Professional Documents
Culture Documents
Network Scheduling Planning & Control
Network Scheduling Planning & Control
Network Scheduling Planning & Control
- Clearly shows tasks that must precede (precedence) or follow (succeeding) other tasks in a
logical manner
- Clear representation of plan – a powerful tool for planning and controlling project
Why PERT/CPM?
-Prediction of deliverables
-Performance evaluation
-Prediction of deliverables
-Performance evaluation
-Transportation activities
-Computer system
-Library activities
Importance of PERT System
-Reduction in cost
-Saving of time
-Determination of activities
-Elimination of risk in complex activities –
-Flexibility
-Evaluation of alternatives-
-Useful in effective control-
-Useful in decision making
-Useful is research work
Critical path
Those activities which contribute directly to the overall duration of the project constitute critical
activities, the critical activities form a chain running through the network which is called critical path.
Critical event : the slack of an event is the difference between the latest & earliest events time. The
events with zero slack time are called as critical events.
Critical activities : The difference between latest start time & earliest start time of an activity will
indicate amount of time by which the activity can be delayed without affecting the total project
duration. The difference is usually called total float. Activities with 0 total float are called as critical
activities
CPM calculation
Path
A connected sequence of activities leading from the starting event to the ending event
Critical Path
Critical Activities
Those activities which contribute directly to the overall duration of the project constitute critical
activities, the critical activities form a chain running through the network which is called critical path.
Critical event : the slack of an event is the difference between the latest & earliest events time. The
events with zero slack time are called as critical events.
Critical activities : The difference between latest start time & earliest start time of an activity will
indicate amount of time by which the activity can be delayed without affecting the total project
duration. The difference is usually called total float. Activities with 0 total float are called as critical
activities
Benefits of CPM/PERT
-Mathematically simple
-PERT assumes a beta distribution for these time estimates, but the actual distribution may be different
-PERT consistently underestimates the expected project completion time due to alternate paths
becoming critical
Project Crashing
Crashing
Crash time
Crash cost
Goal
-Project network times are not a schedule until resources have been assigned.
- The implicit assumption is that resources will be available in the required amounts when
needed.
- Adding new projects requires making realistic judgments of resource availability and
project durations.
Resource-Constrained Scheduling
-Resource leveling (or smoothing) involves attempting to even out demands on resources by
using slack (delaying noncritical activities) to manage resource utilization.
Kinds of resource
-People
-Materials
-Equipment
-Working Capital
GERT
-It allows probabilistic treatment of both network logic and activity duration estimated.
-The technique was first described in 1966 by Dr. Alan B. Pritsker of Purdue University.