Base Frame/ Cabinet Mounting Major

1. Install the BTS 3900 and make sure that cabinet


bolts are fixed well to the shelter ground .
2. Install the L angels of BTS 3900 cabinet and fix
them well to the wall.
3. Cabinet to be earthed
4. BTS to be labeled.
Need OD cabinet photo
Cabinet bolts

L-Angle
Leveling of BTS Cabinet Major

1. Make sure of cabinet leveling during


installation by using water leveling.
Water leveling
Grounding of BTS Cabinet Critical
External Alarms Cable
Installation and Testing Critical

Alarm
Alarm Name Boolean Number
ID

65033 AC1 1
65034 AC2 2
65045 Main Power Failure 13-14-15-16
65049 Water 17
65050 Temp 18
65051 Smoke 19
65052 Door 20
65056 Humidity 24
DC Cable Installation
With Lugs And Shrinks Critical

Terminals to be
installed in All DC
cables connection
with DC input (need
clear photos)
Ethernet Cable Installation Major
AC Cable Installation With
Terminals Major

1. AC cables installed with


terminals
Separation of Power and
Signal Cables Major

1. leave spacing of 4 cm between cabinet and


shelter wall.
2. At indoor sites install all cables : power , E1 ,

10 cm
earth and alarm cables as shown on the shelter
wall using plastic clips.
3. Spacing between the plastic clips is 10 cm
between each other.

m
4c
4. Install power and earth cables at left side .
5. Install E1 , fiber and alarm cables at right side.
6. Make sure that all cables are in good
arrangement and avoid any crossing.
Separation of Power and
Signal Cables Major
Jumper installed in u shape over
ladder
1. Jumper installed in u shape over ladder.
2. E1 & alarm cable installed on the last hole
near shelter wall.
3. Power cables installed on hole (7)& (8) over
ladder.
E1 & alarm cable installed on the
last hole

Power cables installed on hole 7& 8 over


ladder
Separation of Power and
Signal Cables Major
Power cable from left side
1. Install all cables into good arrangement using white tie
wraps.
2. Install fiber cables from right side and install them into
macaroni flexible (need to discuss).
3. Install the power and earth cables from left side.
4. All cables must have printed labels.

Macaroni Flexible

Fiber and alarm cables from right


side
Roxtec Installation Critical

Roxtec should be closed well not to allow any


dust or liquid to enter the cabinet. All non
used holes should be closed.
In reused cabinet cases, roxtec place should be
sealed using scotch
BTS Configuration Critical

1. BTS configuration as the delivered design sheet


2. E1 performance Check and alarm test done for
cabinet ,IBBS and mini shelter
3. BTS is integrated
4. BTS is clear from alarms
Dummy Boards Are Installed In
BTS If Required Major

1. Don’t leave any unused dummy in the site.


2. Missing Dummy may affect negatively on cabinet
cooling system.
No Faulty Modules Inside BTS
Cabinet For On Air Configuration Critical
Cables Inside The BTS Cabinet
Arrangement Major

1. All cables inside RFC cabinet must installed in good


arrangement : jumpers , power cables and CPRI cables.
2. Jumpers under cabinet must arranged well to avoid any
crossing.
3G Configuration Critical

3G cards should be installed as


per design.
All cards should be working
properly
All cables should be connected
in right ports
No Faulty Modules Inside
3G Cabinet Critical
Cables Inside the 3G
Cabinet Arrangement Major
3G Cabinet Roxtec
Installation Critical

Roxtec should be closed well not to allow any


dust or liquid to enter the cabinet. All non
used holes should be closed.
In reused cabinet cases, roxtec place should be
sealed using scotch
All E1 Cables Connected To
3G Are Labeled Major
Leveling of 3G Cabinet Major

• 1.installation
Make sure of cabinet leveling during
by using water leveling.

Water leveling
Grounding of 3G Cabinet Critical
3G Cabinet Is Working On Same As
Three Phase Power Source 2G
BBU & RRU Fixation Major
BBU & RRU Grounding Major
Thanks and Waiting Us