Professional Documents
Culture Documents
Abes Engineering College Department of Civil Engineering: Construction Technology & Management (NCE-603)
Abes Engineering College Department of Civil Engineering: Construction Technology & Management (NCE-603)
DEPARTMENT OF CIVIL
ENGINEERING
Prepared By
Amit Bajaj
SYLLABUS
Network Techniques: Bar Chart, Mile stone chart, work
break down structure, and preparation of networks.
Network techniques like PERT and CPM in construction
Management.
Project Monitoring and resource allocations through
network techniques.
How to draw a Gantt chart with more complicated predecessors.mp4
PROBLEM-1
Draw a bar chart and compute the total duration of the project
from the data given below :
Task (1) 5 days (Duration)
Task (2) 3 days
Task (3) 7 days
Task (4) 2 days
Task (5) 4 days
Task (6) 7 days
Task (1) and (4) will be started together. Task (2) will start
after completion of Task (3) and Task (3) will take place after
Task (1). Task (5) and (6) will be taken up together but only
after completion of Task (3).
PROBLEM-2
Draw a bar chart and compute the total duration of project
from project data given below:
Task A 6 days
Task B 2 days
Task C 8 days
Task D 3 days
Task E 4 days
Task F 7 days
Task A& D will be started together. Task B will start after
completion of Task C and Task C will take place after Task
A. Task E & F will start together but only after the
completion of Task C.
WBS- WORK BREAKDOWN STRUCTURE
A Work Breakdown Structure (WBS) is a decomposition of all the
work necessary to complete a project.
All those activities, which must be completed before the start of activity
under consideration, are called its predecessor activities.
All those activities, which have to follow the activity under consideration,
are called its successor activities.
Interrelationships:
i. Parallel activities or concurrent activities:
y f itt ings 20
nitar
Fix sa
10
Fix e
lectr
i cal f
it tings
30
Looping or Cycling:
EVENTS OR NODES
ii. Events or Nodes: An event is denoted by a circle
i where, i={1,2,3,4…. and so on}
shape of node may be used as
The starting event is always one event, irrespective of the number of starting
activities. This event signifies the commencement status of the project
The numbering of events starts with the first event and progressively
moves from the left to the right of the network diagram.
3.Floats
Time Calculation:
EOT LOT
A
i j
tij
CALCULATION OF EOT & LOT
FORWARD PASS
BACKWARD PASS
EXAMPLE-2
4
8
2
5 7
6
2 2
3
EXAMPLE-3
ACTIVITY TIMES AND FLOATS
D
20 21
4
10 10 14 14
D
20 21
4
FREE FLOAT
D E
i j k
4
INDEPENDENT FLOAT
10 12 18 20
C D E
i j
4
INTERFERING FLOAT
Head Event Slack
Critical: TF=0
3 – 6 – 10
Normal Distribution Curve:
BETA DISTRIBUTION CURVE
DETERMINISTIC CURVE?????
Versus
1. THE EXPECTED TIME (TE) OF AN ACTIVITY
Job to tm tp
A 4 6 11
B 5 10 12
C 4 6 8
CRITICAL PATH ANALYSIS OF PERT NETWORK
1. Calculate te for all activities.
2. Calculate EOT and LOT.
3. Find the longest path having least slack
CENTRAL LIMIT THEOREM
If there are n activities lying along the critical path each
having its own Beta distribution with expected mean time
te1, te2, te3…..ten.
Standard deviation as σ1, σ2, σ3…..σn.
Variance as ν1, ν2, ν3,...νn respectively.
If Z < 0 = chance of completing the project in given time is less than 50%.
STANDARD NORMAL DISTRIBUTION
TABLE