STEERING

COMMITTEE
MEETING – 16
FINANCIAL CLOSURE OF PROJECTS : IPDS BADAUN PROJECT

Handover Handover
S.no Project Activity/Billing unit Unit Scope Completed Balance Remark
Submitted Completed

1 Total number of Towns nos 20 20 0 20 20

20 20 0 20
2 Badaun Total number of Substation/R&M nos 20
400 Mtr. Under court case verdict given in
3 Total 33 KV line ckt km 53.53 53.53 0 53.13 53.13 KEI Favour and Execution work done
4 Total 11 KV Line ckt km 34.9 34.9 0 34.9 34.9

Sr. no Description Issue Action Plan

Erection 10 % bill pending due to Nodal JE


transferred and New Nodal JE not
Verification of appointed at site for verifying Erection 10 New Nodel JE appointed 08.10.2019 and Bill process in
this week
Erection 10% Bills % bill .
1. and Closure
FINANCIAL CLOSURE OF PROJECTS : IPDS RAEBARELI PROJECT

Handover Handover
S.no Project Activity/Billing unit Unit Scope Completed Balance Remark
Submitted Completed

9 9 9 9
1 Total number of Towns nos 0
1 1 1 1
2 Total number of Substation nos 0
Raibareilly
13.3 13.3 13.3 13.3
3 Total 33 KV line ckt km 0
Revised Closure submitted as per
22.5 22.5 22.5 22.5
PFC formats
4 Total 11 KV Line ckt km 0

Sr. No Description Issue Action Plan

Closure report PMA reconciling MVVNL material QTY.


Report pending at PMA level
1. submitted as per Already KEI material QTY reconciliation details
(MVVNL )
PFC format submitted.
OPERATIONAL CLOSURE : IPDS UNNAO PROJECT

Sr. No Description Issue Action Plan


Line charging pending from 33
Charging 33 KV SE from MVVNL called JE regarding the same Joint visit
kV Bay ( 132 kV/33 kV
1. Line Bhagwant under process.
Bighapur PSS )
nagar

Charging11 KV
Maurawa 33 kV line breakdown it has to be done first
Line Neotani Line charging pending due to
2. priority after that fault locator machine will be deployed
feeder cable internal fault
at Neotani.
OPERATIONAL CLOSURE : IPDS BARABANKI PROJECT

Description Issue Action Plan

Charging of 33 KV Line Bay to be allotted by client Matter taken up to the DT and after hard efforts and
Fatehpur Bay Not but still not constructed, follow-ups, construction of Bay started dtd. 06/11/19.
1. available fund cleared by MVVNL
Balance material not
Balance Material at
shifting location not As soon as location finalize , material will transfer.
Store
2. finalized
THANK YOU.