Professional Documents
Culture Documents
Lesson 14-PMP - Process Group View - V3
Lesson 14-PMP - Process Group View - V3
Lesson 14-PMP - Process Group View - V3
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®
The image shows how the project management process is carried out, with the project manager and
team collaborating to produce the project deliverable.
Manage stakeholder
Identify requirements
expectations Project deliverables
Project
sponsor/initiator
Project management
Project inputs
Active communication Balance constraints
with stakeholders (scope, cost, and others)
Project records
The five process groups in project management are initiating, planning, executing, monitoring and
controlling, and closing processes. The image shows how these process groups interact with each
other.
Initiating Process Group Planning Process Group
Monitoring and
Executing Process Group
Controlling Process Group
A project manager is concerned about getting the charter for the project approved.
Project charter sets the beginning of the project where the management has decided in
its favor and is ready to commit resources for it.
Getting the project
charter approved
The project manager and the project team should know the stakeholders and their
requirements, which is the starting point for planning.
Identifying
stakeholders
The activities involved in the planning process and their interactions are depicted in the image.
Project time management Project cost management
Project scope management Plan schedule management
Define activities Plan cost
Plan scope management Sequence activities management
Collect requirements Estimate activity resources Estimate costs
Define scope Estimate activity durations Determine budget
Create WBS Develop schedule
Project communications
management
Project procurement management Project integration Plan communications
Plan procurement
management management
management
Develop project
management
Project human resource
plan
management
Project risk management Plan human resource
management
Plan risk management
Identify risks
Perform qualitative risk analysis
Perform quantitative risk analysis Project quality management Project stakeholder management
Plan risk responses Plan quality Plan stakeholder
management management
Execution is all about performing the plan, that is, producing the deliverables and providing
information on the progress.
Manage
communications
Monitoring is observing and getting data about how things are going within the project. Whereas,
controlling is taking actions to bring things back on track. Monitoring and controlling apply to different
aspects of project management.
Project time management
Project scope management Control schedule Project cost management
Validate scope
Control scope Control costs
Project integration
management
Project procurement Monitor and Project quality management
management control project
Control work and perform Control quality
procurements integrated change
control
Project communications
Project risk management management
Project stakeholder management
Control risks Control
Control stakeholder communications
engagement
Closing processes bring a project or a phase within the project to an orderly conclusion.
● procurement management.
Closing a project or a phase falls under integration management and applies to the overall project.
Study the closing process of process group to answer concept based questions.
Exam Tips
The image shows how the five process groups interact with the different sources of information and
then exchange information internally. Please review the data flow diagram before exam.
a. Initiating
b. Planning
c. Identifying stakeholders
d. Planning stakeholder management
a. Initiating
b. Planning
c. Identifying stakeholders
d. Planning stakeholder management
Answer: c.
Explanation: Identifying stakeholders is the process in which the interested parties are
identified.
a. Initiating
b. Planning
c. Executing
d. Monitoring and controlling
a. Initiating
b. Planning
c. Executing
d. Monitoring and controlling
Answer: d.
Explanation: Change requests are processed in the perform integrated change control
process that is a part of the monitoring and controlling process group.
Answer: c.
Explanation: Conducting procurements is a part of the executing process group where the
basic objective is to finalize the purchase decision and issue agreements and contracts.
Therefore, contracts are the outputs and not inputs to this process.
a. Delivering the agreed scope within the available budget and time
b. Ensuring the best possible quality within the given constraints
c. Ensuring that the organization’s policies are within the legal framework
d. Protecting the project in the midst of uncertainties
a. Delivering the agreed scope within the available budget and time
b. Ensuring the best possible quality within the given constraints
c. Ensuring that the organization’s policies are within the legal framework
d. Protecting the project in the midst of uncertainties
Answer: c.
Explanation: The project manager is expected to perform the actions mentioned in options
a, b, and d. But the project manager is not a legal expert and cannot be held accountable for
ensuring that the organizational policies are within the legal framework.
Answer: a.
Explanation: The processes in a project are carried out in the sequence—Initiating,
planning, executing, monitoring and controlling, and closing.
a. Closing
b. Monitoring and controlling
c. Planning
d. Executing
a. Closing
b. Monitoring and controlling
c. Planning
d. Executing
Answer: b.
Explanation: The deliverables are produced in the executing process group, but they are
validated (accepted or rejected) in the monitoring and controlling process group.
● The project management process starts with an idea being approved by the
Here is a quick
recap of what was project initiator or sponsor. The project manager and the project team then
covered in this understand the requirements and produce the final deliverable.
lesson:
● The five process groups in project management are initiating, planning,
executing, monitoring and controlling, and closing processes.
● The objective of the planning processes is to produce the project
management plan collectively.
● Execution deals with performing the plan to produce the deliverables.
● There are four external sources from which information originates. These
are the organization or enterprise, the customer, the project sponsor or
initiator, and the sellers or suppliers.
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®