PERT / CPM Example

The maintenance planner had received a work order pertaining to a 50 hours engine inspection task card for a helicopter with
the following contents as per AMP.
1. Run up the helicopter engine - 4 hours, then drain the engine oil - 12 hours.
2. Prepare the aircraft for inspection by removal of the engine cowlings and other panels - 8 hours
3. Perform Lycoming Service Bulletin 1080 for some maintenance items that will need special attention - 3 hours
4. Perform Lycoming Service Bulletin 366 for carburetor throttle body screw inspection - 1 hour
5. Perform Lycoming Service Bulletin 388 for condition determination exhaust valve and guide - 1 hour
6. Perform Lycoming Service Bulletin 480E for oil and filter change, oil filter screen change , and oil filter and screen content
inspection - 4 hours
7. Return Cowlings and panels - 4 hours
The Client is asking for the total time estimation of the work?
a. Determination of the correct total time?
b. What is the critical path of the work package?
c. Create a work CPM/PERT chart
d. Create a work CPM/PERT Gantt chart