINE BUIDING '0' M HOUSEKEEPING
COOLING TOWER AND DM TANK AREA HOUSEKEEPING
TURBINE BUILDING ROOF CONTROL ROOM

DEAERATOR FLOOR