Professional Documents
Culture Documents
Ipds Novembder 19
Ipds Novembder 19
COMMITTEE
MEETING – 16
FINANCIAL CLOSURE OF PROJECTS : IPDS BADAUN PROJECT
Handover Handover
S.no Project Activity/Billing unit Unit Scope Completed Balance Remark
Submitted Completed
20 20 0 20
2 Badaun Total number of Substation/R&M nos 20
400 Mtr. Under court case verdict given in
3 Total 33 KV line ckt km 53.53 53.53 0 53.13 53.13 KEI Favour and Execution work done
4 Total 11 KV Line ckt km 34.9 34.9 0 34.9 34.9
Handover Handover
S.no Project Activity/Billing unit Unit Scope Completed Balance Remark
Submitted Completed
9 9 9 9
1 Total number of Towns nos 0
1 1 1 1
2 Total number of Substation nos 0
Raibareilly
13.3 13.3 13.3 13.3
3 Total 33 KV line ckt km 0
Revised Closure submitted as per
22.5 22.5 22.5 22.5
PFC formats
4 Total 11 KV Line ckt km 0
Charging11 KV
Maurawa 33 kV line breakdown it has to be done first
Line Neotani Line charging pending due to
2. priority after that fault locator machine will be deployed
feeder cable internal fault
at Neotani.
OPERATIONAL CLOSURE : IPDS BARABANKI PROJECT
Charging of 33 KV Line Bay to be allotted by client Matter taken up to the DT and after hard efforts and
Fatehpur Bay Not but still not constructed, follow-ups, construction of Bay started dtd. 06/11/19.
1. available fund cleared by MVVNL
Balance material not
Balance Material at
shifting location not As soon as location finalize , material will transfer.
Store
2. finalized
THANK YOU.